CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Welwyn Hatfield Borough Council
Audit Committee, Thursday 21 March 2019 at 7.30pm

SHARED INTERNAL AUDIT SERVICE (SIAS) INTERNAL AUDIT PROGRESS REPORT

Noted Finance 1 paper

Audit Committee noted this item on Thursday 21 March 2019. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

RESOLVED a) Note the Internal Audit Progress Report for the period to 8 March 2019 and; b) Note the proposed amendments to the 2018/19 Annual Audit Plan.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Audit Committee

Recommendations

Members are recommended to:  Note the Internal Audit Progress Report for the period to 8 March 2019, and  Note the proposed amendments to the 2018/19 Annual Audit Plan. Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.7 Proposed Amendments to the 2018/19 Annual Audit Plan 2.9 High Priority Recommendations 2.12 Performance Management

Appendices

A Progress against the 2018/19 Audit Plan

B 2018/19 Audit Plan Start Dates Agreed with Management

C Assurance and Finding Definitions 2018/19

Page 2 1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2018/19 as at 8 March 2019. b) Findings for the period 14 September 2018 to 8 March 2019. c) Details of changes to the planned start dates of audits from the approved 2018/19 Audit Plan. d) Proposed amendments to the 2018/19 Annual Audit report e) An update on performance management information as at 8 March 2019.

Background

1.2The 2018/19 Annual Audit Plan was approved by the Audit Committee at its meeting on 22 March 2018.

1.3The Audit Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the fourth report giving feedback on the delivery of the 2018/19 Internal Audit Plan.

1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1As at 8 March 2019, 88% of the 2018/19 Audit Plan days had been delivered (the calculation excludes contingency). Appendix A provides a status update on each individual project within the audit plan.

2.2The following final reports have been issued since 4 January 2019 (cut-off date for the SIAS Update Report for 17 January 2019 Audit Committee):

Audit Title Date of Assurance Number of Issue Level Recommendations January Incident Management Satisfactory 3 Medium, 1 Low 2019 Software Licence January Satisfactory 2 Medium, 1 Low Management 2019 NDR January Good 2 Low

Page 3 2019 Treasury Management March 2019 Good - 1 High, 2 Medium, 1 Agency Staff March 2019 Limited Low

2.3Details on the status of all audits in this year’s plan can be found in Appendix A.

2.4In respect of the 2018/19 plan, audits continue to be progressed in line with the agreed audit plan with 16 audits at final report stage, eight audits at draft report stage, four audits in fieldwork, and a further one audit at planning or allocated stage. Details of the status of all audits in this year’s plan can be found in Appendix A of this report.

Changes to Projected Audit Start Dates

2.5To help the Committee assess progress in delivering the 2018/19 Audit Plan, Appendix B details agreed start dates. These dates were agreed with management and resources allocated accordingly. This schedule was designed to facilitate smoother delivery of the audit plan through the year.

2.6There have been five days allocated from contingency to the follow up of recommendations. As a result, the contingency balance is currently 0 days.

2.7There are no proposed changes to audit start dates to be reported to the Committee.

Proposed Amendments to Audit Plan

2.8Since the September meeting of this Committee, there has not been any changes to the 2018/19 Audit Plan agreed with Officers of the Council.

High Priority Recommendations

2.9Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SHARED INTERNAL AUDIT SERVICE (SIAS) INTERNAL AUDIT PROGRESS REPORTReport 116 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
GM
Councillor George MichaelidesChairman, present
SM
Councillor Steven MarkiewiczVice-Chairman, present
JB
Councillor Jonathan BoultonCommittee Member, present
JB
Councillor James BroachCommittee Member, present
SR
Councillor Steve RobertsCommittee Member, present
SA
Councillor Simon Anthony WrennCommittee Member, present
PZ
Councillor Paul ZukowskyjCommittee Member, present
DB
Councillor Duncan BellGuest, in attendance
KN
Ka NgOfficer, apologies
RB
Richard BakerOfficer, in attendance
GP
Gurdip PaddanSecretary, in attendance
MC
Mark ChalkleyPublic, in attendance

On this subject at Welwyn Hatfield

Search all
  1. SHARED INTERNAL AUDIT SERVICE (SIAS) INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Shared Internal Audit Service - Progress Report 2025/26Noted
  3. Shared Internal Audit Service - Annual Audit Plan 2026/27Approved
  4. Shared internal audit service (sias) annual report 2024/25Noted
  5. Shared Internal Audit Service - Progress ReportNoted
  6. Shared internal audit service (sias) - progress reportNoted

More from Welwyn Hatfield Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. Noted Open
2 Sep 2026 Rebuilding assurance updateTo note the Rebuilding Assurance Update. Noted Open
2 Sep 2026 Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... Noted Open
2 Sep 2026 Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. Noted Open
2 Sep 2026 Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies