SHARED INTERNAL AUDIT SERVICE (SIAS) - ANNUAL ASSURANCE STATEMENT AND INTERNAL AUDIT REPORT 2024/25

Noted Finance 1 paper

Audit Committee noted this item on Wednesday 25 June 2025. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

RESOLVED The Committee: - Noted the Annual Assurance Statement and Internal Audit Annual Report 2024/25 - Noted the results of the self-assessment required by the Global Internal Audit Standards (GIAS) and the Quality Assurance and Improvement Programme (QAIP) - Approved the SIAS Audit Charter 2025/26; and - Noted management assurance that the scope and resources for internal audit were not subject to inappropriate limitations in 2024/25.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Audit Committee

Recommendations

Members are recommended to:

Note the Annual Assurance Statement and Internal Audit Annual Report 2024/25

Note the results of the self-assessment required by the Global Internal Audit Standards (GIAS) and the Quality Assurance and Improvement Programme (QAIP)

Approve the SIAS Audit Charter 2025/26

Seek management assurance that the scope and resources for internal audit were not subject to inappropriate limitations in 2024/25

1 Annual Assurance Statement and Internal Audit Annual Report 2024/25

Contents 1. Purpose and Background 1.1 Purpose 1.2 Background

2. Annual Assurance Statement for 2024/25 2.1 Assurance Opinion on Internal Control 2.2 Context 2.3 Control Environment 2.4 Review of Effectiveness - compliance with the GIAS and QAIP 2.12 Confirmation of independence of internal audit and assurance on limitations 2.13 Assurance Opinion on Corporate Governance and Risk Management

3. Overview of Internal Audit Activity at the Council in 2024/25

4. Performance of the Internal Audit Service in 2024/25 4.1 Performance Indicators 4.2 Service Developments

5. Audit Charter 2025/26

Appendices

A Final position against the Council’s 2024/25 Internal Audit Plan

B Definitions of Assurance Recommendation Priority Levels 2024/25

C Action Plan Arising from the Global Internal Audit Standards Self-Assessment as of May 2025

D Internal Audit Charter 2025/26

2 Annual Assurance Statement and Internal Audit Annual Report 2024/25

1. Purpose and Background Purpose of Report

1.1This report:

a) Details the Shared Internal Audit Service’s (SIAS) overall opinion on the adequacy and effectiveness of Welwyn Hatfield Borough Council’s (the Council) framework of governance, risk management and control. Reference is made to significant matters and key themes. b) Shows the outcomes of the self-assessment against the Global Internal Audit Standards (GIAS) incorporating the requirements of the Quality Assurance and Improvement Programme (QAIP). c) Summarises the internal audit work that informs this opinion. d) Shows SIAS performance in respect of delivering the Council’s internal audit plan. e) Presents the 2025/26 Audit Charter for approval.

Background

1.2The purpose of internal audit is to strengthen the Council’s ability to create, protect, and sustain value by providing Members and management with independent, risk-based, and objective assurance, advice, insight, and foresight.

1.3A key duty of the Chief Audit Executive (CAE - the Council’s Client Audit Manager) is to provide an annual internal audit opinion, concluding on the overall adequacy and effectiveness of the Council’s framework of governance, risk management and control. This opinion informs the conclusions of the Council’s Annual Governance Statement.

1.4The assurance opinion in this report is based on the 2024/25 internal audit work which was planned and amended to give sufficient assurance on the Council’s management of its key risks. Also considered is any relevant work undertaken in 2025/26 before the Audit Committee report deadline.

1.5The audit plan remained dynamic during the year, with plan changes made to reflect the changing risks of the Council, or pace of transformation or change that would impact on the value of audits originally included in the plan. All plan changes during 2024/25 were communicated to, and approved by, the Audit Committee within the SIAS progress reports.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SHARED INTERNAL AUDIT SERVICE (SIAS): ANNUAL ASSURANCE STATEMENT AND INTERNAL AUDIT REPORT 2024/25Report 602 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
IW
Ian WinterCo-Optee, present
BC
Bernice ComptonSecretary, expected
RM
Roxanne MisirOfficer, in attendance
CW
Councillor Cathy WatsonVice-Chairman, present
RP
Councillor Russ PlattCommittee Member, apologies, sent representative
KN
Ka NgOfficer, expected
RB
Richard BakerOfficer, expected
HO
Helen O'KeeffeOfficer, in attendance
SS
Sheila SaundersOfficer, expected
KF
Katie FullerPublic, in attendance
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeOfficer, expected

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. SHARED INTERNAL AUDIT SERVICE (SIAS) - ANNUAL ASSURANCE STATEMENT AND INTERNAL AUDIT REPORT 2024/25This decision
  2. Shared Internal Audit Service - Progress Report 2025/26Noted
  3. Shared Internal Audit Service - Annual Audit Plan 2026/27Approved
  4. Shared internal audit service (sias) annual report 2024/25Noted
  5. Shared Internal Audit Service - Progress ReportNoted
  6. Shared internal audit service (sias) - progress reportNoted

More from Welwyn Hatfield Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. Noted Open
2 Sep 2026 Rebuilding assurance updateTo note the Rebuilding Assurance Update. Noted Open
2 Sep 2026 Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... Noted Open
2 Sep 2026 Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. Noted Open
2 Sep 2026 Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. Noted Open