West Lancashire Borough Council
Policy & Resources Committee, Wednesday 25 March 2026 at 7.00pm

HRA Q3 Budget Monitoring - Revenue & Capital

Noted Committee 1 paper

AI summaryWest Lancashire Policy & Resources Committee noted the HRA Q3 position for 2025/26, with the revenue forecast around £20k better than budget and 37% of the £23.6m capital budget spent so far.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue and capital position for 2025/26 quarter 3
Money£20k better than budget37% of £23.6m capital budget spent, £3.3m committed
What happens nextNot stated
Who it affectsCouncil housing tenants and serviceHousing Revenue Account funded services and capital works

What was decided

The committee noted the HRA Q3 position for revenue and capital, taking it as information only. Report 3.1, 9.1

Why

The HRA revenue forecast at Q3 is around £20k better than budget, down from a £70k favourable position at Q2, with voids remaining the main budget pressure and the 2024 Right to Buy surge now completing. Report 4.2, 5.1, 5.2

Around 37% of the revised £23.6m capital budget had been spent at Q3, with a further £3.3m committed, and most scheme lines are running behind profile. Report 6.1, P14, P15

What happens next

The committee approved no further action, as the item was for information only and financial pressures are expected to be met from existing HRA resources. Report 8.1, 9.1

The money

  • £20k Q3 forecast improvement against HRA revenue budget Report 5.1
  • £70k Q2 forecast favourable variance against HRA revenue budget Report 5.1
  • £23.6m Revised 2025/26 HRA capital budget Report 6.1
  • £3.3m Capital expenditure commitments at Q3 Report 6.1
  • £5.9m Capital expenditure to date excluding TVD Report 6.1
  • £6,164,000 Revenue contributions to capital (MRR) Report P12, P15

Options considered

  • Chosen: Note the HRA Q3 revenue and capital position. Item was for information only and no formal decision was required Report 3.1, 9.1

Implications

  • Financial: Revenue and capital pressures are expected to be met using existing HRA resources, with most of the budget contingency being used to offset void losses. Report 5.2, 5.3, 8.1
  • Equalities: No direct impact on the public, employees or stakeholders, so no Equality Impact Assessment was required. Report P27
  • Other: No significant sustainability, crime and disorder, or health and wellbeing implications identified. Report 7.1, 10.1

Who and where

  • HRA tenants and households on the council housing waiting list Report 4.2, 5.2
  • Council housing landlord service and contractors carrying out voids and repairs work Report 5.2

Timeline

  • November 2024: Surge of 97 Right to Buy applications ahead of discount changes, with 80 still assumed to reach completion Report 4.2
  • February 2025: Council agreed the 2025/26 HRA revenue and capital budgets Report 4.1
  • July 2025: Council received the 2024/25 outturn report and agreed budget reprofiling and adjustments Report 4.1
  • 2025/26 Q3: Quarter 3 monitoring report showing the position now noted by the committee Report 1.1, 5.1, 6.1

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
  • RTB: Right to Buy, the scheme allowing eligible council tenants to buy their home
  • Q3: Quarter 3, the third quarter of the financial year, covering October to December
  • MRR: Major Repairs Reserve, a reserve used to fund capital works on council housing
  • Voids: Council homes that are empty between tenancies, often while repairs are carried out
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item154

Resolved

That the HRA Q3 position for revenue and capital be noted.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Policy & Resources Committee

Purpose of the report

1.1To provide a summary of the Housing Revenue Account (HRA) and Housing capital programme positions for the 2025/26 financial year based upon quarter 3 monitoring (Q3).

2.0RECOMMENDATIONS TO LANDLORD SERVICES COMMITTEE

2.1That the HRA Q3 position for revenue and capital be noted.

3.0RECOMMENDATIONS TO POLICY & RESOURCES COMMITTEE

3.1That the HRA Q3 position for revenue and capital be noted.

Background

4.1In February 2025, Council agreed the HRA revenue and capital budgets for the 2025/26 financial year. The 2024/25 outturn report to Council in July 2025 agreed some budget reprofiling and adjustments. 2025/26 Q2 monitoring went to Council for approval of some budget virements and capital reprofiling into 2026/27.

4.2Previous HRA reports advised of a surge of 97 RTB (right to buy) applications in November 2024 due to a significant reduction in the level of RTB discount available after that date. Previous assumptions that 80 of these will reach sales completion are still being assumed and a significant number have now reached completion. 5.0 HRA – 2025/26 Q3 Projected Outturn

5.1A summary of the projected HRA revenue outturn against budget is set out in the table below. The HRA Q3 forecast is around £20k better than budget, this compares with the Q2 forecast of £70k favourable.

5.2Budget pressure is primarily due to voids. As reported previously, the impact of high void levels can also be seen in three main ways:

• Rent loss. Budget setting anticipated that it would be mid-year before voids were at broadly target levels. In hindsight this was over-optimistic though latest operational metrics suggest that voids are now coming down. The hit from rent loss has been obscured in-year by the upside from the timing delays on November 2024 surge RTB completions. As the RTB surge finishes the run rate increasingly reflects the downside impact of void loss. • The void revenue cost forecast has worsened, partly in recognition that management are continuing to work hard to bring void levels down again, as seems to be the case in operational metrics. To facilitate catch up, the team are allocating voids works to other contractors too, when Wates are unable to provide the capacity required. • Council Tax payments on void properties remain higher than budget due to more voids and longer void turnaround through the year.

5.3In mitigation, the majority of HRA budget contingency is being used to offset voids revenue expenditure pressure and it now seems unlikely that all the budgeted interest payments for new HRA borrowing in 2025/26 will be required as cash balances have held up better than expected. 2025/26 Q1 Var. Q2 Var. Q3 Var. Revised £000 £000 £000 Budget Area Comment Budget £000 Employee Expenses 5,906 134 0 -50 Net of £400k vacancy factor budget. Void and response repairs Primarily voids. Increased activity to reduce the number of 7,125 0 600 750 plus electrical testing outstanding voids has led to forecast outturn expenditure. £200k pressure on Council tax from voids offset by £200k on Other premises costs 3,460 0 100 50 remaining external decorations budget unlikely to be spent. Various smaller pressures. Transport costs 225 -20 -30 -30 Car user allowances.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Q3 Budget Monitoring: Revenue & CapitalReport 174 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 43 attended
YG
Councillor Yvonne GagenChairperson, present
GD
Councillor Gareth DowlingVice-Chairperson, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, apologies, sent representative
AB
Councillor Alexander BlundellCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
TD
Councillor Thomas de FreitasCommittee Member, present
AM
Councillor Anne Mary FennellCommittee Member, present as substitute
NF
Councillor Neil FureyCommittee Member, present
NH
Councillor Nikki HennessyCommittee Member, absent
PD
Councillor Paul David HeskethCommittee Member, present

All 43 on the meeting page

On this subject at West Lancashire

Search all
  1. HRA Q3 Budget Monitoring - Revenue & CapitalThis decision
  2. HRA Budget Setting Report 2026-27Noted
  3. HRA Budget Setting Report 2026-27Noted
  4. HRA Q2 Budget Monitoring - Revenue & CapitalNoted
  5. HRA Q2 Budget Monitoring - Revenue & CapitalNoted
  6. HRA Q1 Budget Monitoring - Revenue & CapitalNoted

More from West Lancashire Policy & Resources Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MinutesThat the minutes of the meeting held on Wednesday, 25 March 2026 be received as a correct record and signed by the Ch... Decided Open
25 Jun 2026 Terms of ReferenceThat the Terms of Reference be noted. Noted Open
25 Jun 2026 Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen... Noted Open
25 Jun 2026 Public SpeakingA request to speak in relation to the item, Community Infrastructure Levy (CIL) Funding Programme 2025 – Becconsall H... Noted Open
25 Jun 2026 Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewThat in accordance with Option 1 of the report, CIL funding is not allocated towards Becconsall Heritage Park. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies