Resolved (1) The assurance reviews and activities that had been undertaken in the last quarter be noted. (2) The committee was satisfied with the assurance activity April – August 2017. (3) The risk and assurance processes and reporting would be reviewed again once the WMCA leadership team was appointed be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
1. The report provides Members the views of WMCA’s Corporate Assurance Manager’s opinion on the Authority’s systems of Project & Programme Assurance and Business Assurance (including Risk Management, Internal Audit and Business Continuity & resilience) for this reporting period April 2017 – August 2017.
Background
2. The intention of the report is to summarise the assurance activity since the last reporting period and highlight any matters that are of concern that require further consideration or additional assurance activity.
3. Since the last update and supporting the transitional arrangements to WMCA, the Corporate Assurance team have continued to develop and refine appropriate assurance processes for the West Midlands Combined Authority. A brief summary of this activity is also provided in this report for note at this point in time.
Project & Programme Assurance
TfWM/ Corporate Services Minor Project Assurance Summary
4. A total of 20 project assurance reviews have been undertaken by the Corporate Assurance Team in this period. These projects follow the WMCA Gateway Project Methodology for minor projects. Of these, two reviews considered projects which are likely to be in excess of the £5m threshold normally applied to minor projects. These were Longbridge Park and Ride and University Station redevelopment. These projects are in the definition and planning stages and once in delivery a more detailed assurance review will be undertaken.
5. Of the 20 project assurance reviews undertaken since the last update, just under half were for new proposed projects to initiate some development activity (8/20). A similar proportion were undertaken to continue development activity to the next gateway stage (8/20). The assurance reviews recommended that all these proposed projects progress to the next gateway stage. There was no area of significant risk identified with these assurance reviews. A smaller number (3/20) of the project completed project delivery and captured lessons learned. Finally in accordance with established assurance criteria a Health Check review (1/20) was undertaken for a project which had fallen behind its delivery schedule.
6. In accordance with the position reported to the last meeting of this committee, there have been reviews on capital projects which are funded through the Integrated Transport Block approved in March 2017. The main focus of these has been managing the existing asset base with respect to replacement and, or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
7. As a consequence of the quarterly assurance, the project/programme governance arrangements for the Minor Works projects have also been reviewed and a recommendation report presented to the joint TfWM/ Corporate Services Board for consideration. The revised arrangements resulting from this review should strengthen both the assurance and governance arrangements for the minor works projects.
WMCA Investment Programme Major Project Assurance Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Risk & Assurance Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.