CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council
Executive, Tuesday 10 February 2026 at 7.00pm

Supplementary budget request for Warm Homes Social Housing Fund Wave 3

Approved Executive 1 paper

AI summaryWaverley Executive recommends Full Council approve a £510,685.70 supplementary budget increase for the Warm Homes Social Housing Fund Wave 3, to reflect grant money already secured from the Department for Energy Security and Net Zero.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApprove £510,685.70 for FY25/26 Warm Homes Wave 3
Money£510,685.70Supplementary estimate for FY25/26, funded by Wave 3 grant
What happens nextFull Council to consider approvalRequired because supplementary estimate exceeds £250,000 threshold
Who it affectsCouncil tenants in social housingEnergy efficiency upgrades to council-owned homes continue

What was decided

The Executive agreed to ask Full Council to approve a supplementary estimate increase of £510,685.70 for FY25/26 for the Warm Homes: Social Housing Fund Wave 3, funded from the Wave 3 grant. Report 2.1, P6

This request is needed because the current approved budget of £1,073,000 only reflects the co-funding amount, and the £608,291 grant for FY25/26 has now been secured. Report 3.2, 3.3

Why

The Council made a successful bid in November 2024 and was awarded £2,097,557 from the Department for Energy Security and Net Zero over three years, with Waverley contributing £1,000,000 per year in co-funding. Report 1.1, 3.1

A contractor has been procured and the programme is in delivery stage, so the budget must be increased to reflect the grant secured and enable the council to meet its contractual obligations. Report 3.4

What happens next

Finance to increase the Warm Homes: Social Housing Fund Wave 3 budget by £510,685.70 for FY25/26 once Full Council approval is obtained. Report 4.1

The Housing Service to raise a purchase order for the additional amount under the existing contract, and delivery of the programme to continue. Report 4.2

The money

  • £510,685.70 Supplementary estimate increase requested for FY25/26, funded by Wave 3 grant Report P6, 3.2
  • £2,097,557 Total grant awarded by Department for Energy Security and Net Zero over three years Report 1.1, 3.1
  • £1,000,000 Waverley co-funding contribution per annum for three years Report 1.1, 1.2
  • £3,000,000 Total programme value over three years (grant plus co-funding) Report 1.1
  • £1,073,000 Currently approved budget for FY25/26, covering co-funding only Report 3.2
  • £608,291 Secured grant amount for FY25/26 Report 3.2
  • £250,000.00 Threshold above which supplementary estimates require Full Council approval Report P37

Options considered

  • Rejected: Do nothing. Risk to contractor and funder relationships; contract and Grant Funding Agreement already in place Report 11.1, P33, P34
  • Chosen: Approve the supplementary estimate recommendation. Enables delivery against grant funder and contractor contracts and supports decarbonisation of council homes Report P35

Implications

  • Financial: Capital budget for Wave 3 in FY25/26 increases by £510,685.70, fully funded by external grant so no net cost to the council. Report 3.2, 6.2
  • Legal: Full Council approval required under Financial Procedure Rules because the supplementary estimate exceeds £250,000. Report P37
  • Equalities: No equality and diversity implications arising directly from this report; Public Sector Equality Duty considered. Report 12.3, P44
  • Climate: Supports the Council's Net Zero by 2030 commitment and Housing Asset Management Strategy by decarbonising council-owned homes. Report 7.1, 7.2, 12.4, 12.6, P48, P49, P50
  • Risk: Strategic risks to business continuity and HRA finances; operational risks to supplier and grant funder relationships, mitigated by approving the budget increase. Report 10.1, 10.3, P29

Who and where

  • Tenants in Waverley's council-owned social housing receiving energy efficiency upgrades Report 6.1, P48, P49
  • Waverley Borough Council Housing Revenue Account finances Report 10.1, P29
  • West Surrey reorganisation, as the three-year programme (2025-2028) will continue as the council joins West Surrey Report 8.1, P25

