ItemEXE 107/24

Resolved

The Executive APPROVES : i) The allocation of a £99,985 from the New Development Impact Reserve to increase the pre-development budget to cover the costs as set out. This budget allocation will be included within the financial viability appraisal that will accompany the business case and full project budget request ... EXE 107/24
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

This report seeks approval for a supplementary pre-development budget to cover the costs associated with bringing forward new affordable housing at 69 High Street, Godalming.

The Capital Projects Team have commissioned reports and surveys that have informed both the delivery of the commercial and residential elements of the development. These costs have been funded through the budget secured from the Property Investment Reserve.

There is a now a requirement to apportion these costs between the General Fund (GF) and Housing Revenue Account (HRA) ahead of year end 2024/25. This will ensure that the two different schemes for 69 High Street are charged against the appropriate budget (general fund or HRA).

The HRA Pre-development Budget funds pre-development costs for example, commissioning of surveys and reports however due to spend and commitments already made to bring forward other affordable housing projects there is insufficient budget and therefore a supplementary budget request is being made for £99,985.

Recommendation to Executive

That the Executive approves:

i) The allocation of a £99,985 from the New Development Impact Reserve to increase the pre-development budget to cover the costs as set out above. This budget allocation will be included within the financial viability appraisal that will accompany the business case and full project budget request for the new build scheme when it is bought forward.

3. Reason(s) for Recommendation:

3.1To facilitate allocation of supplementary pre-development budget from the New Development Impact Reserve.

4. Exemption from publication 4.1 Open report

Purpose of report

5.1To seek approval from the Executive to transfer £99,985 from the New Development Impact Reserve to the pre-development budget to fund the HRA proportion of the commissioned surveys and reports relating to 69 High Street, Godalming, that will inform the design development of a new affordable housing scheme to the rear of the site.

6. Strategic Priorities

6.1The redevelopment of 69 High Street for housing meets the Strategic Corporate Priorities of the Council. It will bring forward ‘decent and affordable homes’ through the demolition of existing large retail unit to allow for homes to the rear of the site, which will be built and retained by the Council.

6.2It will also support the priority of ‘a more prosperous borough’ through the delivery of a new, smaller, and more appropriate unit with commercial tenant in place and support the local economy and high street.

7. Background 7.1 In February 2022, Full Council approved the acquisition of 69 High Street, Godalming as a General Fund mixed use asset to support the Council’s aspirations contained with the Corporate Strategy 2020-25, including:

 To bring forward affordable housing, in this case in Godalming town centre and  To deliver a positive contribution to Godalming by preserving the integrity of the high street.

7.2The purchase was completed in May 2022. Subsequently officers prepared a business case which was considered, and the recommendations approved by Full Council on 29 August 2023.

Reports and surveys have been procured to inform and secure planning permission for the commercial element of the scheme. A lease for the new retail area has been signed and following contract procedure rules officers are able to enter a PCSA with a preferred contractor.

7.3A design team has also been appointed to develop the affordable housing residential scheme to the rear of the site using HRA Pre- development budget.

8. Consultations

8.1This paper was discussed at Executive Briefing on 25 February 2025. 9. Key Risks

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Affordable Housing Delivery: GodalmingSupplementary 480 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. New Affordable Housing Delivery - GodalmingThis decision
  2. New Affordable Housing Delivery, Chiddingfold – Supplementary Budget AllocationApproved
  3. New Affordable Housing Delivery - Chiddingfold - Supplementary Budget AllocationApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies