Council, Wednesday 22 October 2025 at 7.00pm

Willmer House: Timber Structure Repair and Replacement at Façade

Agreed Committee 1 paper

AI summaryWaverley Borough Council approved £610,248.05 from capital receipts to repair the decayed timber roof frame at the front of Grade 1 listed Willmer House and commission a rear condition survey.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCouncil approved capital budget for timber roof repairs
Money£610,248.05 approvedPlus £60,500 virement from rear window budget
What happens nextRepair work from November 202512-15 weeks duration; rear survey commissioned
Who it affectsMuseum of Farnham buildingGrade 1 listed Willmer House, visitors, future unitary

What was decided

Council approved a budget of £610,248.05, funded from the capital receipts reserve, to carry out repairs restoring the structural function of the timber roof frame at the front of Willmer House, and to commission an external condition survey of the rear of the building. Report 2.2

The Executive on 14 October 2025 had already approved the virement of £60,500 from the 2025/26 capital programme for rear window joinery to support the cost of the structural roof timber repairs. Report P9, 3.3, 2.2

Why

The Council has a legal duty under the Listed Buildings Act 1990 to maintain the Grade 1 listed building it owns, and there is significant wet rot and insect decay in the timber roof frame causing loss of structural function. Report 3.1, 6.6, 6.7, 6.8

Doing the work during the 2025/26 winter shut down is the most cost-effective option; delaying risks a third winter shut down with extension of time costs of more than £200,000 over an extra 30 to 36 weeks. Report 3.2, 6.20, 10.1

Completion by 30 September 2026 is required to avoid repaying some or all of the Arts Council England MEND grant, and the building's future will be considered separately with options including re-imagining it as a Museum of Craft or potential disposal after 2038. Report 3.2, 13.5, 12.1, 12.5, 12.6

What happens next

Listed building consent application has been submitted; timber roof repair work is expected to take 12 to 15 weeks and can start immediately, with completion needed before April 2026 so brickwork reinstatement can resume. Report 4.2, 6.18, 6.19

A condition survey of the rear elevation will be carried out while the rear scaffold is in place, with findings expected before the end of the year, and officers will report back on longer term options for the museum. Report 1.6, 6.21

Ecology survey results for potential bat presence in the roof structure are awaited, and a market valuation of the property is to be obtained as part of future options work. Report 10.2, 12.6

The money

  • £610,248.05 Supplementary estimate from capital receipts reserve for front roof timber repairs and rear survey Report 2.2, 6.24, 13.3
  • £60,500 Virement from rear window joinery budget to support roof timber repairs Report P9, 3.3, 6.22, 13.2
  • £670,748.05 Subtotal funding requirement before deduction of reallocated window budget Report 6.23, P54, 13.3
  • £791,973.18 Total cost of the roof timber repair and associated works Report 6.23, P53
  • £241,054.18 Roof repairs and associated works Report 6.23, P47
  • £120,000.00 Scaffolding costs Report 6.23, P48
  • £23,590.00 Replacement lead hopper and downpipe, ecology and asbestos surveys Report 6.23, P49
  • £50,000.00 Contractor costs for keeping site open during winter shut down Report 6.23, P49
  • £54,500.00 Additional costs for extending the contract period (provisional 8 weeks) Report 6.23, P49
  • £124,564.00 Provisional sums and contingency Report 6.23, P50
  • £138,265.00 Professional fees Report 6.23, P51
  • £40,000.00 Client-side contingency Report 6.23, P52
  • £51,658.86 Adjustment to previous cost report excluding roof costs Report 6.23, P53
  • £69,566.27 Adjustment of superseded or unexpended provisional sums and contingency Report 6.23, P54
  • £200,000 Estimated additional cost of a third winter shut down from extension of time Report 3.2, 6.20, 10.1
  • approx. £6000 per week Indicative weekly cost of extended scaffold and contractor duration Report 3.2
  • £1,720,087 Total approved budget to date for the Willmer House project Report 13.1
  • £734,942 Council-funded share of the Willmer House project budget to date Report 13.1
  • £985,145 External grant share of the Willmer House project budget to date Report 13.1
  • £248,375.80 Supplementary estimate approved in June 2025 for chimney stack rebuilding Report 1.1
  • £160,500 2025/26 capital budget originally approved for rear window redecoration Report 13.2
  • £99,500 Portion of rear window budget linked to an unsuccessful external funding bid Report 13.2
  • approximately £136,554 Capital works and maintenance spend on Willmer House since 2005 Report 6.25
  • £6,827 Average annual capital works and maintenance spend since 2005 Report 6.25
  • £39,894 Routine maintenance spend on Willmer House since 2005 Report 6.26
  • approximately £80,000 Cost of the safety scaffold from December 2019 to January 2025 Report 6.27, P62

