A. That the Masterplan for Skelmersdale Town Centre be approved. B. That the outcome of the public consultation and the changes made to the Masterplan as a result, be noted. C. That TVDL be approved as the scheme Master Developer, subject to compliance with procurement regulations. D. That the Director of Planning, Economy and Wellbeing, in discussion with the relevant Lead Member, be given delegated authority to undertake all actions required to ensure delivery of the Masterplan, including but not limited to progressing funding applications, negotiations with external partners and entering into any necessary legal agreements where appropriate.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To consider public consultation feedback on the draft Skelmersdale Town Centre Masterplan and seek approval for the final version.
1.2To consider delivery options for the Masterplan and approve Tawd Valley Developments Ltd (TVDL) as the scheme Master Developer, supporting West Lancashire Borough Council in implementation.
1.3To note that a Delivery Plan is in development and will set out the phasing, funding mechanisms and key stakeholder engagement required to support the Masterplan's implementation.
Recommendations
2.1That the Masterplan for Skelmersdale Town Centre be approved.
2.2That the outcome of the public consultation and the changes made to the Masterplan as a result be noted.
2.3That TVDL be approved as the scheme Master Developer, subject to compliance with procurement regulations.
2.4That the Director of Planning, Economy and Wellbeing, in discussion with the relevant Lead Member, be given delegated authority to undertake all actions required to ensure delivery of the Masterplan, including but not limited to progressing funding applications, negotiations with external partners and entering into any necessary legal agreements where appropriate. 3.0 BACKGROUND 3.1 West Lancashire Borough Council (WLBC) and Lancashire County Council (LCC) commissioned Tetra Tech (TT) and Lambert Smith Hampton (LSH) to develop a Masterplan for Skelmersdale town centre, including the former Glenburn school site to the south. Over the past three years, the plan has been shaped by extensive research and engagement. Tawd Valley Developments Ltd (TVDL) was engaged in July 2023 to provide technical expertise in finalising the Masterplan.
3.2Without intervention, Skelmersdale’s town centre faces continued economic stagnation, limited connectivity and a weak evening economy. A structured regeneration approach is required to improve infrastructure, stimulate private investment and create a more vibrant town centre. While recent developments have increased market interest, public sector leadership is necessary to de-risk sites and enable viable investment.
3.3Previous regeneration efforts have faced challenges in delivery, leading to public scepticism. This Masterplan differs by incorporating a structured phasing approach, clearer governance through TVDL and alignment with Homes England and other funding mechanisms, ensuring deliverability.
3.4The Masterplan aligns with WLBC’s corporate priorities, the emerging Economic Development Strategy and the Local Plan, supporting investment, job creation and sustainable growth. It meets National Planning Policy Framework (NPPF) objectives, including housing targets and integrates healthy town planning principles, enhancing connectivity and public realm improvements through Tawd Valley Park.
Masterplan Overview
3.5The Masterplan focuses on four key areas to unlock economic growth, attract investment and create a more sustainable town centre.
3.6Town Centre Revitalisation: The heart of the Masterplan focuses on modernising and diversifying the town centre, introducing new commercial spaces, residential development and public realm improvements. The western entrance of the Concourse Shopping Centre will be redesigned to improve access and the existing bus interchange will be relocated to street level, improving accessibility and pedestrian flow. A Business Incubator will support enterprise and job creation, complementing new leisure and cultural facilities to establish a stronger evening economy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.