Wey Court East Project - Financial Update

Approved Executive 1 paper

AI summaryWaverley Executive recommends Council approves £453,710 in extra budget for Wey Court East surgery project to cover construction overspends, funded partly by external income and reserves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo sums totalling £453,710 recommended to Council
Money£453,710 supplementary estimate£281,404 from reserves, £172,306 from external income
What happens nextConstruction contract ends January 2026Retention released, consultants close out early 2026
Who it affectsWey Court East surgery, FarnhamNow operating as Central Surgery Farnham

What was decided

The Executive recommends Council approve a supplementary estimate of £281,404 for the Wey Court East Project, funded from the Revenue Account Reserve (General Fund working balance).

The Executive also recommends Council approve a further supplementary estimate of £172,306, funded from additional external income received from the building lease and additional grant income.

The extra budget is needed so the Council can meet its contractual obligations and guard against exceeding the approved project budget while the Final Account is settled. Report 3.1, 6.13

Why

Project costs have risen because of unknown building conditions found during strip-out, failure of older roof sections, and valid extensions of time claims by the contractor. Report 6.9

Total approved budget is £5,607,719; projected final cost is £6,061,421, leaving a potential £453,710 shortfall against the approved budget. Report P53, P54

Of the shortfall, £172,306 is covered by extra rent income and Surrey Empty Homes funding for EV chargers, with the remaining £281,404 drawn from the Revenue Account Reserve. Report 6.12

What happens next

Construction contract will conclude in January 2026, when the Certificate of Making Good is to be issued and the contractor retention sum released, subject to any defects being rectified. Report 4.1, 6.7

Supporting consultant contracts (Employer's Agent, Architect, Quantity Surveyor) will be concluded after the build contract ends in early 2026.

A lessons learned report has been drafted and may be reviewed by the Resources Overview and Scrutiny Committee. Report 14.1

The money

  • £281,404 Supplementary estimate from Revenue Account Reserve (General Fund working balance)
  • £172,306 Supplementary estimate from additional lease income and grant income
  • £5,607,719 Total approved budget to date (excluding original purchase cost) Report P53
  • £6,061,421 Projected total project cost (excluding original purchase cost) Report P54
  • £453,710 Projected shortfall in budget Report P54
  • £170K per annum Previous holding costs of the vacant Wey Court East property Report 6.1

Options considered

  • Chosen: Allocate additional project budget now to meet projected overspend (Recommended). Ensures the Council does not exceed approved budget and avoids risk of failing to pay valid invoices; any unspent funds would return to the Capital Contingency Fund. Report 11.1
  • Rejected: Wait and request further budget only when payment requests exceed the approved budget. Approval time may exceed invoice payment terms, risking breach of the construction contract and potential legal action. Report 11.2
  • Rejected: Do nothing. Risk of unpaid consultant invoices, underfunded retention payment, and novating services would likely cost more than the budget request and could face legal challenge. Report P50, P51

Implications

  • Financial: Projected payback period in the business case rises from 28 to 31 years when the additional secured income is included.
  • Financial: Head of Finance has confirmed the business case remains strong despite the cost uplift. Report 10.2
  • Legal: Supplementary estimate over £250,000 must be approved by full Council, not just the Executive, under Financial Procedure Rules clause 6.3. Report P59
  • Legal: Failure to pay supplier invoices could expose the Council to breach of contract claims. Report P61
  • Risk: Without additional budget, invoices could not be authorised, risking contractual disputes and possible legal action. Report 10.1
  • Equalities: No equality and diversity implications arise directly from this report; the Public Sector Equality Duty has been considered. Report P67
  • Climate: No direct climate change or sustainability implications arise from this report; the project itself improves the building's environmental performance. Report 12.4, P36
  • Staffing: No human resources implications arise directly from this report, though additional legal input may be needed and is built into the requested budget.

Who and where

  • Waverley Borough Council as project owner and landlord Report 1.1, 6.3
  • Central Surgery Farnham (Downing Street Group Practice), operating the new doctor's surgery Report 6.3, 6.4
  • Frimley Integrated Care Board, which provided additional external funding Report 6.3, 6.12
  • Surrey County Council Empty Homes Fund, source of grant income Report 6.12
  • Russell Cawberry Ltd, construction contractor under JCT Intermediate Construction Contract Report 6.6, 6.7
  • Consultant team: Allen Construction Consultancy, WT Partnership Ltd, ADP Architecture Ltd, Perega Ltd, Stuart McCurry & Partners Ltd Report 6.5, P22, P23, P24, P25
  • Patients and residents of Farnham using Central Surgery Farnham Report 6.4

