A. That the 2020/21 HRA and Housing capital programme positions be noted. B. That call in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 25 March 2021.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide a summary of the Housing Revenue Account (HRA) and Housing capital programme positions for the 2020/21 financial year.
2.0RECOMMENDATIONS TO CABINET
2.1That the 2020/21 HRA and Housing capital programme positions be noted.
2.2That call in is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 25 March 2021.
3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE
3.1That the 2020/21 HRA and Housing capital programme positions be noted.
Background
4.1In February 2020, Council agreed the HRA revenue and capital budgets for the 2020/21 financial year. Subsequently in October 2020 Council noted the favourable financial outturn position of the 2019/20 HRA and Capital Investment Programme and approved a number of budget changes and allocations. Further changes were approved at mid-year reporting.
4.2From April 2020 the Government's new rents policy has been applied, which is a return to annual increases of up to CPI + 1%. There is also a new regulatory framework, which is anticipated, will be more robust. 5.0 HOUSING REVENUE ACCOUNT – PROJECTED OUTTURN
5.1A summary of the projected HRA revenue outturn against budget is set out in Appendix 1 and shows that a favourable budget variance of £480,000 is expected for 2020/2021, representing 1.9% of total turnover. This compares to the mid-year forecast of £710,000 (2.8% of total turnover.) The main change since mid-year is an increase in the forecast for responsive repairs and void revenue repairs, partly offset by a reduction in the forecast for supplies & services. The HRA remains in a healthy overall financial position.
5.2The main variances that are expected at this time are due to the following:
There are a number of vacant posts pending recruitment and consequently a favourable variance is anticipated on employee costs. Responsive repairs and voids revenue repairs are expected to be over budget due to further settlement of prior contract works costs. As both budgets are demand led there are various factors that can influence outturn. Planned revenue works are unlikely to be fully undertaken in year, and the size of this budget has been reviewed during 2021/22 budget setting. The remaining budget contingency is not expected to be used. Dwelling rents are better than budget.
5.3Consideration will be given to how the projected favourable budget variance of £480,000 should be used at year-end.
6.0CAPITAL INVESTMENT PROGRAMME
6.1A summary of the capital expenditure year to date position is shown in Appendix 2. Total expenditure to date is £2.966m which represents 39% of the total revised budget. It is expected that the major part of the revised capital budget will be spent in year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.