Welwyn Hatfield Borough Council
Cabinet, Tuesday 5 August 2025 at 6.30pm

Quarter 1 Capital Budget Monitoring Report

Noted Executive 2 papers

Cabinet noted this item on Tuesday 5 August 2025. Below is the council's own wording, with the papers it was decided on.

Item449

Resolved

Decision taken Cabinet: a) Noted the capital forecast outturn position as shown in Table 1. b) Noted the forecast position as at 30 June 2025 for funding of the capital programme and reserve balances as reflected in Table 2. c) Approved the virements set out in Section 3.2 of the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr Astrid Scott All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 5 AUGUST 2025 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

QUARTER 1 CAPITAL BUDGET MONITORING REPORT 2025-26

1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 1 (June 2025). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £85.189m (which includes the approved re- phasing of budgets from 2024/25) and the forecast outturn is £85.253m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 30 June 2025 for funding of the capital programme and reserve balances as reflected in Table 2. 2.3 That Cabinet approve the virements set out in Section 3.2.

3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£ Original Budget £55.990m

Re-phasing from 2024/25 £29.199m Current Budget £85.189m 3.2 It is recommended that the following virements be approved: • That £0.073m from the Hatfield Town Centre Public Realm budget (App A ref. 8) and £0.200m from the Play Area Replacement Scheme budget (App A ref. 12) be vired to the Hatfield Town Centre Marketplace budget (App A ref. 17) to fund the Hatfield regeneration project. • That £0.240m from the Asbestos budget (App A ref. 61) is vired to the Insulation Improvements budget (App A ref. 51) to cover a higher level of damp and mould works than budgeted. It is likely that overspends on this project will increase throughout the year and additional budget will look to be vired if required. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2025/26 by Fund and Directorate

Re- Variance phasing (Under)/ Budget Outturn to of Over 2025/26 2025/26 Budget Capital Budget Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 229 229 0 0 0

Executive Director (Place) 3,258 3,322 64 0 64 Executive Director (Resident Services and Climate Change) 2,027 2,027 0 0 0

General Fund Total 5,514 5,578 64 0 64 Housing Revenue Account

Executive Director (Place) 17,690 17,690 0 0 0 Executive Director (Res Services and Climate Change) 61,985 61,985 0 0 0 Housing Revenue Account Total 79,675 79,675 0 0 0

Grand TOTAL 85,189 85,253 64 0 64 3.4 There is currently no rephasing identified.

3.5Key forecast variances are outlined below: General Fund: 3.5.1 There are currently no key forecast variances identified. 3.5.2 Overspends There are a number of projects with small overspends which are listed below. All of these overspends will be funded by borrowing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 1 Capital Budget Monitoring ReportReport 208 KB DownloadRead as text
PDF
item 13: appendix a q1 capital monitor 2025-26Appendix 175 KB Download

At this meeting

Whole meeting

Who was there

7 of 18 attended
AS
Councillor Astrid ScottCommittee Member, present
BC
Bernice ComptonOfficer, in attendance
RM
Roxanne MisirSecretary, absent
SB
Councillor Sandreni BonfanteCommittee Member, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, apologies
HO
Helen O'KeeffeOfficer, in attendance
JH
Jenny HowellOfficer, absent
MS
Michael SherryOfficer, in attendance
SM
Sue McDaidOfficer, in attendance

All 18 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Quarter 1 Capital Budget Monitoring ReportThis decision
  2. Quarter 1 capital monitoring report 2026/27Noted
  3. Quarter 3 capital budget monitoring report 2024-25Noted
  4. Quarter 3 Capital Budget Monitoring Report 2023-24Noted
  5. Capital budget monitoring report - quarter 2Decided
  6. Capital monitoring report 2022-23 - quarter 3Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open