Award of Contract - Mechanical and Electrical Contracts (Forward Plan Reference FP1147)

Agreed Executive 1 paper

Cabinet agreed this item on Monday 31 October 2022. Below is the council's own wording, with the papers it was decided on.

Item49c

Resolved

(1) Cabinet agreed to award the contract for M&E Services to RGE Services Limited for a three year period with a possible extension of up to two years, commencing on 1 April 2023. (2) The award is, subject to conclusion of the 30 day leaseholder engagement period under Section 20 of the Landlord and Tenant Act 1985 (and regard being had of any representations) and subject to the expiry of the mandatory standstill period.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Main author: Andrew Harper Executive Member: Cllr Fiona Thomson All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 31 OCTOBER 2022 REPORT OF THE SERVICE DIRECTOR (PROPERTY MAINTENANCE AND CLIMATE CHANGE)

AWARD OF CONTRACT – M&E CONTRACTS

1 Executive Summary 1.1 Following agreement to amalgamate a number of Mechanical & Electrical (M&E) housing contracts a procurement exercise has been undertaken to appoint one Contractor to undertake the works.

2 Recommendation 2.1 That Cabinet agrees to award the contract for M&E Services to RGE Services Limited for a three year period with a possible extension of up to two years, commencing on 1st April 2023. 2.2 The award is, subject to conclusion of the 30 day leaseholder engagement period under Section 20 of the Landlord and Tenant Act 1985 (and regard being had of any representations) and subject to the expiry of the mandatory standstill period.

3 Explanation 3.1 In March 2022, The Executive Member for Housing agreed that the following contracts should not be extended, but the services combined into one procurement: • Door Entry Installations and Maintenance • Fire Alarm Maintenance • Communal Mechanical and Electrical works. 3.2 The Executive Member also agreed that the maximum contract duration would be 5 years and the tenders would be evaluated 50% on Quality and 50% on Price. 3.3 Following an advert, 7 applications were received. One of these companies failed to meet the minimum criteria. The other 6 proceeded to tender stage. 3.4 Of these 6, 5 companies returned tenders. 3.5 These tenders have been evaluated in accordance with the agreed criteria and the results can be found in the Part 2 report

Implications 4. Legal Implications 4.1 The recommendations in this report are in accordance with the Public Contracts Regulations 2015. 4.2 The requirements of the Landlord and Tenant Act 1985 and the mandatory standstill period are referenced in paragraph 2.2 of this report.

-1- 5. Financial Implication(s) 5.1 The estimated value of the service is £900,000.00 per annum. The costs will be met from current budget bids completed for 2023/2024 5.2 An analysis of the tenders is included in the Part 2 report

6. Risk Management Implications 6.1 As with all contracts over the relevant threshold, there is the risk of challenge from unsuccessful bidders. We have completed a full tender process and documented scored and moderation between the evaluators. This is a low risk if challenged. 6.2 Parts of this contract will involve completing essential Building Safety Compliance including communal electrical tests, emergency lighting, fire alarm systems, AOVs and sprinkler systems. There is a risk if the contract is delayed that these works will be affected.

7. Security & Terrorism Implication(s) 7.1 There are no security or terrorism implications with the recommendations in this report.

8. Procurement Implication(s) 8.1 The recommendation is in accordance with the Public Contracts Regulations 2015 and the contract procedure rules

9 Climate Change Implication(s) 9.1 None directly from this report.

10. Human Resources Implication(s) 10.1 There are none.

11. Health and Wellbeing Implication(s) 11.1 There are none.

12. Communication and Engagement Implication(s) 12.1 None directly from this report.

13. Link to Corporate Priorities 13.1 The recommendation contributes to the our priority ‘Quality homes through managed growth’, as well as more specifically our commitment to Provide high quality housing, thriving neighbourhoods and sustainable communities.

14. Equalities and Diversity 14.1 I confirm that an Equality Impact Assessment (EqIA) has not been carried out as here are no changes to the services being provided.

Name of author: Andrew Harper Title: Procurement Manager -2- Date: 30th September 2022

-3-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Contract: Mechanical and Electrical Contracts (Forward Plan Reference FP1147)Forward_plan 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
TK
Councillor Tony KingsburyChairman, present
SB
Councillor Stephen BoultonVice-Chairman, present
SK
Councillor Samuel KasumuCommittee Member, apologies
TM
Councillor Terry MitchinsonCommittee Member, present
NP
Councillor Nick PaceCommittee Member, present
BS
Councillor Bernard SarsonCommittee Member, present
FT
Councillor Fiona ThomsonCommittee Member, present
KN
Ka NgOfficer, in attendance
CB
Chris BarnesOfficer, in attendance
IH
Ian HancockOfficer, in attendance
SM
Sue McDaidOfficer, in attendance
MM
Margaret MartinusOfficer, in attendance

All 13 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Award of Contract - Mechanical and Electrical Contracts (Forward Plan Reference FP1147)This decision
  2. Fp2262 direct award of contract for embankment work at stanborough lakesDecided
  3. FP2208 Award of Contract for Cyclical DecorationsDecided
  4. FP2229 Award of Contract for Roofing Systems and Associated Works to Council Housing BlocksAgreed
  5. FP2227 Award of Contract for Inspection, Serving and Repair of Lifts and StairliftsApproved
  6. FP2171 Award of Contract for Damp and Mould Remediation Works and Legal Housing Disrepair WorksAgreed

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies