CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
West Lancashire Borough Council
Cabinet, Tuesday 12 September 2017 at 7.00pm

Capital Programme Monitoring 2017-18

Noted Executive 2 papers

Cabinet noted this item on Tuesday 12 September 2017. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

RESOLVED (A) That the progress on the Capital Programme as at the end of July 2017 be noted. (B) That call-in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28 September 2017.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To provide an overview of the current progress on the Capital Programme.

2.0RECOMMENDATIONS TO CABINET

2.1That Members note the progress on the Capital Programme as at the end of July, 2017.

2.2That Call In is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28th September 2017.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE

3.1That Members note the current progress on the Capital Programme.

Background

4.1It is an agreed policy and best practice that monitoring reports are produced on a regular basis to ensure that Members are kept informed of the financial position of the Capital Programme. This is the first such report for the 2017/2018 financial year. 5.0 CAPITAL PROGRAMME BUDGETS

5.1A Capital Programme totalling £9.914m was approved at Council on 22nd February 2017. Slippage totalling £5.475m from the 2016/2017 Programme is included for consideration elsewhere on this Agenda and has been added to the 2017/2018 Programme. The Capital Programme for 2017/2018 is, therefore, now £15.389m and this is analysed by Service in Appendix A.

6.0CAPITAL EXPENDITURE

6.1Normally, new capital schemes are profiled with relatively low spending compared to budget in the early part of the financial year with increased spending as the year progresses. This reflects the fact that many new schemes have considerable lead in times, for example, because of the need to undertake a tendering process and award contracts at the start of the scheme. Other schemes are dependent on external partner funding and these schemes can only begin once their funding details have been finalised.

6.2This year so far there has been a relatively low level of expenditure totalling £1.37m by the end of July compared to £6.48m at the same point in 2016/2017 and £2.23m in 2015/16. The expenditure level was particularly high in 2016/17 due to the £3.01m purchase of the Wheatsheaf Walks site, and expenditure of £1.3m for the Firbeck Revival scheme.

6.3It is anticipated that most schemes will progress and spend in line with their budget targets by the year end. All schemes, however, will be reviewed over the coming months and a Revised Medium Term Programme will be reported to Members in the Autumn taking into account new information and recent developments.

7.0CAPITAL RESOURCES

7.1Total budgeted resources for the year are £15.389m. This is analysed in Appendix A and includes funding for slippage.

7.2The main area of the capital resources budget that is subject to variation is in relation to capital receipts. These are the useable proceeds from the sale of Council assets (mainly houses under Right to Buy legislation) that are available to fund capital expenditure. These receipts can vary significantly depending on the number and value of assets sold. The budget for usable capital receipts to be generated from Council House sales in the year is set at £0.695m from 45 sales. By the end June 22 sales were completed generating £0.479m with a further 6 sales in July. In addition there was also £0.250m of one for one capital receipt funding that was generated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 12 KB Download
PDF
Capital Programme Monitoring 2017-18Report 37 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
CC
Councillor Claire CooperCommittee Member, present
JF
Councillor Jenny ForshawCommittee Member, present
JH
Councillor John HodsonCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
CW
Councillor Chris WynnCommittee Member, present
KW
Kim WebberOfficer, present
SG
Sue GriffithsSecretary, expected
DT
Dave TillerayOfficer, expected
JS
Jacqui Sinnott-LaceyOfficer, expected

All 19 on the meeting page

On this subject at West Lancashire

Search all
  1. Capital Programme Monitoring 2017-18This decision
  2. * Capital Strategy & Programme 2026-29Agreed
  3. Capital Strategy & Programme 2026-29Noted
  4. Capital programme reviewApproved
  5. Capital programme reviewApproved
  6. GRA Capital Strategy & Programme 2025/26 to 2027/28Agreed

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies