RESOLVED (A) That the updated Infrastructure Delivery Schedule provided at Appendix 2 to the report, be noted. (B) That the public consultation on four possible options for spending CIL monies in 2017/18 as set out in paragraph 4.11 of the report be approved.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To propose for consultation the possible options for a CIL Funding Programme for 2017/18 based on the CIL monies anticipated to have been collected by the Council by 31 March 2017.
Recommendations
2.1That the updated Infrastructure Delivery Schedule (IDS) provided at Appendix 2 be noted.
2.2That the public consultation for four possible options for spending CIL monies in 2017/18 set out in paragraph 4.11 of the report be approved.
Background
3.1The Council adopted a CIL Charging Schedule in July 2014, and has been charging CIL since 1 September 2014. In March 2015, the Council approved a CIL Governance Framework which set out how decisions would be made on the spending of CIL monies by the Council, amongst other matters. Key to this Framework is the production each year of a CIL Funding Programme to prioritise how the CIL funds raised in a given financial year will be spent the following financial year. A draft of this CIL Funding Programme must be publicly consulted upon before Cabinet make a final decision on it in January of any given year in readiness for spending the monies from April that year.
3.2This report marks the preparation of the second such CIL Funding Programme prepared by the Council and offers possible options on how CIL monies already collected by the Council since 1 September 2014 and those anticipated to be collected by 31 March 2017 could be spent in 2017/18. The options have thus far been prepared in line with the approach set out in the CIL Governance Framework.
3.3The 2016/17 CIL Funding Programme allocated funding to three projects as follows:
Car parking improvements at Station Approach, Ormskirk - £15,000
New allotments, Skelmersdale - £20,000
Boardwalk at Haskayne Cutting Nature Reserve - £8,000
3.4A key document in the process of preparing a CIL Funding Programme is the Infrastructure Delivery Schedule (IDS). The IDS is a database of infrastructure projects that are planned or desired to take place during the current Local Plan period. It originally formed part of the evidence base for the Local Plan and the CIL Charging Schedule but has become more of a “live” document now, allowing monitoring of all infrastructure projects in the Borough and so monitors how the Local Plan is performing in delivering this key aspect of sustainable development.
3.5Many projects on the IDS should have a connection to new development in that they are needed or demanded because of the new development proposed and being delivered through the Local Plan. However, other projects are not necessarily linked to new development in this way, but are still needed to upgrade existing infrastructure provision or reflect aspirations that infrastructure providers have and which, in some cases, may enable further new development in the future.
3.6In relation to CIL, therefore, the IDS provides the basis for assessing which infrastructure projects CIL monies should be spent on, although it should be clarified that not all projects on the IDS will be eligible for and / or need CIL monies. This is discussed further below.
3.7Infrastructure providers, ward councillors, parish councils and relevant council officers have all been given opportunity to input ideas and suggestions on schemes that could go into the latest update of the IDS, and to update details of schemes that are already in the IDS. This has enabled officers to update the IDS (see Appendix A) and then, based on the information submitted, to rank proposed schemes to inform recommendations on how CIL monies could be spent.
3.8In terms of CIL monies collected thus far or anticipated to be collected by 31 March 2017:
£45,703 was collected in 2014/15
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.