West Lancashire Borough Council
Council, Wednesday 15 July 2026 at 7.30pm

Ormskirk to Burscough Linear Park Land Agreement and Active Travel England Grant Funding

Decided Committee 4 papers

AI summaryWest Lancashire Borough Council has accepted a £332,802 Active Travel England grant via Lancashire County Council to fund the Ormskirk to Burscough Linear Park cycle link, and authorised officers to build it and buy the needed land.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated authority given to accept grant, build scheme, and acquire land
Money£332,802 grantConsolidated Active Travel Fund, via Lancashire County Council
What happens nextSign grant agreement and negotiate landLandowner agreement in principle, formal deal pending
Who it affectsOrmskirk to Burscough residents and landownersCycle link from Highgrove Park to Abbey Lane

What was decided

The Director of Finance and Corporate Resources was given delegated authority to accept the £0.332m Consolidated Active Travel Fund grant from Active Travel England, administered by Lancashire County Council. Report 2.1

The Director of Planning, Economy and Wellbeing was given delegated authority to carry out the works, including construction of the Linear Park Cycle Link east of Highgrove Park in Ormskirk to Abbey Lane in Burscough. Report 2.2

The Director of Finance and Corporate Resources, with the Leader, was given delegated authority to take all necessary steps to purchase any applicable land interest, with costs drawn from the project's capital budget. Report 2.3

Why

The scheme addresses a funding shortfall identified in the WSP Group Feasibility Study and supports the Council's Local Plan and Green Infrastructure and Cycling Strategy objectives for a Linear Park between Ormskirk and Burscough. Report 3.4, 3.6

A substantial and contiguous section of the route is in private ownership, so securing land from the primary landowner is essential to the project's deliverability, and agreement in principle has already been reached. Report 3.2, 4.1

What happens next

Sign the Grant Funding Agreement for the £332,802 CATF award, pending the approval now granted. Report 4.2

Conclude formal legal agreements with the primary landowner to secure the necessary land interests and rights, with any compensation determined by valuation and legal advice. Report 4.1, 6.2, 8.1

Arcus Consulting continues professional services for RIBA Stages 2 to 6, with break clauses at Stages 3 and 4 tied to funding and land agreements. Report 3.7, 6.2

The money

  • £0.332m Consolidated Active Travel Fund grant, via Lancashire County Council Report 2.1
  • £332,802 CATF grant awarded by Active Travel England and administered by Lancashire County Council Report 1.1, 4.2
  • £364,200 Previously approved CIL and S106 monies for the project (Cabinet, September 2023) Report 3.3, 6.1
  • £90,645 plus VAT Arcus Consulting commission for RIBA Stages 2 to 6 Report 6.2
  • £51,000 Currently committed Arcus expenditure for RIBA Stages 2 and 3 Report 6.2

Options considered

  • Chosen: Proceed with voluntary land purchase and accept the CATF grant (preferred route). Secures funding shortfall and supports scheme viability; agreement in principle already reached with the primary landowner Report 3.5, 3.6, 4.1
  • Rejected: Decline to purchase the land interest. Likely to delay progress, increase costs, harm value for money and may force use of compulsory purchase powers, which would cost more, take longer and damage the Council's reputation Report 5.1

Implications

  • Financial: Project expenditure will be managed within available capital funding and the conditions of the CATF Grant Funding Agreement; land acquisition costs are met from the capital budget allocated to the project. Report 6.1, 7.4
  • Risk: The principal remaining risk is securing the required land interests; until formal legal agreements are concluded, the Council's ability to deliver the full scheme remains at risk, and delay could affect programme, costs, funding period and public confidence. Report 8.1, 8.3, 8.4
  • Legal: Land terms must reflect valuation and legal advice and the Council's duty to secure best value; compulsory purchase was considered and rejected as a route to progress. Report 5.1, 8.2
  • Equalities: An Equality Impact Assessment has been completed and its results taken into account in the recommendations. Report P31
  • Climate: The proposal has positive sustainability implications through improved walking and cycling infrastructure, supporting active travel and reduced reliance on the private car between Ormskirk and Burscough. Report 7.1
  • Staffing: Arcus Consulting has been appointed following a competitive process to provide professional services through to scheme delivery. Report 3.7, 6.2

Who and where

  • Residents and users of Ormskirk and Burscough who may use the new active travel route Report 2.2, 7.1
  • The primary private landowner holding a substantial and contiguous section of the route Report 3.2, 4.1
  • Vulnerable, deprived and disadvantaged communities between Ormskirk and Burscough, as identified in the health and wellbeing assessment Report 9.1

Timeline

  • 2013: West Lancashire Borough Council Local Plan sets out the aspiration for the Ormskirk to Burscough Linear Park
  • 2017: West Lancashire Borough Council Green Infrastructure and Cycling Strategy published
  • 2022: Section of the route completed by Taylor Wimpey as part of the Grove Farm housing development
  • September 2023: Cabinet approved £364,200 of CIL and S106 monies for part of the Linear Park Report 3.3
  • 2026-07-15: Council approved acceptance of the £332,802 CATF grant, delegated authority to build the scheme and to acquire land Report 2.1, 2.2, 2.3

Plain English for the jargon

  • CATF: Consolidated Active Travel Fund, a government grant stream for walking and cycling infrastructure
  • ATE: Active Travel England, the government body awarding the grant
  • CIL and S106: Community Infrastructure Levy and Section 106 planning obligations, developer contributions used to fund infrastructure
  • RIBA Stages 2 to 6: Royal Institute of British Architects work stages covering concept design through to construction and handover
  • Linear Park: A green corridor alongside the Ormskirk to Burscough railway line, including a shared cycle and pedestrian path
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35

Resolved

A. That the Director of Finance and Corporate Resources be given delegated authority to accept the Consolidated Active Travel Fund ( CATF ) grant of £0.332m, awarded by Active Travel England (ATE) and administered by Lancashire County Council, to support the delivery of the scheme detailed in the report. B. That the Director of Planning, Economy & Wellbeing be given delegated authority to take all necessary steps required to undertake the works as outlined in the report, including but not limited to the construction of the Linear Park Cycle Link east of Highgrove Park in Ormskirk to Abbey Lane in Burscough. C. That the Director of Finance and Corporate Resources, in discussion with the Leader, be given delegated authority to take all necessary steps to purchase any applicable land interest to enable the scheme to be brought forward, the cost of which shall be taken from the capital budget allocated to the project.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of the report

1.1To seek approval for the acceptance of Active Travel England grant funding of £332,802 from Lancashire County Council to enable the delivery of the Ormskirk to Burscough Linear Park.

1.2To approve a compensation payment to the landowners affected by the creation of the Ormskirk to Burscough Linear Park.

Recommendations

2.1That the Director of Finance and Resources be given delegated authority to accept the Consolidated Active Travel Fund (CATF) grant of £0.332m, awarded by Active Travel England (ATE) and administered by Lancashire County Council, to support the delivery of the scheme detailed in this report.

2.2That the Director of Planning, Economy & Wellbeing be given delegated authority to take all necessary steps required to undertake the works as outlined in this report, including but not limited to the construction of the Linear Park Cycle Link east of Highgrove Park in Ormskirk to Abbey Lane in Burscough.

2.3That the Director of Finance and Corporate Resources, in discussion with the Leader, be given delegated authority to take all necessary steps to purchase any applicable land interest to enable the scheme to be brought forward, the cost of which shall be taken from the capital budget allocated to the project.

3.0BACKGROUND 3.1 The Council aspires to deliver a Linear Park between Ormskirk and Burscough, and this is set out in the West Lancashire Borough Council Local Plan (2013) and the West Lancashire Borough Council Green Infrastructure and Cycling Strategy (2017). The route of the Ormskirk to Burscough Linear Park is an area of land which runs alongside the railway line between Ormskirk and Burscough and is partially constructed. A section of the route from Ormskirk to Burscough was completed by Taylor Wimpey in 2022 as part of the Grove Farm housing development.

3.2The land identified for the proposed Linear Park sits across a combination of Council-owned land and land in private ownership. While the Council has a degree of control over the areas within its ownership, a substantial and contiguous section of the site is held by a primary private landowner. As a result, the overall deliverability of the project is entirely dependent on securing agreement with this landowner in relation to the necessary land interests required to enable the scheme to be brought forward. These interests may include land acquisition, long- term lease arrangements, or the granting of easements or access rights, and appropriate compensation to the landowner will be required as part of any agreed arrangements.

3.3In September 2023, Cabinet approved the use of £364,200 of CIL and S106 monies towards the delivery of part of the Ormskirk to Burscough Linear Park, east of Highgrove Park in Ormskirk to Abbey Lane in Burscough.

3.4Additionally, UKSPF funding was allocated to appoint a design consultant, WSP Group, to produce a Feasibility Study to support delivery of this project and assist with the design of a safe cycle and pedestrian Linear Park Cycle Link between the existing cycleway/Linear Park path implemented by Taylor Wimpey and the road junction of Abbey Lane and Liverpool Road South. This Feasibility Study report appraised previously considered route options, further considered new route options and updated costings to help shape decisions in the concept design and spatial coordination stages of project development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1 DRAFT Grant AgreementAppendix 849 KB Download
PDF
App 2 EIAAppendix 144 KB Download
PDF
App 3 Ormskirk to Burscough Linear Park: Feasibility Study redactedAppendix 2.1 MB Download
PDF
Ormskirk to Burscough Linear Park Land Agreement and Active Travel England Grant FundingReport 155 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

41 of 56 attended
JI
Councillor Janet IngmanMayor, present
JH
Councillor John HowardDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
CR
Councillor Charles Robert BerryCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
AB
Councillor Aaron BodyCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
MJ
Councillor Michael John CromptonCommittee Member, present

All 56 on the meeting page

On this subject at West Lancashire

Search all
  1. Ormskirk to Burscough Linear Park Land Agreement and Active Travel England Grant FundingThis decision
  2. 2026/0080/FUL - The Hawthorns, 59 Crabtree Lane,Burscough, Ormskirk, Lancashire, L40 0RNAgreed
  3. Planning Application: 2023/0601/FUL - Bewicks Barn Tarlscough Lane Burscough Ormskirk Lancashire L40 0RJApproved
  4. Funding for the Ormskirk - Burscough Linear ParkApproved
  5. Funding for the Ormskirk - Burscough Linear ParkDecided
  6. 2023/0231/ful - martin mere, fish lane, burscough, ormskirkApproved

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open