The Executive RESOLVED to: I. Go to tender for the main contractor for the repair contract through a competitive tender process with the brickwork conservator, Simpson Brickwork Conservation Limited being a named sub-contractor. II. Issue the invitation to tender prior to obtaining listed building consent. III. Delegate authority to the ... EXE 149/23
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1At a Full Council meeting on 18 July 2023 Members agreed to accept the terms of a capital grant from Arts Council England’s MEND fund to deliver a programme of essential conservation and repairs to the brickwork façade of the Grade 1 Listed Museum of Farnham. Members also resolved to fund a potential budget gap of up to £275,000 if efforts to obtain additional external funding are unsuccessful or the costs of completing the project are higher than estimated.
1.2This report updates Members on the status of the MEND project and asks the Executive for approval to issue a tender for a main contractor for the conservation and repair contract.
2. Recommendation to Executive
That the Executive approves:
I. to go to tender for the main contractor for the repair contract through a competitive tender process with the brickwork conservator, Simpson Brickwork Conservation Limited being a named sub-contractor. II. to issue the invitation to tender prior to obtaining listed building consent. III. a delegation of authority to the Strategic Director for Community Wellbeing in consultation with the Joint Head of Legal and Democratic Support Services to award the contract to the successful bidder. This will be dependent upon listed building consent being granted prior to entering a contract with the recommended contractor.
3. Reason(s) for Recommendation:
3.1Details of the tender for a main contractor
The Council intends to select the main contractor for the repair contract through a competitive tender process with Simpson Brickwork Conservation Limited being a named sub-contractor within the tender package. The Council will enter a JCT Intermediate Building Contract with Contractor Design Portion 2016 with the successful main contractor and the named specialist brickwork conservator being employed by the successful bidder. The price for the specialist brickwork package will be negotiated with Simpson Brickwork Conservation Limited in advance, so that the agreed sum can be included as a fixed cost within the tender. The overall contract value is estimated to be approximately £900,000 plus VAT which includes the cost of the brickwork conservator and the procurement of the handmade bricks.
3.2The Lead Conservation Consultant for the project recommends a single action tender for the specialist brickwork conservator based on his extensive knowledge of the UK’s heritage industry.
3.3Firstly, procuring a brickwork conservator to complete the façade repair is problematic as there is an acute national shortage of suitably qualified brickwork conservators who have experience of large-scale historic brickwork repair. Buildings with highly embellished brickwork facades such as Willmer House are rare, hence the grade 1 listing and consequently there is little demand for this type of work. Simpson Brickwork Conservation is the only company in the UK which is large enough and has sufficient skill, capacity, and experience in-house to deliver a contract of this complexity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.