Welwyn Hatfield Borough Council
Cabinet, Tuesday 10 February 2026 at 6.30pm

FP2227 Award of Contract for Inspection, Serving and Repair of Lifts and Stairlifts

Approved Executive 1 paper

AI summaryWelwyn Hatfield Cabinet awards a five year lifts and stairlifts contract to Stannah Lift Services, worth about £250,000 a year, starting 1 April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFive year contract, starts 1 April 2026
MoneyAbout £250,000 a yearAround 2% increase on current prices
What happens nextContract begins 1 April 2026Current contract ends March 2026
Who it affectsCouncil housing tenants19 passenger lifts and 109 stairlifts

What was decided

Cabinet approved the recommendation as set out in the report.

A five year contract was awarded to Stannah Lift Services Limited, starting on 1 April 2026. Report 2.1, 3.1

Why

The current contract for inspecting, servicing and repairing lifts and stairlifts expires at the end of March 2026, and a replacement is needed to keep the service running. Report 1.2, 3.1

The current provider, Stannah, knows the housing stock well and has delivered a good service, and a direct award through the Fusion 21 framework is compliant with procurement rules. Report 3.3, 3.4, 4.1, 8.1

What happens next

The contract begins on 1 April 2026, replacing the expiring arrangement. Report 2.1, 3.1

The council can end the contract after two years by giving three months notice, to allow flexibility once the new council structure in Hertfordshire is known. Report 3.5

The money

  • £250,000 per annum Approximate annual spend on the service Report 5.1
  • around 2% Estimated price increase compared with current prices Report 5.2

Options considered

  • Chosen: Direct award to Stannah Lift Services Limited via the Fusion 21 framework for five years. Stannah already provides the service, knows the stock, and the framework route is compliant with procurement rules Report 2.1, 3.3, 3.4, 4.1, 8.1

Implications

  • Legal: The direct award to Stannah using the Fusion 21 framework is compliant with the council's Contract Procedure Rules and the Public Contracts Regulations 2015. Report 4.1, 8.1
  • Financial: Annual spend is about £250,000, with an expected price increase of around 2% on current prices. Report 5.1, 5.2
  • Risk: The risk of a procurement challenge is low because the framework is compliant. Operating risks will be managed between the contractor and the council. Report 6.1, 6.2
  • Climate: The contract will be let in line with the council's sustainable procurement approach. Report 9.1
  • Staffing: No direct human resource implications: all staff delivering the service will be employed by Stannah. Report 10.1
  • Other: No security and terrorism implications, health and wellbeing implications, or communication and engagement implications are identified. Report 7.1, 11.1

Who and where

  • Council housing tenants using the 19 passenger lifts and 109 stairlifts in the housing stock Report 3.2
  • The existing contractor, Stannah Lift Services, which will continue under a new contract Report 3.3

Timeline

  • March 2026: Current contract expires Report 1.2, 3.1
  • 1st April 2026: New five year contract with Stannah Lift Services begins Report 2.1
  • After 2 years (from 1 April 2026): Council may terminate the contract on three months notice Report 3.5

Plain English for the jargon

  • Fusion 21: A social enterprise that runs public sector procurement frameworks, including one for lifts that allows compliant direct awards.
  • Direct award: Awarding a contract to a supplier through an existing framework without a further competitive tender.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item550

Resolved

Decision taken Cabinet approved the recommendation as set out in the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Council has a number of stairlifts and passenger lifts in it’s housing stock and requires for them to maintained, inspected and installed by a competent contractor

1.2The current contract expires in March 2026 and a new contract is required to ensure continuity of service.

2 Recommendation(s)

2.1That a 5-year contract is awarded to Stannah Lift Services Limited commencing on 1st April 2026

3 Explanation

3.1The contract for inspection, servicing and repair of both stairlifts and passenger lifts expires at the end of March 2026 and a replacement contract is required to ensure continuity. The contract also includes the installation of new lifts.

3.2There are currently 19 passenger lifts and 109 stairlifts.

3.3Stannah Lift Services (Stannah) currently provide the services. The have provided a good service and know the stock well.

3.4Fusion 21 are a social enterprise specialising in public sector procurement through a framework approach. They have a compliant framework for lifts that allows a direct award to Stannah

3.5Whilst the contract would be for a maximum of 5 years, there would be a clause that would allow for termination at any other time after 2 years with three months notice. This would allow contractual flexibility when the new council structure in Hertfordshire is known.

Implications

4 Legal Implication(s)

4.1The direct award to Stannah, using the Fusion 21 framework is compliant with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015.

-1- 5 Financial Implication(s)

5.1The spend on the services is approximately £250,000 per annum

5.2An analysis of the current prices compared with the Fusion 21 framework prices show and increase of around 2%.

6 Risk Management Implications

6.1The risk of procurement challenge is low due to the compliance of the framework

6.2There are risks of operating the service that will be managed by the contractor and the council

7 Security and Terrorism Implication(s)

7.1None directly associated with this recommendation

8 Procurement Implication(s)

8.1The direct award to Stannah, using the Fusion 21 framework is compliant with the Council’s Contract Procedure Rules and the Public Contracts Regulations 2015.

9 Climate Change Implication(s)

9.1The contract would be let in accordance with the Procurement and Commercial Strategy sustainable procurement

10 Human Resources Implication(s)

10.1There are no direct human resource implications associated with the recommendation as all staff would be employed by Stannah.

11 Health and Wellbeing Implication(s)

There are no direct health and wellbeing implications associated with this recommendation.

11.1Communication and Engagement Implication(s)

There are no communication and engagement implications associated with this recommendation.

12.1Link to Corporate Priorities

11.1The recommendation is linked to the corporate priority – homes to be proud of.

12 Equality and Diversity

14.1An Equality Impact Assessment has not been undertaken as there are no proposed changes to the service

Name of author: Andrew Harper Job Title : Procurement Manager -2- Date: 05/01/2026

-3-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FP2227 Award of Contract for Inspection, Serving and Repair of Lifts and StairliftsReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
BC
Bernice ComptonOfficer, in attendance
RM
Roxanne MisirSecretary, apologies
SB
Councillor Sandreni BonfanteCommittee Member, present
JB
Councillor James BroachCommittee Member, absent
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, apologies
JH
Jenny HowellOfficer, apologies
MS
Michael SherryCouncil Staff, in attendance
CC
Clare CadeOfficer, in attendance

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. FP2227 Award of Contract for Inspection, Serving and Repair of Lifts and StairliftsThis decision
  2. Fp2262 direct award of contract for embankment work at stanborough lakesDecided
  3. FP2208 Award of Contract for Cyclical DecorationsDecided
  4. FP2229 Award of Contract for Roofing Systems and Associated Works to Council Housing BlocksAgreed
  5. FP2171 Award of Contract for Damp and Mould Remediation Works and Legal Housing Disrepair WorksAgreed
  6. FP2169 Award of Contract for Void Refurbishment WorkAgreed

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open