Policy & Resources Committee, Wednesday 19 November 2025 at 7.00pm

Community Infrastructure Levy (CIL) Funding Programme 2025

Noted Committee 4 papers

AI summaryWest Lancashire's Policy and Resources Committee approved CIL funding for 13 projects including £984,101 of Strategic CIL, and deferred a £299,360 heritage park bid.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBecconsall Heritage Park deferred to next meeting
Money£984,101 of Strategic CIL allocatedPlus Ormskirk and Skelmersdale NCIL and Section 106
What happens nextInform bidders, arrange legal agreementsThen deliver projects in 2026 to 2028
Who it affectsWest Lancashire residents and visitorsParishes, clubs, trust and county council

What was decided

Allocated Strategic CIL to 8 projects, including the Burscough to Parbold towpath improvement at £683,875, plus transport, heritage and play projects. Report P39

Allocated Ormskirk Neighbourhood CIL to 4 projects, including £100,000 for Whittle Drive Changing Facilities and £42,300 for the Waterworks Road public right of way. Report P40

Deferred the £299,360 Becconsall Heritage Park bid to the next meeting of the Committee.

Why

Public consultation between 15 July and 12 August 2025 received 194 responses, with general support for the shortlisted projects. Report 5.1, 5.3

Strategic CIL of £3,008,013.40 was collected in 2024/2025, with over £11m held in the CIL balance including commitments. Report 4.1

What happens next

Officers will notify successful bidders and put legal agreements in place before awarding funding.

Project spending and delivery will be reported in future annual Infrastructure Funding Statements published by 31 December each year.

The Whittle Drive changing facilities CIL allocation is being re-set to give a new expenditure deadline of April 2027. Report 4.9

The money

  • £984,101 Total Strategic CIL allocated Report 6.2
  • £222,354 Total Ormskirk Neighbourhood CIL allocated Report 6.2
  • £45,000 Total Section 106 monies allocated Report 6.2
  • £15,000 Total Skelmersdale Neighbourhood CIL allocated Report 6.2
  • £683,875 Burscough to Parbold towpath improvement (largest Strategic CIL award) Report P39
  • £100,000 Whittle Drive Changing Facilities Improvements Report P40
  • £299,360 Becconsall Heritage Park bid deferred to next meeting
  • £3,008,013.40 Strategic CIL collected and retained during 2024/2025 Report 4.1

Options considered

  • Chosen: Allocate Strategic CIL to 8 projects. Public consultation showed support and projects meet the spending criteria Report P39, 5.3
  • Chosen: Allocate Ormskirk Neighbourhood CIL to 4 projects. Projects support local infrastructure and meet the criteria Report P40
  • Chosen: Mix Strategic CIL, Skelmersdale NCIL and Section 106 for Longhey Kickabout. Matches planning permission terms for the £45,000 Section 106 contribution Report P41, 4.5, 4.6
  • Rejected: Allocate £299,360 to Becconsall Heritage Park. Deferred to the next meeting of the Policy and Resources Committee

Implications

  • Financial: CIL and Section 106 monies only; met from existing resources with no call on the general fund. Report 9.1
  • Climate: Supports the Council's Climate Change Strategy by funding active travel and green space improvements. Report 8.2
  • Risk: Risks around timely collection of CIL from developers, but current balances are sufficient to fund these projects. Report 10.1
  • Equalities: An Equality Impact Assessment was prepared and the results fed into the recommendations. Report P55
  • Other: Expected positive effects on health and wellbeing through play, sport, green infrastructure and health facilities. Report 11.1

Who and where

  • Canal and River Trust (Burscough to Parbold towpath) Report P39
  • West Lancashire Light Railway Trust (Y Caban building) Report P39
  • Rufford Parish Council and Burscough Town Council (play area and orchard) Report P39
  • Parbold Memorial Stone Committee Report P39
  • WLBC Economic Regeneration (Ormskirk town centre and clock tower) Report P39, P40
  • Lancashire County Council (bus stops and public right of way) Report P39, P40
  • Ormskirk West End Football Club and WLBC Leisure (Whittle Drive) Report P40
  • WLBC Ranger Service and residents of Ashurst, Skelmersdale (Longhey Kickabout) Report P41, 4.5

Timeline

  • 1st September 2014: West Lancashire started charging CIL on certain new developments Report 3.1
  • 11 April 2025: Bid invitation sent to stakeholders Report P22
  • 12 May 2025: Deadline for receipt of project bids Report P23
  • 15 July to 12 August 2025: Public consultation on the draft CIL Funding Programme Report 5.1
  • 19 November 2025: Policy and Resources Committee decision
  • 2026 to 2028: Project delivery window for funded schemes Report 1.1
  • April 2027: New expenditure deadline for Whittle Drive changing facilities CIL allocation Report 4.9
  • 31st December each year: Annual Infrastructure Funding Statement published

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on certain new developments collected since 1 September 2014
  • NCIL: Neighbourhood CIL, 15% or 25% of CIL passed to the relevant parish or town council, or retained by the council where there is no parish
  • Section 106: Monies secured through a legal agreement with a developer for a specific purpose
  • Strategic Portion: 70% or 80% of CIL retained by the council for strategic infrastructure
  • IDS: Infrastructure Delivery Schedule, a working list of infrastructure projects that may be needed to support growth
  • Whittle Drive: Site in Ormskirk with football pitches and changing facilities used by Ormskirk West End FC
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item127

Resolved

A. That the consultation feedback report at Appendix 2 of the report be noted. B. That Strategic CIL monies be allocated to the following 8 projects: i. Burscough to Parbold towpath improvement, Canal and River Trust - £683,875 ii. West Lancashire Light Railway Y Caban multipurpose building, West Lancashire Light Railway Trust - £90,200 iii. Rufford Recreation Ground Play Area Safety Upgrade, Rufford Parish Council - £12,660 iv. Burscough Community Orchard, Burscough Town Council - £17,916 v. Parbold Memorial Stone, Parbold Memorial Stone Committee - £3,250 vi. Ormskirk Town Centre Access Restriction Measures, WLBC Economic Regeneration - £79,200 vii. Wigan Road, Ormskirk Bus Stop Improvements, Lancashire County Council - £48,500 viii. St Helens Road, Edge Hill University, Ormskirk Bus Stop Improvements, Lancashire County Council - £48,500 C. That Ormskirk Neighbourhood CIL monies be allocated to the following 4 projects: i. Ormskirk Clock Tower Repairs and Maintenance, WLBC Economic Regeneration - £48,750 ii. Whittle Drive Pitch Improvements, Ormskirk West End Football Club - £31,304 iii. Whittle Drive Changing Facilities Improvements, WLBC Leisure - £100,000 iv. Waterworks Road Public Right of Way, Lancashire County Council - £42,300 D. That Strategic CIL, Skelmersdale Neighbourhood CIL and Section 106 monies be allocated to the following project: i. Longhey Kickabout Area, Skelmersdale, WLBC Ranger Service - £30,750 of Strategic CIL, £15,000 of Neighbourhood CIL monies and £45,000 of Section 106 monies (total £90,750) E. That the project - Creation of Heritage Park / Gateway Facility for the Douglas Linear Park and Footpaths – Becconsall Heritage Park – Lancashire Heritage (2018) Community Interest Company – CIL funding requested £299,360 – be deferred for consideration at the next meeting of Policy & Resources Committee.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Policy & Resources Committee

Purpose of the report

1.1To present bids received and consulted upon through the Community Infrastructure Levy (CIL) Funding Programme for 2025 and to propose final recommendations for the allocation and expenditure of CIL and Section 106 monies for projects to be delivered in 2026 to 2028.

Recommendations

2.1That the public consultation feedback report at Appendix 2 be noted.

2.2That Strategic CIL monies be allocated to the following 8 projects:

• Burscough to Parbold towpath improvement, Canal and River Trust - £683,875 • West Lancashire Light Railway Y Caban multipurpose building, West Lancashire Light Railway Trust - £90,200 • Rufford Recreation Ground Play Area Safety Upgrade, Rufford Parish Council - £12,660 • Burscough Community Orchard, Burscough Town Council - £17,916 • Parbold Memorial Stone, Parbold Memorial Stone Committee - £3,250 • Ormskirk Town Centre Access Restriction Measures, WLBC Economic Regeneration - £79,200 • Wigan Road, Ormskirk Bus Stop Improvements, Lancashire County Council - £48,500 • St Helens Road, Edge Hill University, Ormskirk Bus Stop Improvements, Lancashire County Council - £48,500

2.3That Ormskirk Neighbourhood CIL monies be allocated to the following 4 projects:

• Ormskirk Clock Tower Repairs and Maintenance, WLBC Economic Regeneration - £48,750 • Whittle Drive Pitch Improvements, Ormskirk West End Football Club - £31,304 • Whittle Drive Changing Facilities Improvements, WLBC Leisure - £100,000 • Waterworks Road Public Right of Way, Lancashire County Council - £42,300

2.4That Strategic CIL, Skelmersdale Neighbourhood CIL and Section 106 monies be allocated to the following project:

• Longhey Kickabout Area, Skelmersdale, WLBC Ranger Service - £30,750 of Strategic CIL, £15,000 of Neighbourhood CIL monies and £45,000 of Section 106 monies (total £90,750)

Background

3.1The Council has been charging a Community Infrastructure Levy (CIL) on certain new developments in its area since 1st September 2014. A significant portion (70 or 80%, the Strategic Portion) of the revenue that is collected is to be used to fund the provision, improvement, replacement, operation or maintenance of infrastructure to support new development in West Lancashire.

3.215 or 25% of the revenue collected is handed over to the Parish or Town Council in which the development occurred (the higher percentage is where the Parish or Town Council has opted to make a Neighbourhood Plan) – this is known as the Neighbourhood Community Infrastructure Levy (NCIL) Portion. In areas where there is no Parish Council, such as Skelmersdale and Ormskirk, any NCIL Portion of CIL is retained by the Council to be spent on projects in the locality.

3.3The Council's Infrastructure Funding Statement sets out the types of infrastructure that will be provided using CIL monies. There are three main types of infrastructure identified:

• Strategic transport and highways improvements – including cycle network and footpath provision and improvements; • Strategic green infrastructure – including improvements to and provisions of: parks, amenity open space, play areas, outdoor sports facilities and playing pitches, semi-natural open space; • Community Facilities – including libraries, health facilities, community centres, public realm, leisure centres.

3.4The Council approved a CIL and Section 106 Governance and Expenditure Framework (The Framework) in 2015 that set out the structure of the CIL Funding Programme for the allocation and spending of developer contributions collected through CIL and Section 106 obligations; this document was last updated in 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Community Infrastructure Levy (CIL) Funding Programme 2025Appendix 1 124 KB Download
PDF
for Community Infrastructure Levy (CIL) Funding Programme 2025Appendix 2 98 KB Download
PDF
for Community Infrastructure Levy (CIL) Funding Programme 2025Appendix 3 121 KB Download
PDF
Community Infrastructure Levy (CIL) Funding Programme 2025Report 187 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 43 attended
YG
Councillor Yvonne GagenChairperson, apologies, sent representative
GD
Councillor Gareth DowlingVice-Chairperson, present
MA
Councillor Mark AndersonCommittee Member, apologies, sent representative
RB
Councillor Robert BaileyCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
TD
Councillor Thomas de FreitasCommittee Member, present
NF
Councillor Neil FureyCommittee Member, present
NH
Councillor Nikki HennessyCommittee Member, present
SE
Councillor Sarah E LawtonCommittee Member, present
AO
Councillor Adrian OwensCommittee Member, present
MS
Councillor Melissa S ParlourCommittee Member, present

All 43 on the meeting page

On this subject at West Lancashire

Search all
  1. Community Infrastructure Levy (CIL) Funding Programme 2025This decision
  2. Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewDecided
  3. Allocation of community infrastructure levy (cil) funding for phase 2 upgrades to burscough wellbeing & leisure hubApproved
  4. Report on the neighbourhood community infrastructure levy (ncil) portion to parish/town councils 01 october 2024 to 31 march 2025Noted
  5. Community Infrastructure Levy (CIL) Funding Programme 2024Noted
  6. Report on the neighbourhood community infrastructure levy (ncil) portion to parish/town councils 1 april 2024 to 30 september 2024Noted

More from West Lancashire Policy & Resources Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MinutesThat the minutes of the meeting held on Wednesday, 25 March 2026 be received as a correct record and signed by the Ch... Decided Open
25 Jun 2026 Terms of ReferenceThat the Terms of Reference be noted. Noted Open
25 Jun 2026 Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen... Noted Open
25 Jun 2026 Public SpeakingA request to speak in relation to the item, Community Infrastructure Levy (CIL) Funding Programme 2025 – Becconsall H... Noted Open
25 Jun 2026 Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewThat in accordance with Option 1 of the report, CIL funding is not allocated towards Becconsall Heritage Park. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies