AI summaryCouncil noted the Housing Revenue Account Q2 position and approved revenue and capital virements, including reprofiling £7.6m of capital spend from 2025/26 into 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue and capital budget changes endorsed
Money£7.6m reprofiled to 2026/27Plus £5.52m added for Maryvale scheme
What happens nextImplement approved virementsNew contracts to be let for several schemes
Who it affectsCouncil housing tenants and serviceCapital works on stock, voids, RTB income
What was decided
The HRA Q2 position for revenue and capital was noted. Report 4.1
Revenue budget virements set out in paragraphs 6.1 to 6.4 were approved. Report 4.2
Capital budget virements in table 7.6 and reprofiling of £7.6m from 2025/26 into 2026/27 were approved. Report 4.3, 4.4, 7.4
Why
Q2 monitoring shows the HRA revenue forecast is around £70k (0.2%) better than budget, mainly due to delayed Right to Buy completions offsetting voids pressure. Report 6.7
At mid-year, capital budgets were reviewed against operational progress, with unrequired sums vired in-year or reprofiled into 2026/27. Report 7.1
Four gardeners now managed directly within the HRA, and a permanent virement moves £175k from underused external decorations to other premises costs. Report 6.2, 6.4
What happens next
Approved virements and the £7.6m capital reprofiling are to be applied to budgets and reported through the ledger. Report 4.2, 4.3, 4.4
New multi-year contracts are being procured for external works, kitchen and bathroom replacements, electrical upgrades, heating, walls, UPVC windows and the environmental programme. Report 7.6
The 2026/27 budget setting will review staircase lighting service charge levels and update the GRA-to-HRA recharge for temporary accommodation voids. Report 6.3, 6.8
The money
£7.6m HRA capital reprofiled from 2025/26 into 2026/27 Report 4.4, 7.4
£5.52m Maryvale housing scheme estimate added to 2025/26 capital Report 7.5
£70k Q2 revenue forecast variance, 0.2% better than budget
£175k Permanent virement from external decorations to other premises costs Report 6.2
£92k Moved to staircase lighting within other premises costs Report 6.3
£83k Moved to disrepair claims legal fees Report 6.3
£134k Staff costs for four gardeners now managed within HRA Report 6.4
Options considered
Chosen: Note the HRA Q2 revenue and capital position. Standard quarterly monitoring of the HRA budget. Report 4.1
Chosen: Approve the revenue virements in paragraphs 6.1 to 6.4. Reflects management changes for gardeners and rebasing of underused decorations budget. Report 4.2, 6.2, 6.4
Chosen: Approve capital virements set out in table 7.6. Moves unrequired 2025/26 capital to where it is needed in-year. Report 4.3, 7.6
Chosen: Approve £7.6m capital reprofiling from 2025/26 to 2026/27. Schemes awaiting new contracts and slower delivery mean spend will fall in 2026/27. Report 4.4, 7.4
Implications
Financial: Financial implications are expected to be met using existing HRA resources. Report 8.1
Financial: Rent loss on void properties is obscuring the RTB timing upside and is likely to continue above budget. Report 6.7, P23
Financial: Council tax paid on void properties is running higher than budget due to more voids and longer turnaround. Report 6.7, P23
Other: No significant sustainability, crime and disorder, health and wellbeing, or equality impacts identified. Report 7.1, 10.1, P44
Who and where
Council housing tenants, through delays to capital works such as kitchens, bathrooms, rewires, heating, walls, windows and external programmes Report 7.6
Households in temporary accommodation, where higher void rates and an increased recharge to the HRA are flagged Report 6.8
Right to Buy applicants from the November 2024 surge, with sales assumed to complete during the rest of 2025/26 Report 5.2
Timeline
November 2024: Surge of 97 Right to Buy applications received before discount reduction Report 5.2
February 2025: Council agreed the HRA revenue and capital budgets for 2025/26 Report 5.1
July 2025: Council agreed 2024/25 outturn reprofiling and the Maryvale housing scheme Report 5.1, 7.5
End September 2025: 14 of the November 2024 RTB surge had completed Report 5.2
2026/27: Reprofiled £7.6m of HRA capital expected to be spent, alongside existing budget of around £12.2m Report 7.4
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
RTB: Right to Buy, the statutory scheme allowing secure tenants to buy their council home
Virement: Transfer of budget from one spending heading to another within the same fund
Reprofiling: Moving approved budget from one financial year to another
MRR: Major Repairs Reserve, a ring-fenced capital funding source for the HRA
GRA: General Revenue Account, the council's main non-housing fund
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79
Resolved
A. That the HRA Q2 position for revenue and capital be noted. B. That the revenue budget virements in paragraphs 6.1 to 6.4 of the report, be approved. C. That the capital budget virements in table 7.6 in the report, be approved. D. That the capital budget reprofiling of £7.6m from 2025/26 into 2026/27, set out in table 7.6 in the report, be approved.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide a summary of the Housing Revenue Account (HRA) and Housing capital programme positions for the 2025/26 financial year based upon quarter 2 monitoring (Q2).
2.0RECOMMENDATIONS TO LANDLORD SERVICES COMMITTEE
2.1That the HRA Q2 position for revenue and capital be noted and any comments forwarded to the Lead Member for Housing prior to Council on 10 December 2025.
3.0RECOMMENDATIONS TO POLICY & RESOURCES COMMITTEE
3.1That the HRA Q2 position for revenue and capital be noted and any comments forwarded to the Lead Member for Housing prior to Council on 10 December 2025.
4.0RECOMMENDATIONS TO COUNCIL
4.1That the HRA Q2 position for revenue and capital be noted.
4.2That the revenue budget virements in paragraphs 6.1 to 6.4, be approved.
4.3That the capital budget virements in table 7.6, be approved.
4.4That the capital budget reprofiling of £7.6m from 2025/26 into 2026/27, set out in table 7.6, be approved. 5.0 BACKGROUND
5.1In February 2025, Council agreed the HRA revenue and capital budgets for the 2025/26 financial year. The 2024/25 outturn report to Council in July 2025 agreed some budget reprofiling and adjustments. Q1 monitoring went to Policy & Resources Committee to note.
5.2Previous HRA reports advised a surge of 97 RTB (right to buy) applications in November 2024 due to a significant reduction in the level of RTB discount available after that date. Previous assumptions that 80 of these will reach sales completion are still being assumed though there has been a timing delay in this happening. 14 of the November RTB surge have completed by the end of September 2025 with a high number proceeding through the legal process.
6.0HRA – 2025/26 Q2 Budget Virements and Projected Outturn
6.1The table below summarises proposed amendments to the HRA revenue budget. The budget figures below are in £000's so there is a rounding difference.
2025/26 Virements 2025/26 Budget Revised Budget Area £000 Budget £000 Four gardeners, now Employee Expenses 5,773 134 5,906 managed directly rather than recharged. Void and response repairs plus electrical 7,125 7,125 testing Grounds maintenance recharge – four gardeners plus balances to recharges line. Other premises costs 4,243 -783 3,460 £175k from revenue planned maintenance: £92k to staircase lighting and £83k to disrepair claim legal fees. Transport costs 225 225 Budget contingency 290 290 Four Gardeners – Supplies and Services 1,339 3 1,342 supplies and equipment. Remaining Grounds Support Services and 2,612 646 3,258 maintenance recharge internal income (net) from premises costs. Loan interest & Contribution towards 3,740 3,740 Repayment Contributions to capital 6,164 6,164 Dwelling rents -28,321 -28,321 Other external income -3,189 -3,189 Total 0 0 0
6.2Firstly, in recent years it has been reported that the external decorations/planned revenue works budget of £375k has substantially not been utilised. A procurement specification is being planned but the new contract will not come into effect until 2026/27. The estimated annual value of the new contract is likely to be less than £200k, therefore a permanent virement is proposed to move £175k from external decorations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.