QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2024-25

Noted Executive 2 papers

Cabinet noted this item on Tuesday 4 February 2025. Below is the council's own wording, with the papers it was decided on.

Item363

Resolved

Cabinet received a report on the Quarter 3 Capital Budget Monitoring Report 2024/25. Decision taken Cabinet: 1. Noted: a) The capital forecast outturn positions. b) The forecast position as set out at 31 December 2024 for funding of the capital programme and reserve balances. 2. Approved the virements as set out in section 3.2 of the report. Reason for decision The report set out the capital expenditure and associated capital funding as at the end of Quarter 3 (December 2024). The report and appendices detailed the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr Astrid Scott All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 4 FEBRUARY 2025 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2024-25

1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 3 (December 2024). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £79.371m (which includes the approved re- phasing of budgets from 2023/24) and the forecast outturn is £55.666m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 31 December 2024 for funding of the capital programme and reserve balances as reflected in Table 2. 2.3 That Cabinet approve the virements set out in Section 3.2.

3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£

Original Budget £41.049m

Re-phasing from 2023/24 £38.322m Current Budget £79.371m 3.2 It is recommended that the following virements be approved:  That £1,200k from the AHP – New Schemes budget (App A ref. 65) be vired to the AHP – Open Market Purchases budget (App A ref. 53) to fund the purchases that are due to be made in this financial year.  That £200k from the Heating Replacement Programme budget (App A ref. 70) be vired to the Smoke and Carbon Monoxide Alarms budget (App A ref. 69) to fund the overspend on this project. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2024/25 by Fund and Directorate

Re- phasing Forecast (Under)/ Budget Variance of Outturn Over 2024/25 to Budget Capital 2024/25 Outturn Scheme s

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 647 645 (1) 0 (1) Executive Director (Place) 6,700 4,817 (1,883) 1,463 (421) Executive Director (Resident Services and Climate Change) 1,774 1,302 (472) 48 (424)

General Fund Total 9,121 6,764 (2,357) 1,511 (846) Housing Revenue Account Executive Director (Place) 19,916 6,339 (13,577) 14,687 1,110 Executive Director (Res Services and Climate Change) 50,334 42,562 (7,772) 5,975 (1,797) Housing Revenue Account Total 70,250 48,901 (21,349) 20,662 (687)

Grand TOTAL 79,371 55,666 (23,706) 22,173 (1,533) 3.4 There is currently a requirement to rephase £22.173m split between funds as follows: General Fund £1.511m – rephase budget into 2025/26 HRA £20.662m – rephase budget into 2025/26 Total net rephasing - £22.173m

3.5Key forecast variances are outlined below:

General Fund:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
quarter 3 capital monitoring 2024-25Appendix A 107 KB Download
PDF
QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2024-25Report 320 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
BC
Bernice ComptonSecretary, expected
RM
Roxanne MisirSecretary, expected
SB
Councillor Sandreni BonfanteCommittee Member, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
SS
Sheila SaundersOfficer, expected
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeSecretary, expected

All 19 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2024-25This decision
  2. Quarter 1 capital monitoring report 2026/27Noted
  3. Quarter 1 Capital Budget Monitoring ReportNoted
  4. Quarter 3 Capital Budget Monitoring Report 2023-24Noted
  5. Capital budget monitoring report - quarter 2Decided
  6. Capital monitoring report 2022-23 - quarter 3Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies