Capital Programme Outturn 2016-17

Noted Executive 2 papers

Cabinet noted this item on Tuesday 12 September 2017. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

RESOLVED (A) That the final positon, including slippage, on the Capital Programme for the 2016/2017 financial year be noted and endorsed. (B) That call-in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28 September 2017.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To provide a summary of the capital outturn position for the 2016/2017 financial year.

2.0RECOMMENDATIONS TO CABINET

2.1That the final position, including slippage, on the Capital Programme for the 2016/2017 financial year be noted and endorsed.

2.2That Call In is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28 September 2017.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE

3.1That the final position on the Capital Programme for the 2016/2017 financial year be noted.

Background

4.1Members have been kept informed of the financial position of the Capital Programme with regular monitoring reports. This report provides Members with the final position on capital schemes for the 2016/2017 financial year. The position on the current year’s Programme for 2017/2018 is discussed elsewhere on this Agenda. 5.0 CAPITAL PROGRAMME

5.1The Capital Programme of £22.747m at the end of the 2016/2017 financial year is analysed by Service in Appendix A. The key result for the year is that good progress has been made in delivering schemes.

5.2The total capital expenditure for the year was £16.852m which represents 74% of the total Budget for the year. This is slightly higher than 2015/2016 but consistent with earlier programmes as indicated in Table 1:

Table 1: Capital Expenditure against Budgets Expenditure Budget % Spend Year £m £m against Budget 2016/2017 16.852 22.747 74% 2015/2016 17.470 26.661 66% 2014/2015 13.102 17.386 75% 2013/2014 15.129 19.503 78%

5.3In total spending was £0.618m less than 2015/2016 and £3.750m more than 2014/2015. However the percentage spend of 74% was in line with recent experience.

6.0SLIPPAGE OF EXPENDITURE APPROVALS

6.1100% spend against the Budget is never anticipated due mainly to reasons beyond the Council’s control. For example, some schemes are reliant on a significant amount of match funding and external contributions, and others are demand led or dependant upon decisions made by partners.

6.2Schemes that are not completed within the financial year for which they are scheduled are slipped into the following financial year along with their unused expenditure and resource approvals. The total slippage figure for capital schemes from 2016/2017 is £6.383m. The main area of slippage was on the Housing Public Sector programme and details on this position were included in the HRA Revenue and Capital Outturn report to Council in July. Slippage has primarily been allocated to the current financial year (£5.475m) with the balance (£0.908m) slipped into later years.

7.0SIGNIFICANT VARIANCES

7.1There will always be some variances between the original estimated cost of a capital scheme and its final position and the Council has established budgetary management and control procedures in place to minimise such variances. While there have been a number of over and under spends this year, in total expenditure was £0.489m over budget, which is a variance of around 2%. This was primarily as a result of bringing forward the timing of Property Purchases to ensure that the opportunities from one for capital receipt funding were maximised. 8.0 CAPITAL RESOURCES

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 20 KB Download
PDF
Capital Programme Outturn 2016-17Report 147 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
CC
Councillor Claire CooperCommittee Member, present
JF
Councillor Jenny ForshawCommittee Member, present
JH
Councillor John HodsonCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
CW
Councillor Chris WynnCommittee Member, present
KW
Kim WebberOfficer, present
SG
Sue GriffithsSecretary, expected
DT
Dave TillerayOfficer, expected
JS
Jacqui Sinnott-LaceyOfficer, expected

All 19 on the meeting page

On this subject at West Lancashire

Search all
  1. Capital Programme Outturn 2016-17This decision
  2. * Capital Strategy & Programme 2026-29Agreed
  3. Capital Strategy & Programme 2026-29Noted
  4. Capital programme reviewApproved
  5. Capital programme reviewApproved
  6. GRA Capital Strategy & Programme 2025/26 to 2027/28Agreed

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open