A. That the financial performance at the mid year point as set out in Appendix 1 be noted. B. That the results of the Policy Options consultation set out in Appendices 2, 3 and 4 be noted. C. That the following Policy Option proposals be approved from 2017/18: · Introduce a charge of £30 per year for the collection of green compostable material (Appendix 5 reference OP9) · Introduce a charge of £25 per year to have an extra green bin emptied (Appendix 5 reference OP9) · Removal of Static Recycling sites across the Borough (Appendix 5 reference OP10) · Reduce time period for discretionary council tax discounts on empty properties by half (Appendix 5 reference OP12) · Introduce a flat rate for the essential user lump sum car allowance based on the NJC rate for the smallest size cars with pay protection for any staff whose allowance is reduced (Appendix 6 option 2) · Payment of HMRC rates for all business mileage (Appendix 6 option 2) D. That the remaining Policy Option proposals contained in Appendix 5 be deferred for consideration at a later date. E. That the Chief Executive and Heads of Service be given authority to take all ... view the full minutes text for item 49.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To consider financial performance in the current year, and to report the results of the Policy Options 2017/18 consultation before agreeing a final set of Policy Options for implementation.
Recommendations
2.1That the financial performance at the mid year point as set out in Appendix 1 be noted.
2.2That the results of the Policy Options consultation set out in Appendices 2, 3 and 4 be noted.
2.3That the Policy Option proposals set out in Appendix 5 be approved, and that a Policy Option on Car Allowances be considered from the range of potential measures set out in Appendix 6.
2.4That the Chief Executive and Heads of Service be given authority to take all necessary action in connection with the implementation of the approved proposals.
Background
3.1The Council has been going through an extended period of reducing resources primarily as a result of significant reductions in its government grant funding. This period began in 2009 and in response an Organisational Downsizing Initiative was implemented in that year to deliver ongoing annual savings of £1.753m. Over the four year period 2011-15, the Council then delivered a series of large scale saving programmes that have delivered further ongoing annual savings of around £5m. Similarly the GRA faced a budget gap of £1.3m in 2015-16, and has agreed a further package of efficiencies, additional income and savings of £1.7m for the current 2016-17 financial year. This has been a period of unprecedented change for the GRA and there is an expectation that savings will continue to need to be made until at least 2020.
3.2A Policy Options report was presented to the July Council meeting that set out a forecast budget gap of £1.437m for 2017-18. This report then identified a range of measures including proposals to maximise income opportunities, seek efficiencies and economies, and procurement savings, which reduced the budget gap to £0.873m. The July report then set out a further series of potential options for consultation, which are summarised below.
Code Policy Option / Initiative OP9 Introduce an annual charge of £30 to collect garden waste Charge £25 per year per bin to have an extra green bin emptied Stop garden waste collections between November and February OP10 Remove static recycling sites across the borough OP11 Review of mechanical sweeping and street cleansing prestige work OP12 Reduce the time period for discretionary Council Tax Discounts on empty properties by half OP13 Rationalise public toilet provision to reduce costs by 50% OP14 Reduce live monitoring of CCTV in off peak/ quieter periods OP15 Remove essential user lump sum car allowance and consider payment of mileage rates based on the existing casual user mileage rate or the HMRC rate OP16 Remove some of the CCTV cameras in areas with lower crime rates
3.3While every effort has been given to maximising efficiencies and income generation, the scale of the GRA budget gap means that options have to be considered that will have an impact on the public, current service and performance levels, and members of staff. However these Policy Option proposals have been designed to minimise these effects given the level of savings that need to be identified.
4.0BUDGET MONITORING MID YEAR REVIEW
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.