CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
West Lancashire Borough Council
Cabinet, Tuesday 13 September 2016 at 7.00pm

Capital Programme Outturn 2015-16

Noted Executive 5 papers

Cabinet noted this item on Tuesday 13 September 2016. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

RESOLVED (A) That the final position, including slippage, on the Capital Programme for the 2015/2016 financial year be noted and endorsed. (B) That call-in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 29 September 2016.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To provide a summary of the capital outturn position for the 2015/2016 financial year.

2.0RECOMMENDATIONS TO CABINET

2.1That the final position, including slippage, on the Capital Programme for the 2015/2016 financial year be noted and endorsed.

2.2That Call In is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 29th September 2016.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE

3.1That the final position on the Capital Programme for the 2015/2016 financial year be noted.

Background

4.1Members have been kept informed of the financial position of the Capital Programme with regular monitoring reports. This report provides Members with the final position on capital schemes for the 2015/2016 financial year. 4.2 It should be noted that the final accounts for the 2015/2016 year are subject to audit and the figures contained in this report are, potentially, subject to change. However, the Audit is nearing completion and no issues have been raised on the capital programme to date. Members will be informed in due course of any significant matters arising from the Audit.

4.3The position on the current year’s Programme for 2016/2017 is discussed elsewhere on this Agenda.

5.0CAPITAL PROGRAMME

5.1The Capital Programme of £26.661m at the end of the 2015/2016 financial year is analysed by Service in Appendix A. The key result for the year is that good progress has been made in delivering schemes.

5.2The total capital expenditure for 2015/2016 was £17.470m which represents 66% of the total Budget for the year. This is slightly lower than recent programmes as indicated in Table 1:

Table 1: Capital Expenditure against Budgets Expenditure Budget % Spend Year £m £m against Budget 2015/2016 17.470 26.661 66% 2014/2015 13.102 17.386 75% 2013/2014 15.129 19.503 78% 2012/2013 10.241 13.362 77%

5.3In total spending was £4.3m more than 2014/2015 and £2.3m more than 2013/2014. However the percentage spend of 66% was lower than expectation and trend, mainly due to reduced expenditure on the Solar Panel Programme as a result of changes in Government rules on the amount to be paid for Solar PV energy, which was outside the control of the Council. The largest single area is the Housing Public Sector which achieved a total spend of £12.3m or 74% of its budget in 2015/16, compared to a total spend of £10.9m or 79% in 2014/15, showing an increased spend of £1.4m. Head of Service comments on the progress made on capital schemes are set out in Appendix B.

6.0SLIPPAGE OF EXPENDITURE APPROVALS

6.1100% spend against the Budget is never anticipated due mainly to reasons beyond the Council’s control. For example, some schemes are reliant on a significant amount of match funding and external contributions, and others are demand led or dependant upon decisions made by partners.

6.2Schemes that are not completed within the financial year for which they are scheduled are slipped into the following financial year along with their unused expenditure and resource approvals. The total slippage figure for capital schemes from 2015/2016 is £5.751m. An analysis of schemes with a significant amount of slippage is provided in Appendix C.

7.0SIGNIFICANT VARIANCES

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 21 KB Download
PDF
Appendix BAppendix B 122 KB Download
PDF
Appendix CAppendix C 93 KB Download
PDF
Appendix DAppendix D 90 KB Download
PDF
Capital Programme Outturn 2015-16Report 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 21 attended
TA
Councillor Terry AldridgeCommittee Member, present
TB
Terry BroderickOfficer, present
NF
Councillor Neil FureyDeputy Mayor, in attendance
YG
Councillor Yvonne GagenCommittee Member, present
SG
Sue GriffithsSecretary, present
JH
John HarrisonOfficer, present
JH
Councillor John HodsonCommittee Member, present
BL
Bob LivermoreOfficer, present
IM
Councillor Ian MoranCommittee Member, present
AO
Councillor Adrian OwensCouncillor, in attendance
RP
Councillor Robert PendletonCouncillor, in attendance
PR
Peter RichardsOfficer, present

All 21 on the meeting page

On this subject at West Lancashire

Search all
  1. Capital Programme Outturn 2015-16This decision
  2. * Capital Strategy & Programme 2026-29Agreed
  3. Capital Strategy & Programme 2026-29Noted
  4. Capital programme reviewApproved
  5. Capital programme reviewApproved
  6. GRA Capital Strategy & Programme 2025/26 to 2027/28Agreed

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies