Resolved
The Cabinet approved the continued appointment of Bevan Brittan LLP by calling off the Estates Management Lawshare Framework to provide legal services to the Council in support of the Welwyn Garden City Town Centre North re-development.
Cabinet approved this item on Tuesday 9 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet approved the continued appointment of Bevan Brittan LLP by calling off the Estates Management Lawshare Framework to provide legal services to the Council in support of the Welwyn Garden City Town Centre North re-development.
1.1The Council has appointed a broad consultant team to prepare a Supplementary Planning Document (SPD) and Delivery Plan for the redevelopment of Welwyn Garden City Town Centre North.
1.2An urgent need for legal assistance has been identified to review the title for the site, comment on leases, rights and general property matters.
1.3Through comparisons with another legal firm Bevan Brittan demonstrated best value in their fee estimate based on a defined scope for stage 1 of the project. Bevan Brittan, in agreement with the Council’s in-house Legal Services, have had a limited appointment made by calling off the EM Lawshare framework.
1.4At this point in time the detailed scope of later stages of the development are not fully known; however it would be beneficial to continue using Bevan Brittan for the latter stages of the project.
1.5It is requested to continue to call off the EM Lawshare agreement which is compliant with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015.
1.6The General Procurement Board discussed this item at its meeting on 5th June and it was agreed to recommend to Cabinet to make a direct award to Bevan Brittan utilising the EM Lawshare framework.
2 Recommendation(s)
2.1That Cabinet approve the continued appointment of Bevan Brittan LLP by calling off the EM Lawshare Framework, as set out in this report, to provide legal services to the Council in support of the Welwyn Garden City Town Centre North re-development.
-1- 3 Explanation
3.1A broad consultant team (Inner Circle Consulting) has been appointed to commence work on a Supplementary Planning Document and Delivery Plan for the redevelopment of Welwyn Garden City Town Centre North.
3.2There is an urgent need for legal assistance to review the title for the site, comment on leases, rights and general property matters. To this end comparisons have been made between two experienced Legal Firms who have represented the council in similar development opportunities in the past (Capsticks LLP and Bevan Brittan LLP).
3.3Bevan Brittan has demonstrated best value in their fee estimate based on a defined scope for stage 1 of the project. Bevan Brittan, in agreement with the Council’s in-house Legal Services, were appointed by calling off the EM Lawshare framework.
3.4Unfortunately it is not possible, at this stage, to scope out the later stages of the development. However, it would be beneficial to continue using Bevan Brittan for the latter stages of the project. This is because any other firm would need time, which would result in repeated fee expenditure, to get up to speed. It is, therefore, considered appropriate to use the EM Lawshare framework to make a direct award to Bevan Brittan, making use of the competitive rates which have been offered.
3.5It is likely that a WGC Town Centre North will need its own Procurement Board in the future to oversee the developer partner(s) procurement process.
3.6It is requested to continue to call off the EM Lawshare agreement which is compliant with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015.
3.7Budgets are in place to account for the commission.
3.8There will be break clauses in the Contract as set out in the agreed terms of business between the Council and Bevan Brittan.
4 Implications
Legal Implication(s)
4.1The EM Lawshare Framework was set up following a full European procurement process. On this basis and provided that there is compliance with the provisions of the Framework, the requirements of relevant European procurement rules and the Council’s Contract Procedure Rules will be met.
4.2The General Procurement Board have approved the proposed appointment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of Contract for Legal Advice for Welwyn Garden City Town Centre North (Draw Down Request from the Estates Management Lawshare Framework) (Forward Plan Reference FP925)Forward_plan | 117 KB | DownloadRead as text |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.