A. That the temporary suspension of part of the CIL Funding Programme 2023/24 as set out in the report be approved as follows: 1. That the relevant parts of the 2023/24 CIL Funding Programme detailed in this report will be suspended temporarily pending recommencement in Spring 2023 to cover two full financial years (2024/25 and 2025/26). 2. That amendment to the Governance Framework (see Appendix 1) is approved to allow the recommendation at A. to take place. Thereafter the original Governance Framework Timetable will return to the original format. B. That the resource issues regarding CIL and the need for contingency planning in relation to staff, be noted. C. That the Infrastructure Funding Statement be circulated via the Members Update, prior to it being formally published.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To inform Members and seek approval of a temporary suspension of part of the Community Infrastructure Levy (CIL) Funding Programme 2023/24.
2.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE
2.1That the Committee note the content of this report regarding proposed changes to the 2023/24 CIL Funding Programme and agreed comments be passed to Cabinet for their consideration.
3.0RECOMMENDATIONS TO CABINET
3.1That Cabinet, having regard to the content of this report and to the agreed comments of Executive Overview & Scrutiny Committee, approve the temporary suspension of part of the CIL Funding Programme 2023/24 as set out in this report:
1. That the relevant parts of the 2023/24 CIL Funding Programme detailed in this report will be suspended temporarily pending recommencement in Spring 2023 to cover two full financial years (2024/25 and 2025/26). 2. That amendment to the Governance Framework (see Appendix 1) is approved to allow the recommendation at 3.1 to take place. Thereafter the original Governance Framework Timetable will return to the original format. 3.2 That Members note the resource issues regarding CIL and the need for contingency planning in relation to staff.
Background
4.1Members will be aware that the CIL process allows the Council to raise funds from developers who are undertaking new building projects in the area. The money that is collected must be used to fund the provision, enhancement or maintenance of infrastructure to support new development. CIL only applies in areas where the Council has consulted on, and approved, a charging schedule which sets out its levy rates and has published the schedule on its website.
4.2The Council adopted a CIL Charging Schedule in June 2014 and approved a CIL and S106 Governance and Expenditure Framework ('the Framework') in 2015 that set out the structure for the allocation and spending of developer contributions collected through CIL and Section 106 obligations. The Framework was further updated in 2020 following legislative changes and is included at Appendix 1 to this report.
4.3In summary, the Framework explains how the Council invites stakeholders to submit schemes that they want to be funded, either in whole or part, by CIL monies collected by the Council. These schemes are then considered against set criteria, shortlisted and added to an Infrastructure Delivery Schedule. A further shortlisting exercise occurs and schemes that are deliverable over the next two years are added to a draft CIL Funding Programme. A further round of public consultation takes place before the CIL Funding Programme is finalised and approved by Cabinet. Only schemes that are included on the Infrastructure Delivery Schedule can access the Council's CIL monies.
5.0CURRENT POSITION
5.1The Regulations state the money collected in any given year must be split into three parts:
Part 1 Part 2 Part 3 Admin Fee Neighbourhood Portion Strategic Portion 5% 15% (or 25%) 80% (or 70%) TOTAL = 100%
5.2Part 1 – Admin Fee 5% of that year's collected money is retained by the Council as an administration fee. This will not be affected by the decision to temporarily suspend the update of the CIL Funding Programme as detailed in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.