Landlord Services Improvement Plan Update [2025-26]

Noted Executive 2 papers

AI summaryWaverley Landlord Services Advisory Board noted an update on the housing improvement plan, with 53 of 62 actions completed by end of June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted the improvement plan progress report
MoneyNot stated
What happens nextComplete remaining actions by March 2026Target to finish all 62 actions by end of March 2026
Who it affectsCouncil housing tenantsTenants of the council's housing service

What was decided

The Board noted the Landlord Services Improvement Plan update. Report P12

Why

The Regulator of Social Housing gave the housing service a C2 judgement in February 2025, after an inspection in late 2024, and required an improvement plan to address weaknesses against the Consumer Standards. Report 2.1

The Landlord Service Improvement Plan 2025/26 brought existing improvement work together with the Regulator's findings into one plan, with 62 actions assigned to service managers. Report 3.2, 3.3

What happens next

Monthly updates on actions and outcomes will continue to be provided to the Board and the Regulator of Social Housing. Report 5.4

Revised target dates have been agreed for the 9 off track actions, including Action 32 on procuring a communal cleaning contractor, which is delayed by the Sc20 leasehold consultation. Report P9, P10

Options considered

  • Chosen: Note the Landlord Services Improvement Plan update. The Board was asked to note the report and make any comments to the Interim Head of Service. Report P12

Implications

  • Risk: 9 of 62 actions are off track, with reasons including resource and recruitment challenges, external contract or supplier delays, and reprioritising due to new information. Report P9, P11
  • Staffing: Resource capacity constraints are among the causes of off track actions. Report P9
  • Other: Action 32, procuring a contractor for cleaning communal areas, is off target because of delays with the Sc20 leasehold consultation process. Report P10

Who and where

  • Tenants of the council's housing service Report 2.1, 3.1
  • The Regulator of Social Housing Report 2.1, 5.4
  • Service managers responsible for completing the 62 improvement actions Report 3.3

Timeline

  • October to December 2024: Regulator of Social Housing inspection of the housing service Report 2.1
  • February 2025: C2 Regulatory Judgement received under the Consumer Standards Report 2.1
  • End March 2026: Target date for completing all 62 improvement actions Report 3.3
  • End of June 26: 53 actions (85.5%) completed, 8 off track with revised dates, 1 off target Report P8, P9, P10
  • 2026-07-30: Landlord Services Advisory Board noted the update

Plain English for the jargon

  • RSH: Regulator of Social Housing
  • LSIP: Landlord Service Improvement Plan 25/26, the overarching plan for housing service improvements
  • C2: A Regulatory Judgement grade, indicating the landlord needs to take action on identified weaknesses
  • Consumer Standards: The social housing standards assessed by the Regulator of Social Housing
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item45

Resolved

RESOLVED that the Landlord Services Improvement Plan update was noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Background

2.1The Council’s housing service was inspected by the Regulator of Social Housing (RSH) between October and December 2024 and received a C2 Regulatory Judgement in accordance with the Consumer Standards (CS), in February 2025. 2.6 The RSH require any social landlord graded a C2 to develop an improvement plan that will address identified areas of weakness

3. Key Developments

3.1The Council were already progressing a set of improvement plans across the housing service to address known areas of weakness, as well as provide a mechanism for continuous self-development.

3.2The Landlord Service Improvement Plan 25/26 (LSIP) represents an overriding plan, which incorporates a set of separate improvement across the housing service into one overriding parent plan and incorporated the improvements identified from the Regulatory judgement.

3.3Collectively the LSIP identified 62 improvement actions, with assigned target dates for completion. The actions were assigned to service managers who were responsible for their completion. The objective of the plan was to address and complete all actions within one year from its commencement, concluding end March 2026.

5.4Monthly updates are provided to the Landlord Services Advisory Board and Regulator of Social Housing on the actions and outcomes sanctioned by the LSIP Governance

4. Current Progress of the LSIP at the end of June 26

53 Actions (85.5%) have been completed

8 Actions (12.9%) off track with revised target dates agreed. These are due to resource capacity constraints and independencies on related actions.

1 Action (1.6%) off target with remedial action taken: Action 32 (to procure a contractor for the cleaning of communal areas) as a result to delays with the Sc20 leasehold consultation process.

The chart below shows the progress made against the improvement plan actions. All off track actions have had revised dates agreed through the LSIP. Changes in timescales are due to a variety of circumstances e.g. resource and recruitment challenges, external contract or supplier delays, and deprioritising actions due to new information. Further detail can be found in Appendix 1 Landlord Services Improvement Plan

Recommendations

The Board are asked to:  Note and make any comments to Interim Head of Service on the report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Landlord Service Improvement PlanAppendix 1 634 KB Download
PDF
Landlord Services Improvement Plan Update [2025-26]Report 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 19 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, present
JK
Councillor Jacquie KeenCommittee Member, present
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, present
DM
Dave MaddamsObserver, present
LL
Lillian LanekOfficer, present
SR
Scott RichardsonOfficer, present

All 19 on the meeting page

On this subject at Waverley

Search all
  1. Landlord Services Improvement Plan Update [2025-26]This decision
  2. Landlord Services Performance Scorecard and Exceptions Report May 2026Noted
  3. Landlord Services Improvement Plan UpdateNoted
  4. Landlord Services Performance Scorecard and Exceptions Report [April 2026]Noted
  5. Landlord Services Improvement Plan Update [date]Noted
  6. Landlord Services Performance Scorecard and Exceptions Report March 2026Noted

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Annual Complaints and Service Improvement ReportRESOLVED that: · the contents of the Annual Complaints and Service Improvement Report 2025/26, including complaint pe... Noted Open