Resolved
A. That the Capital outturn position be and the proposed Capital allocation set out in Appendix 1 be noted. B. That the Capital programme and Re-profiling in Appendix 1 be approved.
Council noted this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
A. That the Capital outturn position be and the proposed Capital allocation set out in Appendix 1 be noted. B. That the Capital programme and Re-profiling in Appendix 1 be approved.
1.1To provide a summary of the capital outturn position on the General Revenue Account (GRA) for the 2023/2024 financial year.
2.0RECOMMENDATIONS FOR P&R COMMITTEE
2.1That the Capital outturn position and the proposed Capital allocation set out in Appendix 1 be noted.
2.2That the Capital programme and Re-profiling in Appendix 1 be noted.
3.0RECOMMENDATIONS FOR COUNCIL
3.1That the Capital outturn position be and the proposed Capital allocation set out in Appendix 1 be noted.
3.2That the Capital programme and Re-profiling in Appendix 1 be approved.
4.1The Capital Programme is set on a three-year rolling basis and the Programmes for 2023/24, 2024/25 and 2025/26 were approved by Council in February 2023. Most of the unused funding from the previous year has been transferred into the current year.
4.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
4.3It should be noted that the final accounts for the 2023/2024 year are subject to audit and the figures contained in this report are, potentially, subject to change. Members will be informed in due course of any significant matters arising from the Audit.
5.0CAPITAL PROGRAMME OUTTURN
5.1Expenditure on the GRA Capital Programme in the year was £7.152m against a budget of £15.122m), and a breakdown is provided in Appendix 1.
Table 1
Budget Area Expenditure Budget Variance Expenditure £000 £000 £000 % Corporate and Customer Services 249 1,977 -1,728 13% Environmental Services 179 506 -327 35% Finance Procurement & Commercial Property 133 966 -833 14% Housing and Regulatory Services 1,656 2,051 -396 81% Planning & Regulatory 535 749 -214 71% Wellbeing & Place 4,400 8,872 -4,472 50%
TOTAL 7,152 15,122 -7,970 47%
5.2The expenditure level was 47% of the total budget. The largest capital schemes were the Skelmersdale Town Centre Development which has a budget of £3.258m for 2023/24 and actual expenditure of £1.737M which is funded by borrowing and the Leisure Facilities Project, which had a budget of £2.782m and actual expenditure of £1.879m, which is funded by CIL (Community Infrastructure Levy) monies.
6.0RE-PROFILING OF EXPENDITURE APPROVALS
6.1100% spend against the Budget is never anticipated due mainly to reasons beyond the Council’s control. For example, some schemes are reliant on a significant amount of match funding and external contributions, and others are demand led or dependent upon decisions made by partners.
6.2Schemes that are not completed within the financial year for which they are scheduled are carried forward into the following financial year along with their unused expenditure and resource approvals. In line with our normal practice it is expected that the majority of the budget variance will be transferred into the 2024-2025 financial year to enable capital schemes to be completed. This is analysed in Appendix 1 – Capital programme.
7.0SIGNIFICANT VARIANCES
7.1Variances between the original estimated cost of a capital scheme and its final position are normal and the Council has established budgetary management and control procedures in place to minimise such variances. In total expenditure was £7.882m below budget, which is a variance of 53%. An analysis of significant variances by scheme is provided below with a full detailed analysis of all schemes provided in Appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2023-24 GRA Capital OutturnReport | 182 KB | DownloadRead as text |
PDF |
for 2023-24 GRA Capital OutturnAppendix 1 | 343 KB | Download |
PDF |
P&R Min GRA CapitalReport | 50 KB | Download |
Follow Council at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... | Decided | Open |
| 15 Jul 2026 | Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... | Approved | Open |
| 15 Jul 2026 | Public speakingThat the Motion to extend the deadline be approved. | Approved | Open |
| 15 Jul 2026 | GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... | Noted | Open |
| 15 Jul 2026 | 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.