FP2169 Award of Contract for Void Refurbishment Work
AgreedExecutive1 paper
AI summaryCabinet awards a £1.1M void refurbishment contract to Hugh LS McConnel Limited via the Procurement for Housing framework, running from 20 October 2025 to 18 October 2026 with a possible year extension.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedto Hugh LS McConnel Limited for void refurbishment
Money£1.1Mexpected spend on void refurbishment works
What happens next20 October 2025contract start, ending 18 October 2026
Who it affectsCouncil tenants and applicantswaiting for empty homes to be relet
What was decided
Cabinet agreed to award a contract to Hugh LS McConnel Limited under lot 17 (Whole House Works) of the Procurement for Housing framework to refurbish void properties. Report 2.1
The contract will run from 20 October 2025 to 18 October 2026, with a possible one-year extension to 24 October 2027.
Why
The current contractor cannot provide the capacity to refurbish voids in the required timescales, leaving more empty properties than usual.
The contractor's tender was the most economically advantageous under the framework, allowing direct award without a fresh competition.
Refurbishment is needed to bring empty homes back into use quickly for tenants. Report 1.1
What happens next
Works should start from October 2025 using the direct award, avoiding the extra 2 to 3 months that a further competition or open tender would add.
The decision is subject to call-in by the Council's Overview and Scrutiny Committee, and performance and costs will be monitored against approved budgets. Report 6.1, 8.1
The money
£1.1M expected spend on void refurbishment works, covered within current budget Report 5.1
Options considered
Chosen: Direct award under existing framework to Hugh LS McConnel Limited. Most economically advantageous tender and avoids 2 to 3 month delay of further competition
Rejected: Run a further competition under the framework. Would add 2 to 3 months, delaying work to address outstanding voids
Rejected: Run an open tender. Would add 2 to 3 months, delaying work to address outstanding voids
Implications
Legal: Cabinet approval required because the contract value is anticipated to exceed £1 million under the Council's Contract Standing Orders, with use of the framework permitted under the Public Contracts Regulations 2015. Report 4.1
Financial: Expected spend of £1.1M on void refurbishments, to be contained within the current budget, with the final cost depending on the number of voids completed. Report 5.1
Risk: Contractor performance and costs will be monitored to ensure works meet required standards and approved budgets. Report 6.1
Climate: No direct climate implications, but the contractor is expected to use energy efficient methods and contribute to reducing carbon emissions.
Who and where
Council tenants waiting to be housed in void properties Report 1.1
Applicants on the housing list
Existing contractor unable to provide required capacity
Timeline
April 2024: Procurement for Housing framework agreement established Report 3.1
5 September 2025: Report authored by Assistant Director Homes and Neighbourhoods Report P15
7 October 2025: Cabinet decision to award contract Report P1
20 October 2025: Contract intended to commence
18 October 2026: Contract intended to terminate
24 October 2027: Possible end date if one-year extension taken up
Plain English for the jargon
Void property: A council home that is empty between tenancies and needs work before it can be relet.
Lot 17 (Whole House Works): A section of the Procurement for Housing framework covering full refurbishment of residential properties.
Direct award: Appointing a contractor from a framework without running a new competition.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item477
Resolved
Decision taken That Cabinet agreed to award a contract to Hugh LS McConnel Limited for the provision of building works and services under lot 17 of the Framework (Whole House Works) to fulfil the Council’s requirements to refurbish void properties.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Main author: Janice White Executive Member: Cllr Gemma Moore All Wards WELWYN HATFIELD BOROUGH COUNCIL CABINET – 7 OCTOBER 2025 REPORT OF EXECUTIVE DIRECTOR (RESIDENT SERVICES AND CLIMATE CHANGE)
AWARD OF CONTRACT FOR VOID REFURBISHMENT WORKS 1 Executive Summary
1.1On an ongoing basis, the Council has a number of void properties that are awaiting refurbishment before the Council can let the same to tenants. 1.2 In order that the Council can maximise the number of homes available to let, it is important for the Council to ensure that void properties are refurbished in good time and made available for housing. 1.3 Depending on need, refurbishment works would typically include the installation of kitchens and bathrooms and associated works; installation of windows, doors, roofing and related works; electrical and heating works; decorating; and building works. 1.4 Currently, the number of void properties is higher than usual primarily because the Council’s contractor is unable to provide the capacity to undertake refurbishments within the required timescales. 1.5 For the Council to meet its objectives, the Council requires the appointment of a building services contractor to provide additional resources. 1.6 The intention is for the contract to commence on 20 October 2025 and terminate on 18 October 2026, with the possibility of a one-year extension until 24 October 2027. This would assist with the immediate need to progress void refurbishments in good time but also allow for further resilience and options should the Council extend the contract. 2 Recommendation.
2.1That Cabinet agrees to award a contract to Hugh LS McConnel Limited for the provision of building works and services under lot 17 of the Framework (Whole House Works) to fulfil the Council’s requirements to refurbish void properties. 3 Explanation
3.1The recommended contractor is available for appointment via a framework agreement established in April 2024 by Procurement for Housing. 3.2 The framework agreement comprises of several lots for various building services and works and the appropriate lot of the Council’s requirements is lot 17 (Whole House Works) 3.3 The contractor’s tender submission for the framework has been evaluated as the most economically advantageous tender against all other tender submissions. 3.4 In accordance with the rules of the framework, the Council may proceed to appoint -1- the contractor by direct award. 3.5 The appointment of the contractor via the framework should enable works to be undertaken from October this year. The alternatives would be to appoint a contractor via a further competition under the framework or an open tender which would add 2 or 3 months to the process. Officers consider this additional time would be material in terms of progressing works that are now outstanding and meeting housing needs. 3.6 Further details including the tender evaluation and scores are included in the Part 2 (private and confidential) report. Implications 4 Legal Implications
4.1Under the Public Contracts Regulations 2015, the Council may use available frameworks to appoint contractors 4.2 Under the Council’s Contract Standing Orders, contract award is an Executive function because Cabinet must approve contracts with a value, or anticipated value, of more than £1 million. 4.3 The actual cost of works provided under the contract will depend on the number of void refurbishments completed by the contractor. 4.4 Further details are included in the Part 2 (private and confidential) report. 5 Financial Implications
5.1The contract payments will be included within the current budget. 5.2 We expect to spend £1.1M to in voids refurbishment works. 6 Risk Management Implications
6.1Performance and cost will require monitoring to ensure that the works meet the required standards and within approved budgets. 7 Security and Terrorism Implication(s)
7.1None directly associated with this recommendation. 8 Procurement Implication(s)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.