Resolved
It was resolved: To note the Shared Internal Audit Service Progress Report 2025/26
AI summaryWelwyn Hatfield's Audit Committee noted the Shared Internal Audit Service progress report for 2025/26, with 89% of planned audit days delivered by 4 March 2026 and 18 of 24 audits at draft or final report stage.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
It was resolved: To note the Shared Internal Audit Service Progress Report 2025/26
Members are recommended to: • Note the Internal Audit Progress Report for the period to 4 March 2026.
Page 1 Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.5 Medium Priority Recommendations 2.6 Proposed Amendments 2.7 Performance Management
A Progress against the 2025/26 Audit Plan
B 2025/26 Audit Plan Start Dates Agreed with Management
C Assurance and Findings Definitions 2025/26
Page 2 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Internal Audit Plan for 2025/26 as at 4 March 2026. b) The implementation status of previously agreed audit recommendations. c) An update on performance indicators as at 4 March 2026.
1.2The 2025/26 Internal Audit Plan was approved by the Audit Committee on 24 March 2025.
1.3The Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the final update report for 2025/26 on the delivery of the Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 4 March 2026, 89% of the 2025/26 Audit Plan days had been delivered.
2.2There have been two final audit reports issued since the previous progress report.
Audit Title Assurance Opinion Recommendations Equality Impact Reasonable 3 Advisory Actions Assessments Chatbot Maintenance Reasonable 2 Medium Priority and Quality Assurance
High Priority Recommendations
2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to
Page 3 Members’ attention the implementation status of high priority recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.
2.4No new high priority recommendations have been raised as a result of the work completed and reported in the table at paragraph 2.2. Therefore, there are no outstanding high priority recommendations.
Medium Priority Recommendations
2.5It has been agreed with Council management that SIAS will follow up all medium priority recommendations resulting from internal audit reports at the point that they reach the implementation target date advised in the action plan provided by management. There were no medium priority recommendations due for follow up during this cycle as implementation target dates were not yet due.
Proposed Amendments
2.6There are no plan amendments proposed within this reporting period.
Performance Management: Reporting of Audit Plan Delivery Progress
2.7To help the Committee assess the current progress of the projects in the Audit Plan, we have provided an overall progress update of delivery against planned commencement dates at Appendix B. The table below shows that summary of performance based in the latest performance information reported at Appendix A.
No of % of Total Profile to 4 Status Audits at Audits March 2026 this Stage Draft / Final Report Issued 18 75% (20/24) In Fieldwork / Quality Review 6 25% (4/24) Terms of Reference Issued / In Planning 0 0% (0/24) Not Yet Started 0 0% (0/24)
2.8Annual performance indicators and associated targets were approved by the SIAS Board in March 2025. As at 4 March 2026, actual performance for Welwyn Hatfield Borough Council against the targets that can be monitored in year was as shown in the table below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared Internal Audit Service: Progress Report 2025/26Report | 357 KB | DownloadRead as text |
Follow Audit Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. | Noted | Open |
| 2 Sep 2026 | Rebuilding assurance updateTo note the Rebuilding Assurance Update. | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. | Noted | Open |
| 2 Sep 2026 | Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.