CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council
Executive, Tuesday 13 January 2026 at 7.00pm

New Affordable Housing Delivery - Chiddingfold - Supplementary Budget Allocation

Approved Executive 1 paper

AI summaryWaverley Executive recommends £481,880 extra budget, plus £150,000 virement, to complete 24 affordable homes across five sites in Chiddingfold, with Full Council to decide on 27 January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSupplementary budget and virement endorsed
Money£481,880 supplementaryPlus £150,000 virement from contingency
What happens nextFull Council 27 January 2026Then implement contract variations
Who it affectsChiddingfold and future tenantsFive sites, 24 remaining homes

What was decided

The Executive endorsed the report and recommended Full Council approve a supplementary budget of £481,880 to complete the homes across the five Chiddingfold sites. Report 2.1, P2, P3

The Executive also approved a virement of £150,000 from the existing New Development Contingency budget, subject to Full Council backing. Report P4, P5

Authority was delegated to the Strategic Director of Economy, Planning and Place to vary the contract with Feltham Construction Limited and related legal agreements. Report P5, P6, P72

Why

A supplementary budget is needed to deliver the remaining 24 homes and meet the Council's contractual obligations under the construction contract. Report 3.1, 6.14

The Council's Employer's Agent reviewed the contractor's representations and confirmed that the increases in cost and time are justified. Report 3.2

Cost increases stem from utility company delays (notably Thames Water), unforeseen builders' works, adverse weather, and Extension of Time claims, with the original contractor W Stirland going into administration in September 2022 adding further pressure. Report 6.3, 6.6, 6.7, 6.8, P31

What happens next

Full Council will consider the recommendations on 27 January 2026; if approved, officers will implement contract variations and legal agreements to enable completion. Report 4.1, P12

Discussions continue with Homes England over Affordable Homes Programme grant, which if secured would replace the need for borrowing and shorten payback from 45 to 41 years. Report P6, P8, P68

The money

  • £481,880 Supplementary budget to complete the five Chiddingfold sites Report P2
  • £241,990 Funded from Commuted Sums Report P3, P67
  • £239,891 Funded from borrowing (decision wording) Report P3
  • £239,890 Additional borrowing (financial implications text) Report P67
  • £150,000 Virement from existing New Development Contingency budget Report P4, P67
  • £631,880 Total additional budget needed, combining supplementary and virement Report P67
  • £9,305,046 Original budget approved by Full Council on 13 December 2022 Report P66

Options considered

  • Rejected: Option 1: Do nothing. Council could not finance the scheme, would breach contract, and would face damages claims, reputational risk and deteriorating sites. Report 11.1, P59
  • Rejected: Option 2: Reduce overall scope to save costs. Unlikely to yield sufficient savings at this stage and would risk lower-quality homes and redesign costs outweighing savings. Report 11.2
  • Rejected: Option 3: Sell one or two homes to reduce supplementary budget. Would reduce rental income, cut affordable homes and fall short of the Chiddingfold Neighbourhood Plan target. Report 11.3
  • Chosen: Option 4: Approve the recommendations and complete the scheme (Do most). Allows full completion, delivers approved benefits, protects reputation, and uses a mix of internal funds and borrowing. Report 11.4, P63, P64

Implications

  • Financial: Total additional funding of £631,880 required; Homes England grant could replace the £239,890 borrowing element and cut payback from 45 to 41 years. Report P67, P68
  • Legal: Supplementary budget exceeds £250,000 so Full Council approval is required under Financial Procedure Rules clause 6.3; legal services will vary the contract. Report P71, P72
  • Equalities: Public Sector Equality Duty considered; officers concluded there are no equality and diversity implications arising directly from this report. Report P74, P75, P76, P77
  • Climate: Scheme includes air-source heat pumps, enhanced insulation, PV solar panels, SuDS drainage and above-average construction waste recycling, supporting the Council's carbon-neutral 2030 aim. Report P43, 7.3, P81, P82
  • Risk: Key risks include further utility delays, abortive costs until the budget is approved, and reputational damage from unfinished homes and lost rental income. Report 10.3, 10.4, 10.5, 10.6, P53
  • Staffing: Existing Housing Development Manager, Development Officer, Employer's Agent, Clerk of Works and CDM Client Advisor are in place; no additional resource required. Report P79

Who and where

  • Future tenants and buyers of the 24 remaining homes in Chiddingfold Report 3.1, 6.14, P19
  • Residents of Chiddingfold and the wider Waverley borough awaiting affordable housing Report 7.2, 7.4, P45
  • Feltham Construction Limited (main contractor) and its supply chain Report 6.5, P5, P6
  • The successor West Surrey unitary authority, which will inherit the 26 new homes on its asset register after vesting Report 8.2
  • Thames Water and UK Power Networks as statutory utility providers whose delays drove cost and programme overruns Report 6.6, 6.11, 6.12, 10.3

Timeline

  • September 2022: Original contractor W Stirland went into administration before signing the JCT Contract Report 6.3
  • 29 November 2022: Executive considered the report and business cases for each Chiddingfold site Report 6.2, 16.1, P90
  • 13 December 2022: Full Council approved the original £9,305,046 budget for the five Chiddingfold sites Report 6.2, P66, 16.1, P90
  • March 2023: Council entered into a Pre-Construction Services Agreement with Feltham Construction Limited Report 6.5
  • October 2023: JCT Design & Build Contract signed with Feltham Construction Limited Report 6.5
  • April 2024: Work commenced on site at Turners Mead Report 6.6
  • April 2025: Two Turners Mead homes reached practical completion and are now occupied Report 6.6
  • 13 January 2026: Executive endorsed the report and recommended the supplementary budget to Full Council Report 2.1, P2
  • 27 January 2026: Full Council scheduled to decide on the supplementary budget allocation Report 4.1, P12
  • March 2026: Anticipated practical completion of the remaining four sites (24 homes) Report 6.6, 10.4

Plain English for the jargon

  • Commuted Sums: Payments made by developers to a council in lieu of carrying out affordable housing or infrastructure works on site, used by the council to provide housing or services.
  • Extension of Time (EoT): A contractual claim allowing a contractor extra time to complete works without penalty when delays are caused by matters outside their control.
  • JCT Design & Build Contract: A standard form of building contract published by the Joint Contracts Tribunal, under which the contractor designs and constructs the works.
  • PCSA (Pre-Construction Services Agreement): An early-stage contract under which a contractor is appointed to carry out design, planning and pricing work before a main construction contract is signed.
  • Virement: The transfer of budget from one spending head to another within a council's approved budget, allowed under Financial Procedure Rules.
  • SAP rating: Standard Assessment Procedure, the government's method for measuring the energy efficiency of dwellings.
  • SuDS: Sustainable Urban Drainage Systems, features that manage surface water runoff to reduce flood risk and pollution.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 14/25

Resolved

That the Executive resolved to endorse the content of this report and recommend to the Full Council meeting on 27 January 2026: · That Full Council approves the allocation of the supplementary budget of £481,880 to complete the delivery of the homes across the five sites in Chiddingfold, to be funded ... EXE 14/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Executive resolves to endorse the content of this report and recommend to the Full Council meeting on 27 January 2026:

2.1.1. That Full Council approves the allocation of the supplementary budget of £481,880 to complete the delivery of the homes across the five sites in Chiddingfold, to be funded as follow -

 £241,990 from Commuted Sums  £239,891 from borrowing 2.1.2. That, strictly subject to Full Council approving the allocation of the required supplementary budget, the Executive resolves to:

2.1.3. Approve a virement of £150,000 from the existing New Development Contingency budget

2.1.4. Delegate to the Strategic Director of Economy, Planning and Place the authority to vary the contract with Feltham Construction Limited to the extent they consider necessary, together with other such contracts and legal agreements connected with the delivery of the Chiddingfold new build project, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the approved supplementary budget (as revised under recommendation 2.1.2.)

2.1.5. That should external funding be secured from the Homes England Affordable Homes Programme the Executive endorses

2 T New Affordable Housing Delivery, Chiddingfold – Supplementary Budget Allocation

the approval to become an Investment Partner and the utilisation of the funding in order to replace the need for the allocation of budget from the Housing Revenue Account Reserve.

3. Reason(s) for recommendation:

3.1A supplementary budget is required to ensure that sufficient funds are available to deliver the remaining 24 homes and to fulfil the Council’s contractual obligations under the construction contract.

3.2The Council’s Employer’s Agent has carefully reviewed the representations made by the Main Contractor and has confirmed that the increases in cost and time are justified.

4. Next steps

4.1Following a decision by Executive, this report will be considered by Full Council on 27 January 2026. If the recommendations are approved, Officers will proceed with implementing the necessary variations to the contract and other legal agreements to enable the completion of the schemes.

5. Exemption from publication

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Affordable Housing Delivery: Chiddingfold: Supplementary Budget AllocationSupplementary 275 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present

On this subject at Waverley

Search all
  1. New Affordable Housing Delivery - Chiddingfold - Supplementary Budget AllocationThis decision
  2. New Affordable Housing Delivery, Chiddingfold – Supplementary Budget AllocationApproved
  3. New Affordable Housing Delivery - GodalmingApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies