Ormskirk Eastern Gateway Consultation Feedback

Agreed Executive 7 papers

Cabinet agreed this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item92

Resolved

A. That the agreed comments of the Executive Overview and Scrutiny Committee (Appendix 5) be noted. B. That the feedback from the public consultation exercise (Appendices 1 and 2) be noted. C. That, subject to securing funding from Lancashire County Council's Economic Recovery and Growth Fund and minor adjustments to the proposed works based on the feedback from the public consultation, delegated authority be given to the Corporate Director Place and Community, in consultation with the Portfolio Holders for Planning and Economic Regeneration, to negotiate and enter into a Collaboration Agreement with Lancashire County Council to undertake the works, as set out section 4 of the report, on a collaborative basis and to negotiate and enter into all other agreements as necessary for the scheme to proceed. D. That should the funding from the Lancashire County Council's Economic Recovery and Growth Fund not be secured, delegated authority be given to the Corporate Director Place and Community, in consultation with the Portfolio Holders for Planning and Economic Regeneration, to agree suitable changes to the scheme to meet the budget available and to enter into all appropriate agreements as necessary for the revised scheme to proceed. E. That concerns regarding the manoeuvrability of buses and coaches entering, exiting and travelling through the bus station be raised with Lancashire County Council for consideration as they finalise the detailed plans for the Ormskirk Eastern Gateway works.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To report to Cabinet the views of the Executive Overview and Scrutiny Committee and the outcome of the public consultation exercise on the Ormskirk Eastern Gateway project and to request conditional approval to enter into a Collaboration Agreement with Lancashire County Council to procure the works.

Recommendations

2.1That the agreed comments of the Executive Overview and Scrutiny Committee (Appendix 5) be noted.

2.2That the feedback from the public consultation exercise (Appendices 1 and 2) be noted.

2.3That, subject to securing funding from Lancashire County Council's Economic Recovery and Growth Fund and minor adjustments to the proposed works based on the feedback from the public consultation, delegated authority be given to the Corporate Director Place and Community, in consultation with the Portfolio Holders for Planning and Economic Regeneration, to negotiate and enter into a Collaboration Agreement with Lancashire County Council to undertake the works, as set out section 4 of this report, on a collaborative basis and to negotiate and enter into all other agreements as necessary for the scheme to proceed.

2.4Should the funding from the Lancashire County Council's Economic Recovery and Growth Fund not be secured, delegated authority be given to the Corporate Director Place and Community, in consultation with the Portfolio Holders for Planning and Economic Regeneration, to agree suitable changes to the scheme to meet the budget available and to enter into all appropriate agreements as necessary for the revised scheme to proceed.

2.5That concerns regarding the manoeuvrability of buses and coaches entering, exiting and travelling through the bus station be raised with Lancashire County Council for consideration as they finalise the detailed plans for the Ormskirk Eastern Gateway works.

Background

3.1At its meeting on 12th January 2021, Cabinet considered plans for the Ormskirk Eastern Gateway project, and resolved that the proposals set out within the report be publicly consulted upon, jointly with Lancashire County Council (LCC), and that the report be taken to Executive Overview & Scrutiny Committee on 28th January 2021 to seek their views on the proposals.

3.2At its meeting on 28th January 2021, the Executive Overview & Scrutiny Committee resolved to fully support the proposals to Cabinet and encourage the public to take part in the Council's Consultation and also thank LCC for their participation and partnership in the Ormskirk Eastern Gateway Scheme (see minute at Appendix 5).

3.3An on-line public consultation exercise, joint with LCC, was held from 25th January to 21st February 2021. Although the works will be delivered in four phases as described in paras 4.1 - 4.5 below, the consultation exercise was structured around three objectives:

 To create a more attractive and visually appealing town centre  To encourage walking and cycling  To improve and modernise the bus station

3.4A description of the associated works, plans and artist's impressions were included under each Objective, and respondents were invited to "score" how satisfied they were that the proposals would help achieve the objectives.

3.5A total 96 responses were received, 94 of which were "on-line" responses and 2 written submissions. The consultation results summary (how the proposals were rated against the objectives set for the project) and additional comments submitted by the public through the consultation are included as Appendices 1 and 2 respectively. An officer analysis of the additional comments submitted as part of the consultation responses is provided at Appendix 3.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ormskirk Eastern Gateway Appendix 1Appendix 127 KB Download
PDF
Ormskirk Eastern Gateway Appendix 2Appendix 521 KB Download
PDF
Ormskirk Eastern Gateway Appendix 3Appendix 35 KB Download
PDF
Ormskirk Eastern Gateway Appendix 4Appendix 302 KB Download
PDF
Ormskirk Eastern Gateway Appendix 5Appendix 21 KB Download
PDF
Ormskirk Eastern Gateway Appendix 6 EIAAppendix 137 KB Download
PDF
Ormskirk Eastern Gateway Consultation FeedbackReport 307 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 40 attended
JH
Jemma HunstoneCouncil Staff, expected
AS
Andrew SmithCouncil Staff, expected
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
VC
Councillor Vickie CumminsCommittee Member, present
GD
Councillor Gareth DowlingCommittee Member, present
DE
Councillor David EvansCommittee Member, present
JW
Councillor Jenny WilkieCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
AY
Councillor Adam YatesCommittee Member, present
JS
Jacqui Sinnott-LaceyOfficer, in attendance

All 40 on the meeting page

On this subject at West Lancashire

Search all
  1. Ormskirk Eastern Gateway Consultation FeedbackThis decision
  2. Ormskirk Eastern Gateway Proposals.Decided
  3. Ormskirk Eastern Gateway proposals and use of S106 monies on the Edge Hill Cycle LinkApproved
  4. 2018/1291/FUL - Land at the South-Eastern end of the Campus Edge Hill University, St. Helens Road, OrmskirkNoted

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies