Welwyn Hatfield Borough Council
Audit Committee, Wednesday 17 June 2026 at 7.30pm

INTERNAL AUDIT (SIAS) PROGRESS REPORT 2026/27

Noted Finance 1 paper

AI summaryWelwyn Hatfield Audit Committee notes the 2026/27 internal audit progress, with 11% of plan delivered and one new high priority recommendation on data governance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted SIAS report and recommendation status
MoneyNot stated
What happens nextImplement new high priority recommendationCentralised data records by 31 December 2026
Who it affectsCouncil governance and data handlingInternal audit assurance across services

What was decided

The committee noted the Internal Audit Progress Report for the period to 3 June 2026. Report P1

The committee noted the implementation status of internal audit recommendations and the management update. Report P1

Why

The committee receives periodic updates on delivery of the annual internal audit plan as part of its corporate governance role. Report 1.3, 1.4

It is considered good practice for progress reports to include proposed amendments to the agreed annual audit plan. Report 1.4

What happens next

Officers will implement one new high priority recommendation to establish a centralised Record of Processing Activities and retention schedule by 31 December 2026. Report 2.4

SIAS will follow up outstanding medium priority recommendations at their target dates; no plan amendments are proposed this period. Report 2.5, 2.6

The Cabinet Housing Panel will consider a new Housing Excellence Plan on 18 June 2026, addressing a partially implemented housing consumer standards recommendation. Report P63

Options considered

  • Chosen: Note the progress report and recommendations status. Standard committee practice for monitoring internal audit delivery Report 1.4

Implications

  • Legal: The new high priority recommendation requires compliance with UK GDPR Article 30 on Records of Processing Activities. Report 2.4
  • Governance: Internal audit delivery is below profiled targets, with 11% of plan days complete against a 15% target and 8% of projects at draft report stage against a 12% target. Report 2.1, 2.8
  • Risk: The Data Governance audit received a Limited assurance opinion, with one high and three medium priority recommendations. Report P22
  • Staffing: Several medium priority recommendations remain partially implemented, including Orchard housing software rollout, CCTV PIA reviews and Body Worn Camera storage. Report P65, P69, P71

Who and where

  • Council officers responsible for data governance, housing compliance, asset management and CCTV operations Report 2.4, P65, P69, P71
  • Council tenants and residents, as outstanding recommendations relate to housing safety software, asset data and CCTV/body worn camera use Report P63, P65, P67, P69, P71

Timeline

  • 3 June 2026: Reporting date for the progress report Report 2.1
  • 18 June 2026: Cabinet Housing Panel to consider the new Housing Excellence Plan Report P63
  • 31 October 2026: Revised target date for completion of Orchard asset management software implementation Report P65
  • 31 December 2026: Target implementation date for the new high priority Data Governance recommendation Report 2.4

Plain English for the jargon

  • SIAS: Shared Internal Audit Service, the council's internal audit provider
  • RoPA: Record of Processing Activities, required under UK GDPR Article 30
  • CRA: Key Financial Systems audit area covering Cash, Revenues and Assets
  • BWC: Body Worn Camera
  • PID: Project Initiation Document, used in housing improvement planning
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item129

Resolved

a) Note the Internal Audit Progress Report for the period to 3 June 2026 b) Note the implementation status of internal audit recommendations and the management update.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to: • Note the Internal Audit Progress Report for the period to 3 June 2026 • Note the implementation status of internal audit recommendations and the management update.

Page 1 Agenda Item No: 7

Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.5 Medium Priority Recommendations 2.6 Proposed Amendments 2.7 Performance Management

Appendices

A Progress against the 2026/27 Audit Plan

B 2026/27 Audit Plan Start Dates Agreed with Management

C Implementation Status of Outstanding Medium Priority Recommendations

D Assurance and Findings Definitions 2026/27

Page 2 Agenda Item No: 7

1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Internal Audit Plan for 2026/27 as at 3 June 2026. b) In-Year Audit Plan review and proposed plan amendments. c) The implementation status of previously agreed audit recommendations. d) An update on performance indicators as at 3 June 2026.

Background

1.2The 2026/27 Internal Audit Plan was approved by the Audit Committee on 17 March 2026.

1.3The Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the first report giving an update on the delivery of the 2026/27 Internal Audit Plan.

1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1As at 3 June 2026, 11% of the 2026/27 Audit Plan days had been delivered.

2.2There have been 11 final audit reports that have been issued since the previous progress report, all relating to audits from the Council’s 2025/26 internal audit plan. The outcomes of these have been reported in the SIAS Annual Assurance Statement and Annual Report 2025/26, also on the agenda for this Committee, but for completeness are as follows:

Audit Title Assurance Opinion Recommendations Safeguarding Reasonable 3 Advisory Actions Pre Employment Reasonable 1 Low, 3 Advisory Checks Payroll CRA Substantial None Planning Enforcement Reasonable 2 Low, 1 Advisory Authorisations for Reasonable 2 Low, 3 Advisory Enforcement Powers

Page 3 Agenda Item No: 7

Audit Title Assurance Opinion Recommendations Treasury Management Substantial None Data Governance Limited 1 High, 3 Medium Voids Reasonable 1 Low, 2 Advisory Housing Options Grant Reasonable 4 Low, 1 Advisory and Funding Schemes Council Tax Reasonable 2 Low, 1 Advisory Business Rates Reasonable 3 Low, 1 Advisory

High Priority Recommendations

2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.

2.4One new high priority recommendation has been raised as a result of the work completed and reported in the table at paragraph 2.2. This relates to the Data Governance audit and recommends establishing and maintaining a centralised Record of Processing Activities (RoPA) and retention schedule that consolidates service-level information into a single, standardised and regularly reviewed organisational record that is in line with UK GDPR Article 30 requirements. This recommendation has a target implementation date of 31 December 2026.

Medium Priority Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT (SIAS) PROGRESS REPORT 2026/27Report 389 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 13 attended
NJ
Nick JenningsPublic, expected
IW
Ian WinterCo-Optee, expected
DJ
Councillor Duncan JonesChair, present
MH
Councillor Matthew HobbsVice-Chairman, present
GM
Councillor George MichaelidesCommittee Member, present
LR
Councillor Lewis RossCommittee Member, present
VS
Councillor Vaishali ShahCommittee Member, present
KN
Ka NgOfficer, expected
RB
Richard BakerOfficer, expected
HO
Helen O'KeeffeOfficer, expected
KF
Katie FullerPublic, expected
MS
Michael SherryCouncil Staff, expected

All 13 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. INTERNAL AUDIT (SIAS) PROGRESS REPORT 2026/27This decision
  2. Internal audit (sias) - progress report 2026/27Noted
  3. Internal audit (sias) - annual report 2025/26Noted
  4. Internal audit (sias) annual assurance statement and audit report 2025/26Noted
  5. Shared Internal Audit Service - Progress Report 2025/26Noted
  6. Shared Internal Audit Service - Annual Audit Plan 2026/27Approved

More from Welwyn Hatfield Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. Noted Open
2 Sep 2026 Rebuilding assurance updateTo note the Rebuilding Assurance Update. Noted Open
2 Sep 2026 Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... Noted Open
2 Sep 2026 Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. Noted Open