Programme of Essential Repairs - Nye Bevan and Park Pool

Noted Committee 3 papers

AI summaryWest Lancashire Council backs a five-year essential repairs framework for Nye Bevan and Park Pool, with officers to bid for up to £10.5m of Strategic CIL funding and report back in July.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree-part decision on pool repairs noted and agreed
MoneyUp to £10.5mStrategic Community Infrastructure Levy (CIL) bid for leisure infrastructure
What happens nextReport to July CouncilAlongside already commissioned feasibility work
Who it affectsNye Bevan and Park Pool usersTwo leisure facilities in West Lancashire

What was decided

The condition evidence, operational risk profiles and proposed five-year Essential Repairs Programme framework for Nye Bevan and Park Pool were noted. Report 2.1

The Director of Planning, Economy & Wellbeing was given delegated authority to prepare full costed options, with any required surveys or technical studies funded from the existing Leisure Facilities Project capital budgets agreed by Council in December 2025, and to report back to July Council.

Officers were authorised to work up a detailed programme of works and a fully costed leisure infrastructure project, and to submit a formal bid of up to £10.5m of Strategic CIL funding under the Council's Governance and Expenditure Framework.

Why

Officers had set out condition evidence and operational risk profiles pointing to the need for a structured five-year programme of essential repairs at the two pools. Report 2.1, P1

Existing Leisure Facilities Project capital budgets were already in place from a December 2025 Council decision and could fund any further surveys or technical studies needed.

What happens next

The Director of Planning, Economy & Wellbeing will prepare full costed options for the five-year Essential Repairs Programme, combining them with the feasibility work already commissioned.

Officers will work up a detailed programme of works and a fully costed project for leisure infrastructure and submit a formal Strategic CIL bid of up to £10.5m.

A combined report will be brought back to the July meeting of Council.

The money

  • £10.5m Formal bid for Strategic Community Infrastructure Levy funding for leisure infrastructure
  • up to £10.5m Strategic CIL allocation referenced for leisure infrastructure in the officer report Report 2.1

Options considered

  • Chosen: Amendment moved by Councillor Bailey (as set out in the report) Report P1

Implications

  • Financial: Existing Leisure Facilities Project capital budgets, agreed by Council in December 2025, will be used to fund required surveys and technical studies.
  • Financial: A formal Strategic CIL bid of up to £10.5m will be submitted under the Council's Community Infrastructure Levy and Section 106 Governance and Expenditure Framework.
  • Risk: Operational risk profiles at Nye Bevan and Park Pool were noted, framing the case for a structured five-year repairs programme. Report 2.1
  • Other: Delegated authority is given to the Director of Planning, Economy & Wellbeing to develop costed options before reporting back to Council.

Who and where

  • Users of Nye Bevan Pool Report 2.1, P1
  • Users of Park Pool Report 2.1, P1
  • West Lancashire residents who use the borough's leisure facilities Report 2.1, P1

Timeline

  • December 2025: Existing Leisure Facilities Project capital budgets agreed by Council
  • 26 February 2026: Council considers and decides on the Essential Repairs Programme amendment Report P1
  • July 2026 (July Council): Director of Planning, Economy & Wellbeing to report back with full costed options and feasibility work

Plain English for the jargon

  • Strategic CIL: Strategic portion of the Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • Governance and Expenditure Framework: The Council's rules governing how CIL and Section 106 funds are allocated and spent
  • Essential Repairs Programme: A five-year planned framework of works to address condition and operational risks at Nye Bevan and Park Pool
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item116

Resolved

A. That the condition evidence, operational risk profiles and proposed five ? year Essential Repairs Programme framework for Nye Bevan and Park Pool are noted. B. That the Director of Planning, Economy & Wellbeing be given delegated authority to prepare full costed options for the five ? year Essential Repairs Programme, with any required surveys or technical studies funded from the existing Leisure Facilities Project capital budgets agreed by Council in December 2025. Thereafter to report back to July Council along with the feasibility work already commissioned. C. That Officers be authorised to work up a detailed programme of works and a fully costed project for leisure infrastructure, and to submit a formal bid up to £10.5m of Strategic Community Infrastructure Levy (CIL) funding in accordance with the Council’s Governance and Expenditure Framework.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

PROGRAMME OF ESSENTIAL REPAIRS – NYE BEVAN AND PARK POOL Amendment to be moved by Councillor Bailey

2.1That the condition evidence, operational risk profiles and proposed five‑year Essential Repairs Programme framework for Nye Bevan and Park Pool are noted. 2.2 That the Director of Planning, Economy & Wellbeing be given delegated authority to prepare full costed options for the five‑year Essential Repairs Programme, with any required surveys or technical studies funded from the existing Leisure Facilities Project capital budgets agreed by Council in December 2025. Thereafter to report back to July Council along with the feasibility work already commissioned. 2.3 That in principle, Members agree to ringfence £10.5m Strategic Community Infrastructure Levy (CIL) allocation for Leisure infrastructure. Any future spend will be subject to a separate Strategic CIL application and approval in line with the Council’s Community Infrastructure Levy and Section 106 Governance and Expenditure Framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amdt PROGRAMME OF ESSENTIAL REPAIRS Leisure reportReport 62 KB DownloadRead as text
PDF
for PROGRAMME OF ESSENTIAL REPAIRS: LEISUREAppendix 1 66 KB Download
PDF
Programme of Essential Repairs: Nye Bevan and Park PoolReport 187 KB Download

At this meeting

Whole meeting

Who was there

44 of 57 attended
AM
Councillor Anne Mary FennellMayor, present
SP
Councillor Suresh PatelDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
TD
Councillor Terence DevineCommittee Member, present
GD
Councillor Gareth DowlingCommittee Member, present

All 57 on the meeting page

On this subject at West Lancashire

Search all
  1. Programme of Essential Repairs - Nye Bevan and Park PoolThis decision
  2. Programme of essential repairs for nye bevan and park pool leisure centresNoted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open