Cabinet received a report on the Quarter 3 Capital Budget Monitoring Report 2024/25. Decision taken Cabinet: 1. Noted: a) The capital forecast outturn positions. b) The forecast position as set out at 31 December 2024 for funding of the capital programme and reserve balances. 2. Approved the virements as set out in section 3.2 of the report. Reason for decision The report set out the capital expenditure and associated capital funding as at the end of Quarter 3 (December 2024). The report and appendices detailed the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr Astrid Scott All Wards
WELWYN HATFIELD BOROUGH COUNCIL CABINET – 4 FEBRUARY 2025 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)
QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2024-25
1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 3 (December 2024). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £79.371m (which includes the approved re- phasing of budgets from 2023/24) and the forecast outturn is £55.666m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.
2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 31 December 2024 for funding of the capital programme and reserve balances as reflected in Table 2. 2.3 That Cabinet approve the virements set out in Section 3.2.
3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).
£
Original Budget £41.049m
Re-phasing from 2023/24 £38.322m Current Budget £79.371m 3.2 It is recommended that the following virements be approved: That £1,200k from the AHP – New Schemes budget (App A ref. 65) be vired to the AHP – Open Market Purchases budget (App A ref. 53) to fund the purchases that are due to be made in this financial year. That £200k from the Heating Replacement Programme budget (App A ref. 70) be vired to the Smoke and Carbon Monoxide Alarms budget (App A ref. 69) to fund the overspend on this project. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2024/25 by Fund and Directorate
Re- phasing Forecast (Under)/ Budget Variance of Outturn Over 2024/25 to Budget Capital 2024/25 Outturn Scheme s
£'000 £'000 £'000 £'000 £'000
General Fund Executive Director (Finance and Transformation) 647 645 (1) 0 (1) Executive Director (Place) 6,700 4,817 (1,883) 1,463 (421) Executive Director (Resident Services and Climate Change) 1,774 1,302 (472) 48 (424)
General Fund Total 9,121 6,764 (2,357) 1,511 (846) Housing Revenue Account Executive Director (Place) 19,916 6,339 (13,577) 14,687 1,110 Executive Director (Res Services and Climate Change) 50,334 42,562 (7,772) 5,975 (1,797) Housing Revenue Account Total 70,250 48,901 (21,349) 20,662 (687)
Grand TOTAL 79,371 55,666 (23,706) 22,173 (1,533) 3.4 There is currently a requirement to rephase £22.173m split between funds as follows: General Fund £1.511m – rephase budget into 2025/26 HRA £20.662m – rephase budget into 2025/26 Total net rephasing - £22.173m
3.5Key forecast variances are outlined below:
General Fund:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.