Future Leisure Investment Programme Update

Noted Committee 4 papers

AI summaryWest Lancashire Council notes Skelmersdale leisure feasibility findings and Park Pool investment position, and grants the Director delegated authority to complete the detailed business case and further appraisal work using the remaining approved feasibility budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBusiness case and appraisal to proceed using remaining budget
Money£10.5 million CIL, £400,000 Park PoolStrategic CIL opportunity and Park Pool allocation
What happens nextCouncil report December 2026Combined leisure investment programme report due
Who it affectsSkemersdale and Park Pool usersSwimming and leisure services across the borough

What was decided

Members noted the findings of the Skelmersdale leisure feasibility study and the emerging position on future investment requirements at Park Pool. Report 3.1

The Director of Planning, Economy & Wellbeing received delegated authority to complete the detailed business case for future Skelmersdale leisure provision and to undertake further appraisal work on Park Pool investment options, using the remaining approved leisure feasibility budget. Report 3.2

Why

Both Nye Bevan Leisure Centre and Park Pool are ageing, require significant capital investment, and the combined operation requires a subsidy exceeding £1.18 million per annum. Report 4.1, 7.1

An October 2024 review found the previously approved leisure transformation programme could not be delivered within available funding, and a 2024 consultation received over 2,000 responses with 88.5% opposing closure of either facility.

The Skelmersdale feasibility work by Recreation Group identified more viable leisure propositions than previous options and confirmed that decisions on Park Pool and Skelmersdale investment are closely linked. Report 5.2, 5.9

What happens next

Officers will complete the detailed business case for future Skelmersdale leisure provision and undertake further appraisal of Park Pool investment options, using the remaining balance of the approved feasibility allocation. Report 6.1, 6.2, 7.6

A combined leisure investment report covering both facilities, funding options and Strategic CIL considerations will be presented to Council in December 2026. Report 6.5, 6.6, 7.8

Officers will continue to develop the detailed programme of works and formal Strategic Community Infrastructure Levy funding bid authorised by Council in February 2026. Report 5.8, 7.7

The money

  • £500,000 Reallocated in December 2025 from the existing leisure capital programme for feasibility, design and technical work Report 4.5
  • £100,000 Previously approved for feasibility, design and technical work Report 7.4
  • approximately £50,000 Used to date in completing the feasibility work, leaving a remaining balance Report 7.4
  • £400,000 Previously identified allocation for Park Pool essential repairs Report 5.6, 7.5
  • in excess of £1.18 million per annum Combined operating subsidy required for Park Pool and Nye Bevan Report 7.1
  • approximately £10.5 million Potential Strategic Community Infrastructure Levy funding for leisure Report 5.8, 7.7
  • up to £10.5 million Formal Strategic CIL funding bid authorised by Council in February 2026 Report 7.7

Options considered

  • Chosen: Complete the Skelmersdale detailed business case. Builds on substantially completed feasibility work to develop a robust evidence base for future decisions Report 3.2, 6.1, 6.2
  • Chosen: Undertake further appraisal of Park Pool investment options. Establish a comparable evidence base and assess whether a more comprehensive investment approach could deliver greater long-term value Report 3.2, 5.7, 6.4, 7.6
  • Rejected: Invest in Park Pool solely for compliance and operational resilience. Would support continued operation but would not materially alter the age, efficiency or long-term sustainability of the facility Report 5.7

Implications

  • Financial: Combined operation of Park Pool and Nye Bevan requires a subsidy exceeding £1.18 million per annum, with continued pressure on capital and revenue budgets from ageing infrastructure and reactive maintenance. Report 7.1, 7.2, 7.3
  • Financial: Approximately £10.5 million of Strategic Community Infrastructure Levy funding could support future leisure investment, but determining its most effective use requires further appraisal. Report 5.8, 7.7
  • Climate: Both facilities operate from ageing buildings with energy-intensive plant; a more comprehensive refurbishment at Park Pool or new Skelmersdale provision could improve energy efficiency and reduce future maintenance. Report 8.1, 8.2, 8.3
  • Risk: Both facilities continue to operate with ageing infrastructure, increasing the risk of unplanned failures and service disruption, with reputational risk from a lack of progress given strong public interest. Report 9.3, 9.5
  • Risk: Local Government Reorganisation means responsibility for leisure will transfer to successor arrangements, requiring investment strategy and project development to a delivery-ready stage. Report 9.4
  • Other: Continued operation of both facilities supports health, wellbeing, swimming provision and school curriculum access, with over 2,000 consultation respondents previously showing strong public support for retention. Report 10.1, 10.2

Who and where

  • Residents using Nye Bevan Leisure Centre and Park Pool in West Lancashire Report 4.1, 10.1
  • Schools, community groups and organised clubs relying on swimming provision Report 10.2
  • Skilmersdale residents, with feasibility work considering the Ingram and Glenburn sites Report 5.1
  • Council taxpayers, given the combined annual subsidy and capital investment pressures Report 7.1, 7.3

Timeline

  • October 2024: Council considered a review of the leisure estate identifying an affordability gap Report P51
  • October to December 2024: Consultation generated over 2,000 responses, with 88.5% opposing closure of either facility
  • February 2025: Council resolved to retain both facilities and established the cross-party Leisure Operations Working Group Report 4.3
  • December 2025: Council approved reallocation of £500,000 for feasibility, design and technical work, plus targeted Park Pool works Report 4.5
  • February 2026: Council approved further work on essential repairs, future investment and a Strategic CIL funding proposal Report 4.6, 7.7
  • December 2026: Combined leisure investment report to be presented to Council covering both facilities, funding and delivery Report 6.5, 6.6, 7.8

Plain English for the jargon

  • Strategic Community Infrastructure Levy (CIL): A local levy that councils can use to fund infrastructure to support development in their area.
  • Leisure Operations Working Group: A cross-party group set up by Council in February 2025 to review operational performance, subsidy levels, building condition and future investment options.
  • Essential Repairs Programme: The programme of works identified to address compliance, building condition and operational resilience issues at Park Pool.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37

Resolved

A. That the findings of the Skelmersdale leisure feasibility study and the emerging position regarding future investment requirements at Park Pool be noted. B. That the Director of Planning, Economy & Wellbeing be granted delegated authority to complete the detailed business case for future leisure provision in Skelmersdale and to undertake further appraisal work relating to future investment options at Park Pool, utilising the remaining approved leisure feasibility budget.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of the report

1.1To provide Members with an update on the feasibility work undertaken for future leisure provision in Skelmersdale, the emerging investment requirements identified at Park Pool and the development of future funding opportunities. The report seeks approval to continue the next phase of appraisal and business case work to inform future investment decisions across the Council’s leisure estate.

2.0RECOMMENDATIONS TO THE LEISURE WORKING GROUP

2.1The report be noted.

3.0RECOMMENDATIONS TO COUNCIL

3.1That the findings of the Skelmersdale leisure feasibility study and the emerging position regarding future investment requirements at Park Pool be noted.

3.2That the Director of Planning, Economy & Wellbeing be granted delegated authority to complete the detailed business case for future leisure provision in Skelmersdale and to undertake further appraisal work relating to future investment options at Park Pool, utilising the remaining approved leisure feasibility budget. 4.0 BACKGROUND

4.1The Council has been considering the future of its leisure estate for a number of years in response to the age, condition and operating costs associated with both Nye Bevan Leisure Centre and Park Pool. Previous reports have highlighted increasing maintenance requirements, growing revenue subsidy pressures and the need for significant future capital investment to ensure the continued provision of swimming and leisure services across the borough. 4.2 In October 2024, Council considered a review of the leisure estate which identified a significant affordability gap within the previously approved leisure transformation programme. The review concluded that the approved replacement schemes could not be delivered within the available funding envelope and that alternative approaches would need to be considered. Consultation undertaken between October and December 2024 generated over 2,000 responses, with 88.5% of respondents opposing the closure of either facility and highlighting the importance of swimming provision for residents, schools and community groups.

4.3In February 2025, Council resolved to retain both facilities in operation and requested further work to understand the investment requirements associated with maintaining services whilst developing longer-term solutions. A cross-party Leisure Operations Working Group was subsequently established to review operational performance, subsidy levels, building condition and future investment options.

4.4During 2025, the Working Group considered a range of evidence including strategic leisure advice, condition surveys, engineering assessments and financial modelling. This work confirmed that both facilities continue to play an important role within the borough’s leisure offer but also identified significant future investment requirements associated with ageing buildings, life-expired infrastructure and ongoing operating costs.

4.5In December 2025, Council approved the reallocation of £500,000 from the existing leisure capital programme to support feasibility, design and technical work relating to future leisure provision in Skelmersdale and to commission targeted works at Park Pool. Council further resolved that future proposals, associated costs, delivery routes and funding strategies should be brought back to Members before any planning submission or external funding application was made.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Skelmersdale Feasibility StudyAppendix 1 17 MB Download
PDF
Skelmersale Brief ExplorationAppendix 2 801 KB Download
PDF
Essential Repairs Programme of Required WorksAppendix 3 76 KB Download
PDF
Future Leisure Investment Programme UpdateReport 141 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

41 of 56 attended
JI
Councillor Janet IngmanMayor, present
JH
Councillor John HowardDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
CR
Councillor Charles Robert BerryCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
AB
Councillor Aaron BodyCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
MJ
Councillor Michael John CromptonCommittee Member, present

All 56 on the meeting page

On this subject at West Lancashire

Search all
  1. Future Leisure Investment Programme UpdateThis decision
  2. Future of Leisure: Feasibility Funding for Skelmersdale and OrmskirkApproved
  3. Future direction of the Wellbeing and Leisure ServiceNoted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open