Resolved
A. That the revised Capital Programme, including the budget adjustments contained within Appendix A, be agreed. B. That progress against the Revised Capital Programme at Quarter 2 be agreed.
Council agreed this item on Wednesday 11 December 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
A. That the revised Capital Programme, including the budget adjustments contained within Appendix A, be agreed. B. That progress against the Revised Capital Programme at Quarter 2 be agreed.
1.1To note the Revised General Revenue Account (GRA) Capital Programme for 2024/25 and provide an update on progress on capital schemes.
2.0RECOMMENDATIONS FOR P&R COMMITTEE
2.1That the revised Capital Programme, including the budget adjustments contained within Appendix A, be noted.
2.2That progress against the Revised Capital Programme at Quarter 2 be noted.
3.0RECOMMENDATIONS FOR COUNCIL
3.1That the revised Capital Programme, including the budget adjustments contained within Appendix A, be agreed.
3.2That progress against the Revised Capital Programme at Quarter 2 be agreed. 3.0 BACKGROUND
3.1The Capital Programme is set on a three-year rolling basis and the Programmes for 2024/2025, 2025/2026 and 2026/2027 were approved by Council in February 2024.
3.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
3.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Public Sector programme is the subject of a separate report elsewhere on the agenda and will be also presented to this Policy and Resources Committee. This report concentrates on the GRA programme.
4.0REVISED CAPITAL PROGRAMME
4.1The revised Capital Programme that is set for the 2024/2025 financial year together with underspends brought forward from the previous financial year totals £15.692m of which £3.258m has been spent to date as shown in Appendix A - 2024/2025 Revised Capital Programme Spend to Date Against Budget.
4.2The £160k for Resurfacing of Blaguegate Lane has now been returned to the Clinical Commissioning Group and has therefore been removed from the Capital Programme.
4.3The £47k grant that was expected for Play Strategy Improvements is unlikely to be received and has also therefore been removed from the Capital Programme.
4.4A budget of £3.188m in Total has been agreed for Burscough Sports Centre which is to be funded as follows. The capital programme has been amended to add the borrowing and CIL to the Capital Programme. Funding £000 Notes Grant from West Lancashire Community Leisure Trust 75 Receipts 321 217k of this budget been spent in 2023/24 leaving £703k for CIL (Community Infrastructure 2024/25 (shown in Levy) 920 appendix A) Borrowing 1872
Total 3188
4.5The following items are part of the transformation budget and are not expected to be spent until June 2025 and will therefore be re-profiled into 2025/26.
Description £000 I C T Infrastructure -150 ICT Development Programme -754 Website -20 Invest to Save Digital Services -59 CRM System -61 Microsoft Enterprise Site Licence -166 Website development -100 Communication devices -40 Digital innovation and the continued development of -80 ServiceNow
Total -1430
5.0CAPITAL EXPENDITURE
5.1Generally, capital schemes are profiled with relatively low spending compared to budget in the early part of the financial year with increased spending as the year progresses. This reflects the fact that many new schemes have considerable lead in times. Other schemes are dependent on external partner funding and can only begin once their funding details have been finalised. Other related issues include contract retentions or contingencies that will only be spent some time after completion of the contract.
5.2For the current year, £296k (3.75%) of expenditure from borrowing has been incurred by the end of Quarter 2.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for GRA Capital Q2 2024/25Appendix 1 | 236 KB | Download |
PDF |
GRA Capital Q2 2024/25 Monitoring ReportReport | 225 KB | DownloadRead as text |
Follow Council at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... | Decided | Open |
| 15 Jul 2026 | Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... | Approved | Open |
| 15 Jul 2026 | Public speakingThat the Motion to extend the deadline be approved. | Approved | Open |
| 15 Jul 2026 | GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... | Noted | Open |
| 15 Jul 2026 | 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.