A. That the public consultation feedback report, in Appendix 3, be noted. B. That Strategic CIL monies be allocated to the following 5 projects, to be delivered in 2025 - 2027: I. £11,610 - New Multi-Play Unit Equipment at Rufford Play Area. Rufford and Holmeswood Parish Council II. £79,868 - Firswood Road Bridge Safety Scheme, Lathom South. Lathom South Parish Council III. £78,100 - Helmsdale Play Area equipment replacement and improvements, Skelmersdale. WLBC IV. £95,000 - Fairy Glen Environmental Improvements Phase 2, Appley Bridge. WLBC V. £96,320 - Skelmersdale Heritage Trail and Pond Link Path at Tawd Valley Park. WLBC
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To present bids received and consulted upon through the CIL Funding Programme for 2024 and to shortlist bids and propose final recommendations for the allocation and expenditure of CIL Funding Programme in 2024.
2.0RECOMMENDATIONS TO POLICY AND RESOURCES COMMITTEE
2.1That the public consultation feedback report provided at Appendix 3 be noted.
2.2That Strategic CIL monies be allocated to the following 5 projects, to be delivered in 2025 - 2027:
• £11,610 - New Multi-Play Unit Equipment at Rufford Play Area. Rufford and Holmeswood Parish Council • £79,868 - Firswood Road Bridge Safety Scheme, Lathom South. Lathom South Parish Council • £78,100 - Helmsdale Play Area equipment replacement and improvements, Skelmersdale. WLBC • £95,000 - Fairy Glen Environmental Improvements Phase 2, Appley Bridge. WLBC • £96,320 - Skelmersdale Heritage Trail and Pond Link Path at Tawd Valley Park. WLBC 3.0 BACKGROUND
3.1The Council has been charging a Community Infrastructure Levy (CIL) on certain new developments in its area since 1 September 2014. A significant portion (70 or 80%, The Strategic Portion) of the revenue that is collected is to be used to fund the provision, improvement, replacement, operation or maintenance of infrastructure to support new development in West Lancashire.
3.215 or 25% of the revenue collected is handed over to the Parish or Town Council in which the development occurred (the higher percentage is where the Parish or Town Council has opted to make a Neighbourhood Plan) – this is known as the Neighbourhood Community Infrastructure Levy (NCIL) Portion. In areas where there is no Parish Council, such as Skelmersdale and Ormskirk, any Neighbourhood Portion of CIL is retained by the Council to be spent on projects in the locality.
3.3The Council's Infrastructure Funding Statement sets out the types of infrastructure that will be provided using CIL monies. There are three main types of infrastructure identified:
• Strategic transport and highways improvements – to include cycle network provision and improvements, footpaths, bus stops; • Strategic green infrastructure – including improvements to and provisions of: parks, amenity open space, play areas, outdoor sports facilities and playing pitches, semi-natural open space; • Community Facilities – including libraries, health facilities, community centres, public realm, leisure centres.
3.4The Council approved the revised Governance and Expenditure Framework for CIL and Section 106 (The Framework) and necessary constitutional changes in September 2024. This document sets out the structure of the CIL Funding Programme (CFP) for the allocation and spending of developer contributions collected through CIL and Section 106 obligations on an annual basis.
3.5The Framework explains how the Council invite stakeholders to submit projects that they want to be funded, either in whole or part, by CIL monies collected by the Council. These projects are then to be considered against set criteria, shortlisted and added to the Infrastructure Delivery Schedule (IDS).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.