Subject to there being a successful application by the Council in obtaining grant from the Social Housing Decarbonisation Fund, The Executive RESOLVED to: I. Approve, in consultation with the Borough Solicitor , delegation of authority to the Executive Head of Housing Services to: a. Award directly a contract to E.ON ... EXE 140/23
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
To appoint a contractor to undertake the energy efficiency work in the Council’s homes. 1. Executive Summary
In January 2024, the Council made a bid for a grant from the Social Housing Decarbonisation Fund: Wave 2.2 competition (SHDF). In the bid E.ON were named as the partner to deliver the energy efficiency works.
This report is seeking delegation of authority to the Executive Head of Housing Services, in consultation with the Borough Solicitor, to directly award a works contract to E.ON for the value of £560K if the Council is successful in its bid to the SHDF. 2. Recommendation to Executive
That, subject to there being a successful application by the Council in obtaining grant from the Social Housing Decarbonisation Fund, the Executive:
1. approves, in consultation with the Borough Solicitor, delegation of authority to the Executive Head of Housing Services to:
(a) directly award a contract to E.ON to deliver energy efficiency works to council homes through a public sector framework (Fusion 21) for the value of £560K.
(b) enter into a Grant Funding Agreement (GFA), Grant Offer Letter (GOL), Data Sharing Agreement (DSA) and associated documents with the Department of Energy, Security and Net Zero (DESNZ).
2. approves expenditure of £280,000 as allocated by the Council as part of the match funding.
3. Reason(s) for Recommendation:
3.1The Council has made a bid to secure 50/50 match funding from the Government under the Social Housing Decarbonisation Fund – Wave 2.2 to deliver fabric first decarbonisation measures to improve the energy performance of at least 100 of the Council’s poorest energy efficiency performing homes.
3.2In November 2022 an unsuccessful application was made in collaboration with Surrey County Council to secure SHDF Wave 2.1 grant.
3.3In November 2023 the Department for Energy Security and Net Zero (DESNZ) announced the availability of a further £80m grant funding as a top up to SHDF Wave 2.1 for eligible providers to deliver home energy efficiency measures. 3.4 The announcement of the fund was made on 24th November 2023 with a 19th January 2024 closing date, now extended to 31st January 2024. The allocation decision is due to be made in March 2024.
3.5The works must be delivered by March 2025 to receive the 50/50 match funding and the improved homes must reach Energy Performance Certificate (EPC) Band C.
3.6The Council has allocated £280K for this project / bid as 50% of the costs are to be covered by the applicant.
3.7Applicants are expected to have a good understanding of PAS 2030 (Publicity Available Specification for the installation of energy efficiency measures) requirements prior to submitting a bid.
3.8Bidders must also be able to evidence they have identified a delivery partner to undertake the work. The contractor needs to be TrustMark Registered PAS 2030:2023.
3.9All projects must be compliant with PAS 2030.
3.10Grant recipients must have a system in place across their delivery teams to ensure they can fulfil the monitoring and reporting requirements as outlined in the GFA with DESNZ.
3.11The administration and ancillary costs should be no more than 15% of total grant funding.
3.12Officers collaborated with the energy provider E.ON to collate the data required for the application.
3.13If successful in the bid, officers are recommending a direct award of work to E.ON. Via Lot 1 Decarbonisation Framework, Fusion 21 based on the following reasons:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.