Executive Overview & Scrutiny Committee noted this item on Thursday 9 November 2023. Below is the council's own wording, with the papers it was decided on.
That the reported be noted; and 2. That clarification be sought regarding the issues raised at paragraphs 6.3 and 6.4; and at Appendix C, page 46 regarding Changing Places; and 3. That points of clarification relating to paragraphs 6.3 and 6.4 and Changing Places will be circulated to the Committee following the meeting.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To agree a Revised General Revenue Account (GRA) Capital Programme for 2023/24 and provide an update on progress on capital schemes.
Recommendations
2.1That the revised Capital Programme, including budget adjustments and re- profiling contained within Appendix A and B, be approved.
2.2That progress against the Revised Capital Programme at the mid-year point be noted.
Background
3.1The Capital Programme is set on a three-year rolling basis and the Programmes for 2023/2024, 2024/2025 and 2025/2026 were approved by Council in February 2023.
3.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
3.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Public Sector programme is the subject of a separate report elsewhere on the agenda and will be also presented to this Cabinet meeting. This report concentrates on the GRA programme.
4.0REVISED CAPITAL PROGRAMME
4.1The original Capital Programme that was set for the 2023/2024 financial year together with underspends brought forward from the previous financial year totals £13.971m of which £3.448m is funded by Capital Receipts as shown in Appendix A - Funding of Capital Programme.
4.2Heads of Service have reviewed their respective schemes and are now proposing that changes are made as a result of more up to date information that has become available. This review process has incorporated a number of considerations including: • Re-profiling of schemes to match the anticipated timing of spending. • Increasing expenditure budgets to reflect new and / or additional external funding
4.3The proposed changes to the 2023/24 Programme are analysed in Appendix C. This shows a net decrease of £7.754m largely due to the following • Restructuring Costs - £152k • Capitalise revenue transformation costs - £300k • Burscough Sports Centre - £396k • Affordable Housing - £247k • Skelmersdale Town Centre - £3.258m • Play Strategy Improvements – £315k • Leisure Centre Projects (CIL funded) - £1.561m • UK Shared Prosperity Fund - £254k
The revised GRA Capital Programme totals £6.187m for 2023/24 following these changes.
4.4There is a new bid for £80K for a replacement Webaspx system that has been requested to be added to the Capital Programme.
5.0CAPITAL EXPENDITURE
5.1Generally, capital schemes are profiled with relatively low spending compared to budget in the early part of the financial year with increased spending as the year progresses. This reflects the fact that many new schemes have considerable lead in times. Other schemes are dependent on external partner funding and can only begin once their funding details have been finalised. Other related issues include contract retentions or contingencies that will only be spent some time after completion of the contract.
5.2For the current year, £2.674M (19.4%) of total expenditure has been incurred by the midyear (before capital Re-profiling). A substantial amount of this is due to spend on the Leisure Centres (£1.096M), Disabled Facilities Grants (£790k) and the Cycle Trail at Cheshire Lines (£436k).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive Overview & Scrutiny Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.