RESOLVED (A) That the financial position in respect of the 2016/2017 HRA and Council Housing Capital Investment Programme be noted. (B) That the proposed £50,000 capital budget virement from the Disabled Adaptation scheme to the Lift scheme as set out in paragraph 6.3 of the report be approved. (C) That call-in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 30 March. 2017.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide an update on the current position in respect of the 2016/2017 Housing Revenue Account (HRA) and Council Housing Capital Investment Programme.
2.0RECOMMENDATIONS TO CABINET
2.1That the financial position in respect of the 2016/2017 HRA and Council Housing Capital Investment Programme be noted.
2.2That the proposed £50,000 capital budget virement from the Disabled Adaptation scheme to the Lift scheme as set out in paragraph 6.3 be approved.
2.3That Call In is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 30th March. 2017.
3.0RECOMMENDATION TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE
3.1That the financial position in respect of the 2016/2017 HRA and Council Housing Capital Programme be noted.
4.0BACKGROUND 4.1 A one year budget for both the HRA and the housing investment programme was set for 2016/17. This addressed the immediate budget gap created by the change in Government policy on Council housing rents announced in the summer of 2015. A series of policy options were approved by Council in July 2016 and October 2016 that will address the on-going financial pressures created by the 1% per annum rent reduction that will be required over the 4 year period to 2019- 2020. These policy options will also allow some money to be set aside to help fund future additional budget pressures which progressively build during this period.
5.0REVENUE BUDGET MONITORING
5.1It is our standard practice to review financial performance to ensure that budgets are being effectively controlled so that any issues can be addressed in a timely fashion. A summary of the HRA Revenue position is shown in Appendix 1 which identifies that a favourable budget variance of £1.301m is projected for the year. This is equivalent to 5.0% of the overall budget requirement, and so is a relatively modest variance in percentage terms. This compares to a projected position of a favourable variance of £0.967m at the mid year stage.
5.2The main reasons for this position are that the active management of staffing levels should deliver a favourable budget variance of just over £450,000 based on current trends, and because there have been no calls to date on the central contingency budget of £398,000. The void repairs and response repairs budgets are expected to finish the year around £250,000 below budget, but as both budgets are demand driven and depend partly upon uncontrollable factors such as the severity of the remaining winter months, this could vary.
5.3The projections have been calculated on a prudent basis, and consequently it can be confidently expected that the HRA will meet its budget targets. This will continue our track record of managing our financial performance to ensure that the outturn position is in line with the budget.
5.4Consideration can be given to how this projected favourable budget variance should be used when Council consider the outturn position later this year in July, taking into account the latest HRA Business Plan projections.
6.0CAPITAL BUDGET MONITORING
6.1A summary of the Housing Capital Investment Programme position is shown in Appendix 2. The total budget for the year is £15.070m and expenditure up to the 26th January 2017 was £7.367m, which represents 49% of the total budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.