Resolved
The Executive
Executive decided this item on Tuesday 5 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive
Waverley Borough Council Report to: Executive Date: 5 March 2024 Ward(s) affected: Farnham Castle Ward Report of Director: Dawn Hudd, Strategic Director, Place Author: Debbie Smith, Development Programme Manager Tel: 01483 523443 Email: [email protected] Executive Portfolio Holders responsible: Cllr Tony Fairclough Tel: 01483 523 443 Email: [email protected] Report Status: Part Exempt Key Decision: No
Brightwells Yard Development Project 1. Executive Summary 1.1 This report sets out the options available to the Council in response to a request from Crest Nicholson (Crest) to change some aspects of the Development Agreement (DA) the Council has with them for the Brightwells Yard development in Farnham (the Development).
2. Recommendation to Executive 2.1. That the terms of the Brightwells Yard Development Agreement (“the DA” further defined below) are varied as follows:
i. The ultimate long-stop date for Practical Completion to change from 15 August 2024 to 28 February 2025. ii. Developer obligations to deliver the Borelli Bridge (“the Bridge”) be removed from the DA and a separate agreement entered into obliging the developer to deliver the bridge by 31 August 2025. iii. That the full and final set of drawings, plans and specifications comprising the Works and agreed between the parties since the Development began, be appended to the Development Agreement thereby superseding the original documents included. iv. That the previous form of Car Park Underlease be removed and replaced with a new revised version of the Car Park Underlease which takes account of agreed changes to the service charge provisions which WBC’s officers have in principle agreed. v. Authority be delegated to the Strategic Director - Place, to settle the terms upon which these changes will be documented and to authorise execution of any deeds and documents required to give effect to those changes in consultation with the Portfolio Holder for Finance, Assets and Property, the Portfolio Holder for Brightwells and Executive Head of Legal and Democratic Services.
3. Reason(s) for Recommendation: 3.1. The developer, Crest Nicholson, has approached the Council and explained that there are certain delivery complications which will mean that they will be unable to deliver the scheme in accordance with the original timeline. They have therefore asked for more time to deliver the scheme. The impact of this will have implications for those businesses who want to invest time and money into the development and this is expanded upon in paragraph 3.3 below. For the reasons below officers consider it to be in the best interests of the Council to agree to delay completion of the scheme.
3.2Crest is committed to (and close to) building out the remainder of the development and have provided a programme of works to indicate the development’s completion.
3.3Tenants under agreements for lease for commercial units at the development need comfort that their lease position is secure, which an extension to the long- stop date will support. Similarly prospective tenants who may be considering taking a unit would also require more certainty. Unless the long-stop date is extended, the Council would have the option to terminate the DA and thereby undermine the leasing structure for the site (and remove Crest as developer). A new long-stop date therefore removes this threat and provide certainty to leaseholders, Crest, the Council and Surrey County Council.
3.4Removing the completion of the Bridge from what is required for the overall Development to reach Practical Completion will allow the scheme to open and potential tenants to take occupation earlier. This will support the regeneration of the area and bring the development to life.
3.5The tidying up of plans referred to in the DA to allow the most recent and as built drawings to be reflected and allow for a smooth Practical Completion process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Brightwells Yard Development ProjectReport | 507 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.