A REGENERATION PLAN FOR SKELMERSDALE TOWN CENTRE

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item90

Resolved

A. That a Place-Shaping Hub made up of the partners outlined in paragraph 3.5 of the report be established. B. That the Terms of Reference of the Place Shaping Hub be agreed as follows: "To create and develop a Regeneration Plan for Skelmersdale Town Centre, that meets the aspirations and key priorities for the Council and its partners, initially concentrating on the area outlined at Appendix A and consider other specific, but connected, pieces or work around other key regeneration projects in the wider Skelmersdale and Up Holland area, including Estates Regeneration and Green Infrastructure proposals, including consideration of available funding." C. That a Skelmersdale Town Centre Regeneration Plan Cabinet Working Group be established consisting of 4 Labour Members, 2 Conservative Members and 1 Our West Lancashire Member, with a Chairman and Vice-Chairman to be nominated by the Leader of the Council with the following Terms of Reference: "( a ) To receive presentations and reports in relation to the progress of the Skelmersdale Town Centre Regeneration Plan. (b) To consider proposals arising from the Skelmersdale Town Centre Regeneration Plan. (c) To make recommendations to Cabinet and/or Council as appropriate."
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To provide an update on the development of a 'Place Shaping' Hub and the preparation of a specific Regeneration Plan for Skelmersdale Town Centre, and to establish a 'Place Shaping Hub' and Cabinet Working Group to steer this work.

Recommendations

2.1That a Place-Shaping Hub made up of the partners outlined in paragraph 3.5 of this report be established.

2.2That the Terms of Reference of the Place Shaping Hub be agreed as follows:

"To create and develop a Regeneration Plan for Skelmersdale Town Centre, that meets the aspirations and key priorities for the Council and its partners, initially concentrating on the area outlined at Appendix A and consider other specific, but connected, pieces or work around other key regeneration projects in the wider Skelmersdale and Up Holland area, including Estates Regeneration and Green Infrastructure proposals, including consideration of available funding."

2.3That a Skelmersdale Town Centre Regeneration Plan Cabinet Working Group be established consisting of 4 Labour Members, 2 Conservative Members and 1 Our West Lancashire Member, with a Chairman and Vice-Chairman to be nominated by the Leader of the Council with the following Terms of Reference:

(a) To receive presentations and reports in relation to the progress of the Skelmersdale Town Centre Regeneration Plan. (b) To consider proposals arising from the Skelmersdale Town Centre Regeneration Plan. (c) To make recommendations to Cabinet and/or Council as appropriate." 3.0 BACKGROUND

3.1Since the original Skelmersdale Town Centre Masterplan SPD1 was adopted, there have been many changes to the plans for Skelmersdale Town Centre. However, as Phase 1 of the most recent proposals gets under construction and the Council's Development Agreement with St Modwen's comes to an end, there is a need to begin to consider what to plan for on the land, referred to as Town Centre Phase 2 as outlined in Appendix A and understand what wider opportunities exist within the Skelmersdale and Up Holland 'neighbourhood'.

3.2Alongside this, two key housing sites in the east of the town centre (Findon and Delf Clough) are under construction, the proposals for the new Skelmersdale Wellbeing & Leisure Hub are developing, and the proposals for a new Rail Station on the former Westbank / Glenburn site in the south of the town centre are very much still moving forward. Furthermore, in connection with the latter, LCC now own the whole of the former Glenburn School site (including the playing fields) and the adjacent former Skelmersdale College site at Westbank, and so not only have control of the land needed for the new rail station, but a large area of land to the west of this which they wish to bring forward for development.

3.3In addition, the original masterplan and subsequent update to this through Policy SP2 of the adopted Local Plan 2012-2027 earmarked the Council's own land to the north of Yewdale (and south-west of the Tawd Valley) for potential housing development. The Council has not been in a position to bring this land forward as yet, and so, alongside considering the former Glenburn School site with LCC, it is now timely to reconsider what this Council wants to utilise its land at Yewdale for, as part of the wider regeneration of Skelmersdale and in light of the Tawd Valley Park Masterplan2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A REGENERATION PLAN FOR SKELMERSDALE TOWN CENTREReport 169 KB DownloadRead as text
PDF
Skelmersdale TC Regeneration Plan: Appendix AAppendix 1.5 MB Download

At this meeting

Whole meeting

Who was there

9 of 40 attended
JH
Jemma HunstoneCouncil Staff, expected
AS
Andrew SmithCouncil Staff, expected
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
VC
Councillor Vickie CumminsCommittee Member, present
GD
Councillor Gareth DowlingCommittee Member, present
DE
Councillor David EvansCommittee Member, present
JW
Councillor Jenny WilkieCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
AY
Councillor Adam YatesCommittee Member, present
JS
Jacqui Sinnott-LaceyOfficer, in attendance

All 40 on the meeting page

On this subject at West Lancashire

Search all
  1. A REGENERATION PLAN FOR SKELMERSDALE TOWN CENTREThis decision
  2. A Regeneration Plan for Skelmersdale Town CentreNoted

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open