A. That the financial outturn position of the 2023/24 HRA and Capital Investment Programme be noted. B. That the allocation of revenue funds in paragraphs 4.4 and 4.5 of the report, be approved. C. That capital reprofiling and the release of capital budget identified in table 5.1 and paragraphs 5.2 and 5.3 of the report, be approved. D. That the switching of funding from HRA borrowing to HRA revenue contributions and capital receipts in paragraph 5.5 of the report, be approved. E. That the 2024/25 budget virements in paragraphs 5.6 and 5.7 of the report, be approved.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide a summary of the Housing Revenue Account (HRA) revenue and capital outturn positions for the 2023/24 financial year.
Recommendations
To Policy & Resources Committee
2.1That the financial outturn position of the 2023/24 HRA and Capital Investment Programme be noted and any comments forwarded to the Housing portfolio holder in advance of Council on 17 July 2024.
To Council
2.2That the financial outturn position of the 2023/24 HRA and Capital Investment Programme be noted.
2.3That the allocation of revenue funds in paragraphs 4.4 and 4.5 be approved.
2.4That capital reprofiling and the release of capital budget identified in table 5.1 and paragraphs 5.2 and 5.3 be approved.
2.5That the switching of funding from HRA borrowing to HRA revenue contributions and capital receipts in paragraph 5.5 be approved.
2.6That the 2024/25 budget virements in paragraphs 5.6 and 5.7 be approved. 3.0 BACKGROUND
3.1The HRA has recovered well after a deficit in 2022/23, despite rents being capped at 7% in 2023/24. Whilst this is still high from the perspective of our tenants, the contracts the Council operates did not generally have such a cap on them, for example the total value of the repairs contract revenue budget increased by around 13% from 2022/23 to 2023/24.
3.2This has created ongoing budget pressure in 2024/25 also. Coupled with increased regulatory expectations, ensuring a healthy and responsive funding base for the HRA is even more important than previously.
4.0HOUSING REVENUE ACCOUNT – REVENUE OUTTURN
4.1A summary of the HRA revenue outturn, and a comparison of how it compares to in-year forecasts of outturn, is set out in the table below. This shows that a favourable budget variance of £0.451m was achieved at the year end, which is around 1.5% of the total budget. This represents good financial performance. 2023/24 Q1 Q2 Q3 Budget Area Budget Forecast Forecast Forecast Outturn Comment £000's £000's £000's £000's £000's Pay settlement offset by vacancies after vcf Employee Expenses 4,577 150 200 150 78 Non budgeted redundancy costs £38k LCC pension fund contribution £53k less than budgeted Void and response repairs 5,370 0 0 250 140 Over budget due to retrospective costs for 2022/23. plus electrical testing External decorations budget not used offsets most Other premises costs 4,241 0 0 0 132 other cost pressures. £155k tenant disrepair claims. Transport costs 191 0 0 -25 -16 Contingency not used as costs contained within Budget contingency 390 0 -150 -200 -390 operational budgets. Cumulative effect of various smaller variances. Supplies and Services 1,590 0 0 0 -43 Net of funding hardship payments Estates recharge for HRA valuations. Legal recharge Support Services and for vacant post. Communications vacant post. 2,819 0 -110 -150 -229 internal income (net) Caretaking internal income for works completed. Includes £49k to the HRA Transformation reserve. Loan interest & Contribution £3,432k is 'fixed' interest and debt repayment. 3,492 0 0 0 -60 towards Repayment £60k external borrowing not required. As per February 2024 budget report, switch funding to Contributions to capital 7,205 0 0 0 500 reduce borrowing requirement. Dwelling rents -25,900 -100 -150 -250 -215 50 Fairlie stock and 39 rtb sales £123k Furnishing service Improvement due to £128k interest received on cash Other external income -3,975 -50 -50 -100 -348 balances and £148k leaseholder income towards roof, exterior works and window works. Total 0 0 -260 -325 -451 1.5% of total expenditure budget 4.2 The main budget pressures in 2023/24 were: • Pay settlement larger than budgeted. • Use of agency staff to fill key vacant posts. • Higher Contract inflation, particularly on the key repairs contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.