Resolved
That the HRA Q1 position for revenue and capital be noted.
Policy & Resources Committee noted this item on Wednesday 24 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the HRA Q1 position for revenue and capital be noted.
1.1To provide a summary of the Housing Revenue Account (HRA) and Housing capital programme positions for the 2025/26 financial year based upon quarter 1 monitoring (Q1).
2.0RECOMMENDATIONS TO LANDLORD SERVICES COMMITTEE
2.1That the HRA Q1 position for revenue and capital be noted.
3.0RECOMMENDATIONS TO POLICY & RESOURCES COMMITTEE
3.1That the HRA Q1 position for revenue and capital be noted.
4.1In February 2025, Council agreed the HRA revenue and capital budgets for the 2025/26 financial year. The 2024/25 outturn report to Council in July 2025 agreed some budget reprofiling and adjustments.
4.2Previous HRA reports advised of a surge of 97 RTB (right to buy) applications in November 2024 due to a significant reduction in the level of RTB discount available after that date. Previous assumptions that 80 of these will reach sales completion are still being assumed though there is a timing delay in this happening. 5.0 HRA – 2025/26 Q1 Projected Outturn
5.1A summary of the projected HRA revenue outturn against budget is set out in the table below. The HRA Q1 forecast is around £270k (0.9%) better than budget.
5.2The favourable variance at Q1 is primarily due to the timing delay in RTB completions from the surge in November 2025. It is being assumed that these will complete in due course during 2025/26.
5.3Four Gardeners responsible for work on HRA land have been moved from Environmental Services GRA to the HRA. This creates some pressure on staff cost budgets that is offset by relief on the recharge budget. The net effect is nil. 2025/26 Q1 Var. Budget Area Budget £000 Comment £000 Forecast assumes that current favourable variance will augment the February 2025 approved budget proposal to restructure Neighbourhoods. Employee Expenses 5,773 134 £134k adverse is four gardeners moved from ES, over budget but netted against recharges below budget. Void and response repairs 7,125 0 plus electrical testing Other premises costs 4,243 0
Transport costs 225 -20 Car user allowances and Fleet costs.
Budget contingency 290 0 Assuming that all contingency will be used.
Supplies and Services 1,339 0 Support Services and Four Gardeners moved back to HRA from ES GRA by ROD therefore staff 2,612 -134 internal income (net) costs over budget and recharges under budget. Net zero. £3,057k interest – self-financing debt Loan interest & Contribution 3,740 0 £402k existing debt repayment set aside towards Repayment £345k interest – new external debt if required. Contributions to capital 6,164 0 Forecast based on early run rate which reflects still high but reducing void Dwelling rents -28,321 -250 rates in Q1, offset because RTB applications from last November which have net yet completed. Other external income -3,189 0 Total 0 -270 6.0 Capital Investment Programme
6.1The table below maps the 2025/26 HRA capital budget, (including budget proposals), approved in February 2025 and the 2024/25 capital slippage approved in July 2025. Together with the latest TVD scheme approvals these create the revised 2025/26 HRA capital budget of £25.214m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA Q1 Budget Monitoring: Revenue & CapitalReport | 172 KB | DownloadRead as text |
Follow Policy & Resources Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | MinutesThat the minutes of the meeting held on Wednesday, 25 March 2026 be received as a correct record and signed by the Ch... | Decided | Open |
| 25 Jun 2026 | Terms of ReferenceThat the Terms of Reference be noted. | Noted | Open |
| 25 Jun 2026 | Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen... | Noted | Open |
| 25 Jun 2026 | Public SpeakingA request to speak in relation to the item, Community Infrastructure Levy (CIL) Funding Programme 2025 – Becconsall H... | Noted | Open |
| 25 Jun 2026 | Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewThat in accordance with Option 1 of the report, CIL funding is not allocated towards Becconsall Heritage Park. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.