Timeline

  • 2017: Council purchased the property at Wey Court, Farnham. Report 6.1
  • October 2021: Council approved redevelopment of the building for conversion into a new doctors' surgery. Report 6.2, 16.3
  • November 2022: Executive approved updated lease proposals and updated budget. Report 6.2, 16.2
  • July 2024: Executive approved budget allocation to replace the roof. Report 6.2, 16.1
  • January 2025: Construction achieved Practical Completion. Report 6.7
  • February 2025: Central Surgery Farnham opened to the public. Report 6.4, 6.7
  • 14 October 2025: Executive considered the financial update and recommended supplementary estimates to Council. Report 2.1
  • January 2026: Construction contract concludes; Certificate of Making Good to be issued; 12-month defects period ends; contractor retention due. Report 4.1, 6.7
  • Early 2026: Supporting consultant contracts to be concluded.

Plain English for the jargon

  • Supplementary estimate: Additional budget approved outside the original budget to cover new or increased spending requirements.
  • Final Account: The agreed final statement of all sums due to the contractor and consultants for the completed works.
  • Practical Completion: The point at which the building is complete enough to be handed over and used for its intended purpose, even if minor items remain.
  • Certificate of Making Good: A certificate issued at the end of the defects period confirming that defects have been put right.
  • Retention sum: A portion of the contract price withheld until the end of the defects period to ensure defects are remedied.
  • Defects period: A set period after Practical Completion during which the contractor must rectify any defects that appear, here 12 months.
  • JCT Intermediate Construction Contract: A standard form of building contract issued by the Joint Contracts Tribunal for use on intermediate-scale projects.
  • Quantity Surveyor: A consultant who advises on construction costs, contracts and the final account.
  • Novating services: Transferring an existing contract from one party to another, typically requiring the original party's agreement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 76/25

Resolved

RECOMMENDED that Council: 1. Approve a supplementary estimate of £281,404 for the Wey Court East Project, to be funded from the Revenue Account Reserve (General Fund working balance). 2. Approve a supplementary estimate of £172,306 for the Wey Court East Project to be funded from additional external income received from ... EXE 76/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Wey Court East Project is a Council-led redevelopment project involving the conversion of a vacant, Council-owned office building in Farnham into a modern doctor’s surgery. 1.2 The new facility, now operating as “Central Surgery Farnham” opened to the public in February 2025. Since its opening, the surgery has been extremely well received by both staff and patients, providing much-needed healthcare capacity and demonstrating the Council’s commitment to delivering high-quality community infrastructure. 1.3 The projected final account for the project, allowing for all possible unconfirmed increases, exceeds the approved budget. This report, therefore, seeks additional budget to ensure that the Council can meet its contractual obligations and guard against exceeding the approved project budget.

Recommendations

2.1That the Executive recommends that Council:

2.1.1 Approve a supplementary estimate of £281,404 for the Wey Court East Project, to be funded from the Revenue Account Reserve (General Fund working balance). 2.1.2 Approve a supplementary estimate of £172,306 for the Wey Court East Project to be funded from additional external income received from the lease on the building and additional grant income.

3 Reason(s) for recommendation:

2 Wey Court East Project – Financial Update

3.1The recommendations outlined in this report are necessary to ensure that sufficient budget is available to meet the Council’s contractual commitments in relation to the Final Account for the Wey Court East Project.

4 Next steps

4.1The construction contract will conclude in January 2026 with the intention for the Certificate of Making Good to be issued and the contractor retention sum to be released or retained, subject to any defects being rectified. 4.2 The conclusion of the supporting consultant contracts e.g. Employer’s Agent, Architect, Quantity Surveyor will take place after the conclusion of the build contract in early 2026.

5 Exemption from publication

5.1Part of this report is exempt from publication.

5.2Appendix 1 is to be treated as exempt for the purposes of the Council’s Access to Information Procedure Rules because it contains commercially sensitive information and is therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972 as follows:

- Information relating to the financial or business affairs of any particular person (including the authority holding that information).

5.3The content is restricted to all councillors.

5.4It is likely that the exempt information can be expected to be made available for public inspection once the final account is settled for the development.

6 Background and Proposal

3 Wey Court East Project – Financial Update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wey Court East Project: Financial UpdateReport 501 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, apologies
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. Wey Court East Project - Financial UpdateThis decision
  2. Wey Court East Project - Financial UpdateApproved
  3. Wey Court EastApproved
  4. Wa/2023/00905 - wey court east union road farnham gu9 7ptDecided
  5. Wey Court East Project UpdateApproved
  6. Item B2, WA/2017/0953 - Community Centre, Wey Court, FarncombeDecided

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies