Waverley Borough Council

Water Hygiene Report

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a monthly Water Hygiene Report covering remedial work on council housing stock, with a revised reporting format and weekly performance reviews now in place with contractor SMS.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMonthly Water Hygiene Report recorded by the board
MoneyNot stated
What happens nextWeekly operational meetingsThroughout July 2026 at The Burys
Who it affectsCouncil housing tenants and staffTenants needing access for water safety surveys

What was decided

The board noted the monthly Water Hygiene Report, as recommended, and endorsed the revised governance, reporting and programme management arrangements. Report P42

A joint recovery plan was formally agreed between WBC and SMS on 26 June 2026 to accelerate completion of outstanding water safety remedial actions. Report P17, P18

A standardised reporting format was agreed on 2 July 2026, with weekly performance review meetings to be held at The Burys. Report P26, P27

Why

Asset and survey data inherited from the previous contractor HSL was incomplete, requiring validation through new surveys before mains conversions could be specified accurately. Report P2, P3, P5, P6

Access problems, particularly to loft spaces and to properties generally, slowed the early stages of the SMS contract and required WBC to provide additional access support. Report P2, P13, P14

In April 2026, the programme was escalated to the Interim Head of Housing following discussions with the Regulator of Social Housing, with a projected completion period of about two and a half years. Report P9

What happens next

Weekly operational planning meetings will run throughout July 2026 at The Burys, led by the SMS Project Lead and WBC colleagues, covering access, quotations, delivery issues and completion targets. Report 6.1, P30, P31

SMS will provide weekly updates against the agreed programme tracker, including overdue and newly identified actions completed, outstanding surveys, access rates and planned completions. Report 6.3, P35, P36

A follow-up meeting with Mike Crook, Chief Executive of SMS, is scheduled for 2:00 pm on 3 September 2026. Report P18

Options considered

  • Chosen: Adopt revised approach of using remedial actions and enhanced Planned Preventative Maintenance to manage risks while longer-term mains conversion proposals are considered as part of future cyclical investment programmes. Ongoing access challenges and the need to gather accurate programme data mean risks can be managed more rapidly through PPM while conversion options are explored Report P20, P21, P22, P23, P24

Implications

  • Risk: 1,017 remedial actions were outstanding as at 1 July 2026 across low, medium and high risk categories, with a target cumulative completion of 968 by end of December 2026 and 1,017 thereafter. Report P45, P46, P48, P49
  • Staffing: A dedicated WBC resource will liaise with residents to maximise access, and an SMS senior project lead has been appointed to coordinate delivery. Report P18
  • Legal: Reporting and assurance arrangements are framed in part to support the Regulator of Social Housing, with whom senior WBC leaders discussed the programme in April 2026. Report P9, P27
  • Other: The council states there is no immediate risk to residents' health and safety, citing completed Water Risk Assessments, prioritised high-risk works, ongoing PPM, and interim control measures. Report P39, P40, P41
  • Financial: Validating asset information and completing additional surveys was intended to improve programme cost accuracy and reduce unnecessary expenditure across all tenures. Report P6, P7

Who and where

  • Waverley Borough Council tenants across the housing stock, including residents of Faulkner Court where works were delayed until 16 June 2026 Report P1, P8
  • WBC housing staff involved in access support, surveying and performance monitoring Report P14, P18
  • The Regulator of Social Housing, which receives assurance information where required Report P9, P27

Timeline

  • 18 December 2025: SMS Environmental Services Ltd entered a 36 month contract with WBC, extendable by 24 months Report P1
  • January 2026: Service delivery transferred from HSL to SMS Report P3
  • April 2026: Programme escalated to Interim Head of Housing after discussions with the Regulator of Social Housing Report P9
  • 16 June 2026: Works at Faulkner Court were delayed until this date Report P8
  • 23 June 2026: Interim Head of Housing raised delivery and reporting matters with the CEO of SMS Report P16
  • 26 June 2026: Joint recovery plan agreed between WBC and SMS Report P17, P18
  • 29 June 2026: Collaborative working session held at The Burys Report P18
  • Throughout July 2026: Weekly operational planning meetings scheduled at The Burys Report 6.1, P30
  • 2 July 2026: Standardised reporting format and finalised performance and completion table agreed and submitted Report P18, P26
  • 3 September 2026, 2:00 pm: Follow-up meeting scheduled with the CEO of SMS Report P18
  • By end of December 2026: Target cumulative completion of 968 of 1,017 outstanding remedial actions Report P48, P49

Plain English for the jargon

  • PPM: Planned Preventative Maintenance, including temperature monitoring, flushing and inspection of water systems
  • SMS: SMS Environmental Services Ltd, contractor for water safety remedial works
  • WBC: Waverley Borough Council
  • LSAB: Landlord Services Advisory Board, the Executive Working Group receiving this report
  • CWS: Cold Water Storage, used in the context of access hazards
  • HSL: Previous water hygiene services contractor for WBC, before SMS took over
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

RESOLVED that the monthly Water Hygiene Report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Background

SMS Environmental Services Ltd (SMS) entered into a contract with Waverley Borough Council (WBC) on 18 December 2025 to manage and deliver water safety remedial actions across the housing stock. The contract is for an initial term of 36 months, with an option to extend for a further 24 months.

Prior to SMS, HSL delivered water hygiene services for WBC, including water risk assessments, remedial works and planned preventative maintenance (PPM). During the course of that contract, challenges were reported in accessing certain areas, particularly loft spaces. Reasons included restricted access due to limited space, a lack of suitable flooring and insufficient lighting to enable safe working.

Page 1 of 7 Following the expiry of the previous contract, responsibility for delivery of the service transferred to SMS in January 2026.

3. Remedial Programme Progress

Following the transition from HSL to SMS, WBC identified that the available asset and survey data was incomplete. Information requiring validation included the type of water system (direct mains, stored water, communal system, etc.), water storage tank specifications, the location of hot water cylinders and other property-specific details.

As a result, an initial programme of surveys and feasibility assessments was required before mains conversions could be accurately specified and delivered. This approach was intended to:

 Improve the accuracy of programme costs;  Reduce unnecessary expenditure across all tenures;  Minimise repeat visits;  Reduce the risk of future water-related incidents, including flooding.

The requirement to validate asset information and complete additional surveys meant that progress during the early stages of the contract was slower than originally anticipated. Additional programme challenges also arose at Faulkner Court, where works were delayed until 16 June 2026.

In April 2026, the delivery of the programme was escalated to Nesan Thevanesan, Interim Head of Housing, following discussions with the Regulator of Social Housing and WBC's senior leadership team regarding the completion of outstanding remedial actions. At that time, the projected completion period for all outstanding works was approximately two and a half years. To explore opportunities for accelerating delivery, revised programme plans and Gantt charts were requested.

Following this escalation, WBC and SMS established a programme of regular meetings, often taking place more than once per week, to develop a comprehensive programme tracker. The objective was to establish:

 A clear schedule of planned completions;  Forecast completion dates;  Progress against overdue remedial actions;  Progress against newly identified remedial actions.

Although works continued to progress on site, further development of programme reporting was required to provide complete visibility of completed and outstanding actions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Hygiene ReportReport 257 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 19 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, present
JK
Councillor Jacquie KeenCommittee Member, present
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, present
DM
Dave MaddamsObserver, present
LL
Lillian LanekOfficer, present
SR
Scott RichardsonOfficer, present

All 19 on the meeting page

On this subject at Waverley

Search all
  1. Water Hygiene ReportThis decision
  2. New contract for the Water Hygiene Risk Assessments and Planned Preventative Maintenance ServicesDecided
  3. Water Hygiene & Legionella Management Internal Audit Recommendation and PolicyNoted
  4. New Contract for Water Hygiene Remedial WorksApproved
  5. Approval of Additional Budget Request for Water Hygiene Services ProcurementApproved
  6. Additional budget requst for water hygiene works to the council's homes reportApproved

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open
30 Jul 2026 Annual Complaints and Service Improvement ReportRESOLVED that: · the contents of the Annual Complaints and Service Improvement Report 2025/26, including complaint pe... Noted Open