Timeline

  • November 2024: Council submitted successful bid and Executive approved procurement route and contractor Report 1.1, 1.3
  • February 2025: Council awarded £2,097,557 grant from the Department for Energy Security and Net Zero Report 1.1
  • March 2025: Full Council approved £1,000,000 per annum co-funding for three years as part of 25/26 budget Report 1.2, 15.2
  • 2025 to 2028: Three-year Warm Homes: Social Housing Fund Wave 3 delivery period Report 8.1, P25
  • February 2026: Capital bids for energy efficiency projects to be presented to Council for approval
  • 2030: Council target to achieve Net Zero Report 7.1
  • 2026-02-10: Executive decision to recommend supplementary budget increase to Full Council

Plain English for the jargon

  • DESNZ: Department for Energy Security and Net Zero, the government funder of the grant
  • Supplementary estimate: An addition to the approved budget for the financial year, required when extra spending is needed beyond what was originally agreed
  • HRA: Housing Revenue Account, the ring-fenced account that holds income and spending on council housing
  • PO: Purchase Order, a formal instruction to a supplier to provide goods or services
  • Co-funding: Money the council itself contributes alongside the external grant to fund the programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 30/25

Resolved

RESOLVED that: It was requested that the Council: · Approve a supplementary estimate increase of £510,685.70 for FY25/26 for the Warm Homes: Social Housing Fund Wave 3, to be funded from Warm Homes: Social Housing Fund Wave 3 grant.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1In November 2024, the Council made a successful bid to the Warm Homes: Social Housing Fund Wave 3. In February 2025, the Council was awarded £2,097,557 over 3 years from the Department for Energy Security and Net Zero (DESNZ) and is contributing co- funding of £1,000,000 per annum to a total of £3,000,000 over the 3 year programme. The Wave 3 programme is currently in delivery phase.

1.2£1,000,000 contribution per annum for 3 years by Waverley BC was approved by Full Council as part of the 25/26 budget papers in March 2025.

1.3Executive approved the procurement route and to enter into contract with a contractor to deliver the energy efficiency works in November 2024.

1.4Since successfully being awarded the grant, it is requested that the approved budget for the Wave 3 programme is increased to reflect this. As such this report is being written to seek approval from the Executive and Council increase for a supplementary estimate increase of £510,685.70 for FY25/26 for the Warm Homes: Social Housing Fund Wave 3, due to successfully receipt of grant.

Recommendations

2.1That the Executive requests the Full Council to resolve, and that Full Council resolves, to:

2.1.1 Approve a supplementary estimate increase of £510,685.70 for FY25/26 for the Warm Homes: Social Housing Fund Wave 3, to be funded from Warm Homes: Social Housing Fund Wave 3 grant .

3 Reason(s) for recommendation:

3.1The council made a successful bid to the Warm Homes: Social Housing Fund and has secured £2,097,557 from the Department of Energy Security and Net Zero, over the next three years.

2 Supplementary budget request for Warm Homes: Social Housing Fund Wave 3

3.2The budget currently approved for FY25/26 is £1,073,000 and accounts for the approved anticipated co-funding amount only for the project. The secured grant for FY25/26 is £608,291. Finalising the project programme and budget, following grant allocation, it is concluded that an additional budget estimate of £510,685.70 is required to deliver against the contracted programme.

3.3Since the grant has been successfully secured, officers are requesting for the budget to be increased to account for both the cofounding and grant amount allocated to FY25/26.

3.4A contractor has been procured and the programme is in delivery stage and on track to delivery against the grant funding requirements for FY25/26.

4 Next steps

4.1Finance to increase the Warm Homes: Social Housing Fund Wave 3 budget by £510,685.70 for FY25/26.

4.2Housing Service to raise a PO for the additional amount inline with the contract with the contractor for FY25/26. 4.3 Delivery of programme to continue.

5 Exemption from publication

5.1All of this report is not exempt from publication.

6 Background and Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Supplementary budget request for Warm Homes Social Housing Fund Wave 3Supplementary 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Supplementary budget request for Warm Homes Social Housing Fund Wave 3This decision
  2. Supplementary budget request for Warm Homes: Social Housing Fund Wave 3Approved
  3. New Affordable Housing Delivery, Chiddingfold – Supplementary Budget AllocationApproved
  4. New Affordable Housing Delivery - Chiddingfold - Supplementary Budget AllocationApproved
  5. Budget management - request for supplementary estimate regarding injunction at pollingfold place, rudgwick, horshamApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies