HRA Revenue and Capital Monitoring

Noted Executive 1 paper

Cabinet noted this item on Tuesday 12 March 2019. Below is the council's own wording, with the papers it was decided on.

Item95

Resolved

RESOLVED A. That the financial position in respect of the 2018/19 HRA and Council Housing Capital Investment Programme be noted. B. That call-in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28th March.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To provide an update on the current position in respect of the 2018/19 Housing Revenue Account (HRA) and Council Housing Capital Investment Programme.

2.0RECOMMENDATIONS TO CABINET

2.1That the financial position in respect of the 2018/19 HRA and Council Housing Capital Investment Programme be noted.

2.2That call in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 28th March.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE

3.1That the financial position in respect of the 2018/19 HRA and Council Housing Capital Programme be noted. 4.0 BACKGROUND

4.1In February 2018 Council agreed the 2018/19 HRA revenue and capital budgets. Subsequently in July 2018 Council noted the favourable financial outturn position of the 2017/18 HRA and Capital Investment Programme and approved a number of budget changes and allocations. Further changes were approved at the mid- year review stage at Council in December 2018.

4.2As a result of previously approved policy options, the HRA should be able to achieve a balanced budget position during the period of 1% per annum rent reductions that will need to be implemented under government rules until 2020.

5.0HOUSING REVENUE ACCOUNT – PROJECTED OUTTURN

5.1A summary of the projected HRA revenue outturn is set out in Appendix A and shows that a favourable budget variance of £1,427,000 is expected, representing 5.6% of total turnover. This compares to the mid-year projected outturn position of £1,146,000 (4.5% of total turnover). This demonstrates that the HRA remains in a healthy financial position. The main reasons for this positive forecast are that:

 There are a number of vacant posts, largely in Property Services, pending recruitment of the permanent staff to fill them. Consequently a significant favourable variance is anticipated on employee costs.

 Following painting contractor issues in 2017/18 a more integrated and planned approach is being taken that delivers pre-painting at the same time as guttering and other works. The pre-painting budget itself will therefore largely not be used in the current financial year.

5.2At the mid-year stage, demand-led pressure on the void repairs and responsive repairs budget were reported. This position has improved during the second half of the year and it is now expected that this will break even. As both budgets are demand led, there remain various factors that can influence the exact final outturn. This is the main change in the projected outturn position since the mid- year stage.

5.3It can be confidently expected that the HRA will meet its budget targets and this will continue our track record of managing our financial performance to ensure that the outturn position is in line with the budget. At its meeting in February 2019 Council approved the use of £1,100,000 of the projected outturn to support the 2019/20 HRA budget position. Consideration will be given as to how the remaining projected favourable budget variance should be used in the HRA Outturn report to Council in July 2019, when the final year end position is known.

6.0CAPITAL INVESTMENT PROGRAMME

6.1A summary of capital expenditure to the end of December 2018 against the revised budgets is shown in Appendix B. Total expenditure to date is £8.839m which represents 57% of the total revised budget of £15.455m. This compares to expenditure of £4.036m at the quarter 3 point of 2017/18, which represented 38% of the total budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Revenue and Capital MonitoringReport 355 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 25 attended
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
CC
Councillor Claire CooperCommittee Member, present
JF
Councillor Jenny ForshawCommittee Member, present
JH
Councillor John HodsonCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
AY
Councillor Adam YatesCommittee Member, present
KW
Kim WebberOfficer, in attendance
JH
John HarrisonOfficer, in attendance
JS
Jacqui Sinnott-LaceyOfficer, absent
HM
Heidi McDougallOfficer, absent

All 25 on the meeting page

On this subject at West Lancashire

Search all
  1. HRA Revenue and Capital MonitoringThis decision
  2. HRA Outturn 2025/26 - Revenue & CapitalNoted
  3. HRA Outturn 2025/26 - Revenue & CapitalNoted
  4. HRA Q3 Budget Monitoring - Revenue & CapitalNoted
  5. HRA Q2 Budget Monitoring - Revenue & CapitalNoted
  6. HRA Q2 Budget Monitoring - Revenue & CapitalNoted

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open