AI summaryWaverley Council approves £453,710 in extra budget to cover projected overspend on the Wey Court East doctor's surgery project in Farnham, funded partly from reserves and partly from extra income.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo cover projected Wey Court East overspend
Money£453,710 total extra budget£281,404 from reserves, £172,306 from extra income
What happens nextConstruction contract ends January 2026Then consultant contracts end in early 2026
Who it affectsCouncil finances, surgery, contractorsCentral Surgery Farnham and project supply chain
What was decided
A supplementary estimate of £281,404 for the Wey Court East Project was approved, funded from the Revenue Account Reserve (General Fund working balance).
A further supplementary estimate of £172,306 was approved, funded from additional external income received from the lease on the building and additional grant income. Report P6
The council set aside the budget to ensure it can meet contractual obligations on the Final Account and avoid exceeding the approved project budget. Report 1.3, 3.1
Why
The projected final account exceeds the approved budget because of cost uplifts linked to unknown building conditions, failure of older roof sections, and valid extensions of time claims. Report 1.3, 6.8
Without additional budget, invoices for valid construction and consultancy work could not be paid, risking breach of contract and legal action. Report 10.1, 11.2, 11.3
The Head of Finance has confirmed the business case remains strong and the uplift represents a low percentage increase to the project budget. Report 10.2
What happens next
The construction contract will conclude in January 2026, with the Certificate of Making Good issued and the contractor retention sum released or retained subject to any defects being rectified. Report 4.1
The supporting consultant contracts, including Employer's Agent, Architect and Quantity Surveyor, will conclude after the build contract in early 2026. Report 4.2
A lessons learned report has been drafted and the Resources Overview and Scrutiny Committee may wish to review it. Report 14.1
The money
£281,404 Supplementary estimate from Revenue Account Reserve (General Fund working balance)
£172,306 Supplementary estimate from additional lease income and grant income Report P6
£5,607,719 Total approved project budget to date, excluding original purchase cost
£6,061,421 Projected total project cost, excluding original purchase cost
£453,710 Projected shortfall in project budget
£170K per annum Previous holding costs on the vacant Wey Court East property Report 6.1
Options considered
Chosen: Allocate additional project budget now to meet projected overspend. Ensures the council can pay valid invoices, avoids breaching the construction contract, and any unspent funds would return to the Capital Contingency Fund. Report 11.1, 2.1
Rejected: Only request further budget when payments exceed the approved budget. Approval timescales may exceed invoice payment terms, risking breach of contract on the build contractor's retention. Report 11.2
Rejected: Do nothing. Could leave consultant invoices unpaid, breach the construction contract, and trigger costs and legal action. Report 11.3
Implications
Financial: Projected payback period on the business case is adjusted from 28 to 31 years when including the additional income secured.
Financial: Of the £453,710 shortfall, £172,306 is covered by additional rent and Surrey Empty Homes funding for EV chargers, with the balance from the Revenue Account Reserve.
Legal: Under clause 6.3 of the Financial Procedure Rules, a supplementary estimate over £250,000 must be approved by full Council; failure to pay suppliers could expose the council to breach of contract claims.
Risk: Without the extra budget, invoices could not be authorised, risking contractual disputes; this is mitigated by approving the budget request and negotiating consultant fees. Report 10.1
Equalities: The Public Sector Equality Duty has been considered and there are no equality and diversity implications arising directly from this report.
Climate: There are no climate change or sustainability implications arising directly from this report, though the project itself improves the environmental performance of the building. Report 12.4, P38
Staffing: There are no human resources implications, although additional legal input may be needed and costs for external support have been built into the budget request.
Who and where
Central Surgery Farnham, operated by Downing Street Group Practice under a full repairing and insuring lease with the council Report 1.2, 6.3
Russell Cawberry Ltd, the construction contractor working under a JCT Intermediate Construction Contract Report 6.6
The consultant team: Allen Construction Consultancy, WT Partnership Ltd, ADP Architecture Ltd, Perega Ltd and Stuart McCurry & Partners Ltd Report 6.5, P25, P26
Frimley Integrated Care Board and Surrey County Council, who provided additional external funding Report 6.12
Farnham residents and patients using the new surgery Report 1.2, 6.4
Timeline
2017: The council purchased the Wey Court property Report 6.1
October 2021: Council approved the redevelopment of Wey Court East for a new doctor's surgery Report 6.2, 16.3
November 2022: Council approved updated budget and lease proposals Report 6.2
July 2024: Executive approved a budget allocation to replace the roof Report 6.2, 16.1
January 2025: Construction achieved Practical Completion
February 2025: Central Surgery Farnham opened to the public Report 1.2
22 October 2025: Council approved supplementary estimates for the projected overspend
January 2026: Construction defects period expires and contractor retention is due Report 4.1
Early 2026: Supporting consultant contracts conclude Report 4.2
Plain English for the jargon
Supplementary estimate: Additional budget approved outside the original estimate, required when spending needs exceed approved limits; over £250,000 must be approved by full Council under the Financial Procedure Rules.
Revenue Account Reserve (General Fund working balance): The council's general reserves held to manage cash flow and unforeseen spending pressures.
JCT Intermediate Construction Contract: A standard form building contract published by the Joint Contracts Tribunal, used here between the council and Russell Cawberry Ltd.
Certificate of Making Good: A certificate confirming the contractor has rectified any defects identified during the defects period.
Full repairing and insuring lease: A lease where the tenant is responsible for all repairs, maintenance and insurance of the building.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCNL65/25
Resolved
That the supplementary estimate of £281,404 for the Wey Court East Project, to be funded from the Revenue Account Reserve (General Fund working balance), be approved. 2. That a supplementary estimate of £172,306 for the Wey Court East Project to be funded from additional external income received from the lease on the building and additional grant income, be approved.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1The Wey Court East Project is a Council-led redevelopment project involving the conversion of a vacant, Council-owned office building in Farnham into a modern doctor’s surgery.
1.2The new facility, now operating as “Central Surgery Farnham” opened to the public in February 2025. Since its opening, the surgery has been extremely well received by both staff and patients, providing much-needed healthcare capacity and demonstrating the Council’s commitment to delivering high-quality community infrastructure.
1.3The projected final account for the project, allowing for all possible unconfirmed increases, exceeds the approved budget. This report, therefore, seeks additional budget to ensure that the Council can meet its contractual obligations and guard against exceeding the approved project budget.
Recommendations
2.1That Council: 2.1.1 Approve a supplementary estimate of £281,404 for the Wey Court East Project, to be funded from the Revenue Account Reserve (General Fund working balance).
2.1.2 Approve a supplementary estimate of £172,306 for the Wey Court East Project to be funded from additional external income received from the lease on the building and additional grant income.
3 Reason(s) for recommendation:
3.1The recommendations outlined in this report are necessary to ensure that sufficient budget is available to meet the Council’s contractual commitments in relation to the Final Account for the Wey Court East Project.
4 Next steps
2 Wey Court East Project – Financial Update
4.1The construction contract will conclude in January 2026 with the intention for the Certificate of Making Good to be issued and the contractor retention sum to be released or retained, subject to any defects being rectified.
4.2The conclusion of the supporting consultant contracts e.g. Employer’s Agent, Architect, Quantity Surveyor will take place after the conclusion of the build contract in early 2026.
5 Exemption from publication
5.1Part of this report is exempt from publication.
5.2Appendix 1 is to be treated as exempt for the purposes of the Council’s Access to Information Procedure Rules because it contains commercially sensitive information and is therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972 as follows:
- Information relating to the financial or business affairs of any particular person (including the authority holding that information). 5.3 The content is restricted to all councillors.
5.4It is likely that the exempt information can be expected to be made available for public inspection once the final account is settled for the development.
6 Background and Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.