RESOLVED that the monthly Water Hygiene Report be noted.
AI summaryWaverley's Landlord Services Advisory Board noted a monthly Water Hygiene Report covering remedial work on council housing stock, with a revised reporting format and weekly performance reviews now in place with contractor SMS.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the monthly Water Hygiene Report be noted.
SMS Environmental Services Ltd (SMS) entered into a contract with Waverley Borough Council (WBC) on 18 December 2025 to manage and deliver water safety remedial actions across the housing stock. The contract is for an initial term of 36 months, with an option to extend for a further 24 months.
Prior to SMS, HSL delivered water hygiene services for WBC, including water risk assessments, remedial works and planned preventative maintenance (PPM). During the course of that contract, challenges were reported in accessing certain areas, particularly loft spaces. Reasons included restricted access due to limited space, a lack of suitable flooring and insufficient lighting to enable safe working.
Page 1 of 7 Following the expiry of the previous contract, responsibility for delivery of the service transferred to SMS in January 2026.
3. Remedial Programme Progress
Following the transition from HSL to SMS, WBC identified that the available asset and survey data was incomplete. Information requiring validation included the type of water system (direct mains, stored water, communal system, etc.), water storage tank specifications, the location of hot water cylinders and other property-specific details.
As a result, an initial programme of surveys and feasibility assessments was required before mains conversions could be accurately specified and delivered. This approach was intended to:
Improve the accuracy of programme costs; Reduce unnecessary expenditure across all tenures; Minimise repeat visits; Reduce the risk of future water-related incidents, including flooding.
The requirement to validate asset information and complete additional surveys meant that progress during the early stages of the contract was slower than originally anticipated. Additional programme challenges also arose at Faulkner Court, where works were delayed until 16 June 2026.
In April 2026, the delivery of the programme was escalated to Nesan Thevanesan, Interim Head of Housing, following discussions with the Regulator of Social Housing and WBC's senior leadership team regarding the completion of outstanding remedial actions. At that time, the projected completion period for all outstanding works was approximately two and a half years. To explore opportunities for accelerating delivery, revised programme plans and Gantt charts were requested.
Following this escalation, WBC and SMS established a programme of regular meetings, often taking place more than once per week, to develop a comprehensive programme tracker. The objective was to establish:
A clear schedule of planned completions; Forecast completion dates; Progress against overdue remedial actions; Progress against newly identified remedial actions.
Although works continued to progress on site, further development of programme reporting was required to provide complete visibility of completed and outstanding actions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Water Hygiene ReportReport | 257 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
| 30 Jul 2026 | Annual Complaints and Service Improvement ReportRESOLVED that: · the contents of the Annual Complaints and Service Improvement Report 2025/26, including complaint pe... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.