A. That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A to the report and the progress against the Revised Capital Programme at Quarter 1, be noted . B. That future GRA Capital Monitoring reports be considered by the newly established Budget/Council Plan Committee, unless there are specific recommendations for Cabinet to consider.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide the Revised General Revenue Account (GRA) Capital Programme for 2022/23 and an update on the progress of capital schemes at quarter 1.
Recommendations
TO EXECUTIVE OVERVIEW & SCRUTINY:
2.1That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A to the report and the progress against the Revised Capital Programme at Quarter 1, be noted and agreed comments be forwarded to Cabinet to consider.
2.2That future GRA Capital Monitoring reports be considered by the newly established Budget/Council Plan Committee, unless there are specific recommendations for this Committee and Cabinet to consider.
TO CABINET: 2.3 That, subject to consideration of any agreed comments from the Executive Overview & Scrutiny Committee, the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A to the report and the progress against the Revised Capital Programme at Quarter 1, be noted.
2.4That future GRA Capital Monitoring reports be considered by the newly established Budget/Council Plan Committee, unless there are specific recommendations for Cabinet to consider.
Background
3.1The Capital Programme is set on a three-year rolling basis and the programme for 2022/2023 to 2024/2025 was approved by Council in February 2022.
3.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
3.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Revenue Account programme is subject to a separate report, this report concentrates on the GRA Capital Programme.
4.0REVISED CAPITAL PROGRAMME
4.1The original 2022/23 Capital Programme of £6.033m was set at February 2022 Council, the re-profiling of £9.262m from 2021/22 into 2022/23 was further approved at July 2022 Council, so that the total Capital Programme for 2022/23 now totals £15.295m, of which £4.723m is funded by Capital Receipts.
4.2Heads of Service are currently undertaking a review of their respective schemes and are proposing changes and re-profiling of the Capital Programme, that are a result of more up to date information becoming available. The quarter 1 review process has incorporated a number of considerations including: Re-profiling of schemes to match the anticipated timing of spending. Increasing expenditure budgets to reflect new and / or additional external funding
4.3The proposed changes to the 2022/23 Programme at quarter 1 are analysed in Appendix A. This shows a net decrease of £4.551m largely due to Leisure Facilities Project £3m. Burscough Sports Centre £386k Revenue Transformation costs £300k. Affordable Housing £247k.
4.4The revised GRA Capital Programme at quarter 1 totals £11.386m of which £3.566 is funded by Capital Receipts following these changes.
4.5The review exercise currently being undertaken with Heads of Service will be completed by quarter 2, and a fully revised 3-year 2022/23 to 2024/25 Capital Programme, will be presented at December 2022 Council for approval and form the basis of the 2023/24 to 2025/26 budget setting.
5.0CAPITAL EXPENDITURE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.