LEISURE CENTRE CONTRACT MANAGEMENT AND INVESTMENTS

Agreed Scrutiny 1 paper

Overview and Scrutiny Committee - Services agreed this item on Monday 21 March 2022. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

It was agreed to set up a Task and Finish Group to monitor progress. Members nominated were: Cllrs M Foryszewski, J Else and M Wicks plus one member of the Resources O&S to be nominated. Cllr Else also enquired about the extension of car park set out on page 207. She commented that this had been going on for a long time. Kelvin Mills advised that they were just waiting for Secretary of State approval.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Overview and Scrutiny Committee - Services

WAVERLEY BOROUGH COUNCIL

OVERVIEW & SCRUTINY

MARCH 2022

Title: Leisure Management Contract update

Portfolio Holder: Cllr Kika Mirylees – Health, Wellbeing, Parks and Leisure

Head of Service: Kelvin Mills, Head of Commercial Services

1 Leisure Management Contract

Current position

1.1The current leisure management contract, for our five leisure centres, expires on 30 June 2023 and the Council needs a new contractual arrangement to be in place for the 1 July 2023.

1.2A Leisure Management Contract tender Project Working Group (PWG) has been established to maximise the tendering opportunity for the Council and ensure that the leisure portfolio is in the best possible position to deliver value for money for the council. The group consists of representatives from Leisure, Finance, Procurement and Legal.

1.3In September consultants, Max Associates, were appointed to produce an options appraisal of alternate management arrangements.

Max Associates Options Appraisal headlines

1.4Management options reviewed included:  In house provision  Setting up a company under Teckal procurement rules  Setting up a charitable trust, and  External leisure provider.

1.5The review centred on; a) The value of joint procurement for the two independent leisure contracts for WBC and GBC b) The value of one joint contract for all of the leisure facilities within Waverley and Guildford

1.6The options appraisal included detailed knowledge and experience of the leisure industry and identified the specific positives and negatives of each option (including the time related risks of going to market). 1.7 The Draft Management Appraisal conclusions are;

1.7.1 Across all options the external contractor model has scored highest and is considered best able to deliver against the Councils’ priorities set out in the evaluation criteria.

1.7.2 The in-house, Local Authority Trading Company (LATC) and Not for Profit Distributing Organisation (NPDO) options have all scored considerably lower across both Councils due to the additional financial and operational risk they place on the Councils.

1.7.3 The NPDO option would also require the Councils to go through a procurement process where the newly established NPDO would have to compete against established operators. Due to the lack of trading history it is unlikely that a NPDO would be successful in a procurement process and therefore it is recommended that the Councils do not progress the NPDO option.

1.7.4 The leisure centre portfolios for each Council are very different. Waverley Borough Council facilities are typical community leisure centres with a standard facility mix. Guildford Spectrum is a significant facility and destination venue, with a facility mix that some operators have little experience of managing. The size of the building brings its own maintenance and lifecycle issues and therefore higher level of risk than standard leisure centres.

1.7.5 Due to the nature of Guildford Spectrum and its unique facility mix it is anticipated that whilst there would be interest from the largest national operators, overall interest could be limited due to;  Guildford Spectrum presenting a significant operational and financial risk to operators that some will not be willing to take as they recover from the Covid19 pandemic.  Guildford Spectrum is likely to require a different contract specification compared to other leisure centres due to the facility mix and activities available. It also has different priorities being a destination venue with a significant commercial offer.  There are only a few operators that have the experience of delivering large scale investment projects, therefore if investment into Guildford Spectrum is required as part of the tender (even if funded by the Council), then this is likely to impact the operators that are able to bid for the contract.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LEISURE CENTRE CONTRACT MANAGEMENT AND INVESTMENTSReport 268 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
KD
Councillor Kevin DeanusChair, apologies
PM
Councillor Peter MarriottVice Chair, present
CC
Councillor Carole CockburnCommittee Member, present
CB
Councillor Christine BakerCommittee Member, apologies
MD
Councillor Martin D'ArcyCommittee Member, present
SD
Councillor Sally DicksonCommittee Member, present
JE
Councillor Jenny ElseCommittee Member, present
MF
Councillor Mary ForyszewskiCommittee Member, present
RR
Councillor Ruth ReedCommittee Member, present
PT
Councillor Philip TownsendCommittee Member, present
MW
Councillor Michaela WicksCommittee Member, present
RS
Councillor Richard SeaborneSubstitute, in attendance

All 14 on the meeting page

On this subject at Waverley

Search all
  1. LEISURE CENTRE CONTRACT MANAGEMENT AND INVESTMENTSThis decision
  2. Cranleigh Leisure CentreApproved
  3. Cranleigh Leisure CentreApproved
  4. Cranleigh Leisure Centre New BuildApproved
  5. Wa/2024/02091 - waverley borough council cranleigh leisure centre village way cranleigh gu6 8afDecided
  6. Farnham Leisure Centre decarbonisationApproved

More from Waverley Overview and Scrutiny Committee - Services

All decisions
MeetingDecisionOutcome
15 Sep 2025 Committee Work ProgrammeRESOLVED that the be noted. Noted Open
15 Sep 2025 The Issues and Options Consultation for the new Waverley Local PlanIt was agreed that references should clarify its age and limited relevance, with consultation questions framed to gat... Agreed Open
15 Sep 2025 The Surrey Hills National Landscape Management Plan 2025 to 2030It was agreed that Part 4 (Policy Framework) was of particular importance to Waverley Borough Council as a local plan... Agreed Open
15 Sep 2025 Proposed Revised Overview & Scrutiny Committee ArrangementsIt was agreed that such an arrangement was both necessary and logical given the increasing extent of joint working. H... Agreed Open
23 Jun 2025 Committee Work ProgrammeThat the Committee Work Programme be noted. Noted Open