RESOLVED (A) That the new Self Build and Custom Build Register Application Form provided at Appendix B to the report be approved. (B) That the proposal to set a fee of £120 per application to the Self Build and Custom Build Register be approved and that authority be delegated to the Director of Development and Regeneration, in consultation with the Portfolio Holder for Planning, to review and amend the application fee to reflect costs associated with the application process as necessary each year.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek approval for a change in the way the Self Build and Custom Build Register is managed by the Council, including vetting the financial ability of an applicant to undertake a self-build, a protocol for doing so and setting an application fee to cover the costs of this process.
Recommendations
2.1That the new Self Build and Custom Build Register Application Form provided at Appendix B be approved.
2.2That the proposal to set a fee of £120 per application to the Self Build and Custom Build Register is approved and that authority is delegated to the Director of Development and Regeneration, in consultation with the Portfolio Holder for Planning, to review and amend the application fee to reflect costs associated with the application process as necessary each year.
Background
3.1In March 2015, the Self-Build and Custom Housebuilding Act 2015 was enacted by Parliament. This Act placed a duty on local authorities to keep a register of individuals, and associations of individuals, who wish to acquire serviced plots of land, to bring forward self-build and custom housebuilding projects and to place a duty on those authorities to have regard to those registers in carrying out planning and other functions.
3.2On 1st April 2016, the Self-Build and Custom Housebuilding (Register) Regulations 2016 came into force. These implemented the requirement for local authorities to hold a register of individuals and associations who are seeking to acquire serviced plots of land in the authority’s area in order to build their own home (the Self Build and Custom Build Register, to be referred to as "the Register" in this report).
3.3Through these Regulations, the Council was required to publicise the ability for individuals and associations to apply for entry on the Register, and the Regulations and subsequent national planning practice guidance set out what eligibility criteria the Council could use to assess those applications.
3.4The Council, aware of these Regulations as they moved through Parliament, was prepared for them to come into force and was able to take applications for the Register from 1 April 2016 (see application form at Appendix A). The Register was publicised by a press release which was reproduced as a press article in the Champion, through other Council publications (such as the Let’s Talk Business newsletter) and on the Council’s website. As of 31 July 2017, the Register has 33 individuals on it who have advised us that they are seeking a range of plot sizes in various parts of the Borough.
3.5On 31st October 2016, two further sets of regulations came into force, the Self- Build and Custom Housebuilding (Time for Compliance and Fees) Regulations 2016 and the Self-build and Custom Housebuilding Regulations 2016.
3.6The Self-Build and Custom Housebuilding (Time for Compliance and Fees) Regulations 2016 placed a requirement on local authorities to grant sufficient planning permissions for serviced plots of land for self and custom-build to meet the demand evidenced by their Register, specifically to have granted these permissions within 3 years of a given base date.
3.7The first base date is taken to be 31st October 2016 (when the regulations came into force) and the Council had 12 individuals on the Register at that time, and so must grant permission for at least 12 serviced plots by 31st October 2019. At least a further 21 serviced plots (to take the permissions up to the current 33 individuals on the Register) may also be required within the next three years if the number of people on the Register remains the same between now and 31 st October 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.