Options considered

  • Rejected: Do nothing and reinstate parapet wall over decayed timbers. Dangerous structural failure risking severe damage or collapse and wasting the investment already made in restoring the front facade Report 11.1, P76
  • Rejected: Delay timber repairs while investigating funding sources. Not cost effective: would block the brickwork programme, risk a third winter shut down costing up to £200,000, and risk repaying ACE grant
  • Chosen: Approve the roof timber repairs with minimal delay during the 2025/26 winter shut down. Most economical option, keeps the MEND-funded project on the critical path, avoids a third winter shut down, and meets ACE grant conditions Report 11.3, 11.5, 2.2

Implications

  • Financial: £610,248.05 supplementary estimate funded from the capital receipts reserve, with a further £60,500 vired from the rear window redecoration budget; around 5% contingency is included in the cost. Report 2.2, 3.3, 13.3, 13.4
  • Legal: The Council has a legal duty to maintain the Grade 1 listed building under the Listed Buildings Act 1990; failure to act could lead to a Repairs Notice or Repairs Order from the local planning authority. Report 3.1, 6.1
  • Legal: Failure to complete the front facade project by 30 September 2026 could result in repaying some or all of the Arts Council England MEND grant, and a 15-year covenant on the freehold runs until 2038. Report 3.2, 8.1, 12.1, 13.5
  • Legal: The virement of £60,500 was within the Executive's powers under Financial Procedural Rules 5.2, 5.3, 5.5; the supplementary estimate above £250,000 required Full Council approval under FPR 6.3. Report 14.4, 14.5, 14.6, 14.7, 14.9
  • Risk: Timber roof has extensive wet rot and insect decay, with only about 30% of the wall plate and 40% of the tie beam section remaining, and the ceiling is sagging at second floor level. Report 6.6, 6.8
  • Risk: Ecology survey for bats in the roof structure carried out on 24 September 2025 found no evidence of bats, but the report is still pending. Report 10.2
  • Risk: The rear elevation is in poor and rapidly declining condition with loose masonry around window openings presenting a health and safety risk to the public; a condition survey will be carried out while the rear scaffold is in place. Report 1.5, 6.21
  • Equalities: Officers have concluded that there are no equality and diversity implications arising directly from this report, as it concerns essential repair and conservation work to an historic building. Report 15.3
  • Climate: The report contains no direct climate change or sustainability implications beyond extending the life of a heritage building using traditional conservation materials and processes. Report 16.1
  • Other: Property will presumably transfer to a newly created unitary authority following Local Government Reorganisation, subject to the 15-year ACE covenant running to 2038. Report 8.1, 12.1

Who and where

  • Visitors and users of the Museum of Farnham Report 7.1, 1.1
  • Waverley Borough Council as owner of the Grade 1 listed Willmer House Report 3.1, 6.1
  • Arts Council England and National Heritage Lottery Fund as external funders Report 6.2, 13.1, 13.5
  • Future unitary authority that will inherit the property Report 8.1
  • Farnham Town Council, Farnham Maltings and Farnham and District Museum Society involved in workshops on the museum's future Report 12.3
  • Members of the public near the rear of the building, given the risk of falling masonry

Timeline

  • 2005 to present: Approximately £136,554 spent on capital works and maintenance on Willmer House, averaging £6,827 per year Report 6.25
  • 2015: Highly vulnerable condition of the front facade first reported following a conservation condition survey by Simpson Brickwork Conservation Report 6.2
  • 2023: Council secured external funding from Arts Council England and the National Heritage Lottery Fund, and signed the ACE funding agreement including a 15-year covenant on the freehold running to 2038 Report 6.2, 8.1, 12.1
  • January 2025: 83-week programme of essential repair and conservation work commenced to restore the historic brick facade Report 6.1
  • February 2025: Council approved £160,500 capital programme allocation for redecoration of rear windows Report 6.22, 13.2
  • 3 June 2025: Executive approved £248,375.80 supplementary estimate for rebuilding two chimney stacks Report 1.1
  • 12 June 2025: Site inspection by structural engineer from the Morton Partnership and conservator from Dolman Conservation identifying urgent need for timber roof repairs Report 6.6
  • Summer 2025: Council held facilitated workshops on re-imagining the museum involving Farnham Town Council, Farnham Maltings and Farnham and District Museum Society Report 12.3
  • 24 September 2025: Ecology survey carried out to assess potential bat presence in the historic roof structure Report 10.2
  • 14 October 2025: Executive approved virement of £60,500 from rear window joinery budget to support the roof timber repairs Report P9, 3.3, 6.22
  • 22 October 2025: Full Council decision to approve £610,248.05 supplementary estimate for the timber roof repairs and rear condition survey Report 2.2
  • November 2025 to March 2026: Critical timing window for the structural timber repairs, with an estimated duration of 12 to 15 weeks Report 3.2, 6.18, 6.19
  • April 2026: Brickwork reinstatement works resume after the winter shut down Report 3.2
  • By 30 September 2026: Project completion deadline required to meet ACE MEND grant conditions and avoid a third winter shut down Report 3.2, 6.20, 13.5
  • Before the end of 2025: Council expects to receive findings of the rear elevation condition survey Report 1.6
  • 2038: Expiry of the 15-year Arts Council England covenant requiring the building to be used as a museum Report 8.1, 12.1

Plain English for the jargon

  • Listed Building: A building of special architectural or historical interest that is protected in law and requires consent for alterations.
  • Grade 1 Listed: The highest grade of listed building protection in England, applied to buildings of exceptional interest.
  • Listed Building Consent: Approval required from the local planning authority before works can be carried out to a listed building.
  • Capital receipts reserve: Council reserves of money received from selling capital assets, used to fund new capital expenditure.
  • Virement: The transfer of an approved budget from one purpose to another within the Council's financial rules.
  • Supplementary estimate: Additional budget approval sought outside the original budget setting process to cover new or increased costs.
  • MEND Fund: Arts Council England's Museum Estate and Development fund, a capital grants programme for museums.
  • Flitch plate: A steel plate sandwiched between timber beams to reinforce or repair a decayed structural member.
  • Wall plate: A horizontal timber beam running along the top of a wall to support the ends of roof joists or rafters.
  • Tie beam: A horizontal structural timber spanning between load-bearing elements to resist outward spread of the roof.
  • Wet rot: A form of timber decay caused by fungal growth in damp conditions, weakening the structural timber.
  • NHLF: National Heritage Lottery Fund, a major UK funder of heritage projects using National Lottery money.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCNL67/25

Resolved

That a budget of £610,248.05, to be funded from the capital receipts reserve for the purpose of carrying our repairs to restore the structural function of the timber roof frame at the front of Willmer House, as detailed in paragraphs 6.11 – 6.18 of the agenda report, be agreed 2. That the budget would also be used to instruct an external survey to assess the condition of the rear of the building, be agreed.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Council

Executive summary

1.1At a meeting on 3rd June 2025, the Executive approved the recommendations in a report regarding repair works to The Museum of Farnham, which occupies Grade 1 Listed Willmer House. This included agreeing a supplementary estimate of £248,375.80 to cover the costs of rebuilding two chimney stacks, which pose a risk to health and safety and the extension of the tendered contract to complete the works.

1.2The Executive report on 3rd June also raised concerns about the condition of the timber roof structure which, following the removal of the parapet wall is now fully exposed at the front façade interface. Since the Executive in June, there has been a detailed assessment of the timber roof frame involving a site meeting with a structural engineer and a timber frame and joinery conservator. Their findings conclude that repair and replacement of the roof timbers is essential and urgently required to restore the structural function of the roof.

1.3This report explains how the roof structure works and the urgent need for the repair work. It proposes the most cost-effective repair solution, which is for the structural timber works to take place during the 2025 winter shut down. As well as the need for an integrated scaffold covering the whole of the rear elevation. Front and rear scaffolding is necessary to support the load of the roof structure while the chimney and roof repairs are carried out.

1.4The report gives a breakdown of the costs of repairing the structural roof timbers at the front of the building only. This is because, we do not have a cost estimate for repairing the roof timbers at the back of the building yet.

1.5However, a preliminary visual inspection of the brickwork on the rear of the building has been carried out following safety concerns that bricks are coming loose around the window openings. It is clear from this cursory inspection that brickwork decay is widespread and that the condition of the external windows and door frames is declining at a rapid rate. The overall condition of the rear appears to have reached a critical point where major intervention is likely to be needed.

1.6It is therefore recommended that a condition survey is carried out while the rear scaffold is in situ to understand the extent and severity of the problems. Subject to approval, the Council expects to receive the findings of the rear survey before the end of the year.

2 Willmer House Timber Roof Structure Repairs

2. Recommendations: 2.1 At their meeting on 14 October the Executive resolved to:

Approve the virement of £60,500 capital funding from the 2025/26 capital programme for rear window joinery to be reallocated to support the overall cost of repairing the structural roof timbers at the front of the building.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Willmer House: Timber Structure Repair and Replacement at FaçadeReport 444 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

38 of 50 attended
PR
Councillor Penny RiversMayor, present
DM
Councillor David MunroDeputy Mayor, present
LA
Councillor Lauren AtkinsCommittee Member, present
JA
Councillor Jane AustinCommittee Member, present
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
DB
Councillor Dave BusbyCommittee Member, apologies
LC
Councillor Laura CavaliereCommittee Member, apologies
PC
Councillor Peter ClarkCommittee Member, present
CC
Councillor Carole Cockburn BEMCommittee Member, apologies
JC
Councillor Janet CroweCommittee Member, apologies
JD
Councillor Jerome DavidsonCommittee Member, present

All 50 on the meeting page

On this subject at Waverley

Search all
  1. Willmer House: Timber Structure Repair and Replacement at FaçadeThis decision
  2. Willmer House: Timber Roof Structure Repair and Replacement at Front FacadeApproved
  3. Progress report on the essential repair and conservation works to Grade 1 Willmer House, Museum of FarnhamApproved

More from Waverley Council

All decisions
MeetingDecisionOutcome
29 Jul 2026 Annual Standards Report 2025-26RESOLVED that the Annual Report 2025-26 of the Joint Standards Committee be deferred to a future meeting. Deferred Open
29 Jul 2026 Member Questions at MeetingsThat 1. The amended Council Procedure Rule 12 as set out in Appendix 2 to this report, be adopted 2. The Monitoring O... Approved Open
30 Jun 2026 Amended Redundancy Policy - Pension Strain CostsThat 1. the amendment to the redundancy policy to remove the deduction of pension strain costs from redundancy paymen... Approved Open
30 Jun 2026 Councillor Connor Relleen - Approval of Reason for Non-attendance at meetingsThat 1. the reason for Councillor Connor Relleen’s failure to attend any meeting of the Council or any of its committ... Agreed Open
30 Jun 2026 Waverley Householder CIL - Lack of ProgressRESOLVED that the motion as set out in agenda report be supported. The Chamber adjourned for a 10 minute comfort brea... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies