Resolved
That the contents of the report be noted.
Audit Committee noted this item on Monday 22 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
A Progress against the 2020/21 Audit Plan
B 2020/21 Audit Plan Start Dates Agreed with Management
C Implementation Status of Outstanding Medium Priority Recommendations as at 5 March 2021
D Assurance and Finding Definitions 2020/21
Page 2 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2020/21 as at 5 March 2021. b) Details of changes to the planned start dates of audits from the approved 2020/21 Audit Plan. c) Proposed amendments to the 2020/21 Annual Audit Plan report. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information as at 5 March 2021.
1.2The 2020/21 Annual Audit Plan was approved by the Audit Committee at its meeting on 19 March 2020.
1.3The Audit Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the fourth report on the delivery of the 2020/21 Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed Annual Audit Plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 5 March 2021, 92% of the 2020/21 Audit Plan days had been delivered.
2.2The following final reports have been issued since 8 January 2021 (cut-off date for the SIAS Update Report for 20 January 2021 Audit Committee):
Audit Title Date of Issue Assurance Number of Level Recommendations Revenues February 2021 Good 1 Low
Treasury March 2021 Good None. Management
2.3To help the Committee assess progress in delivering the 2020/21 Audit Plan, Appendix B details agreed start dates. These dates were agreed with
Page 3 management and resources allocated accordingly. This schedule was designed to facilitate smoother delivery of the audit plan through the year.
Proposed Amendments to Audit Plan
2.4There have been no amendments made to the Audit Plan since the last Committee meeting in January 2021.
High Priority Recommendations
2.5Members will be aware that a Final Audit Report is issued when it has been agreed by management. This includes an agreement to implement the recommendations that have been made. It is Internal Audit’s responsibility to bring to Members’ attention the non-implementation of high priority recommendations. It is the responsibility of officers to implement the recommendations by the agreed date.
2.6There are no high priority recommendations that remain outstanding and we have not made any new high priority recommendations during 2020/21.
Medium Priority Recommendations
2.7From 1 April 2019, SIAS has assumed responsibility for the co-ordination of following up the implementation status of Internal Audit medium priority recommendations from the Council’s Principal Governance Officer. Internal Audit has worked with Council management to develop a database of audit recommendations, regardless of the recommendation priority, to monitor the implementation status and progress to date. It has been agreed with Council management that SIAS will follow up all recommendations made since 1 April 2018.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SHARED INTERNAL AUDIT SERVICE: PROGRESS REPORTReport | 277 KB | DownloadRead as text |
Follow Audit Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. | Noted | Open |
| 2 Sep 2026 | Rebuilding assurance updateTo note the Rebuilding Assurance Update. | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. | Noted | Open |
| 2 Sep 2026 | Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.